Pre-Inspection
|
6/25/2024
|
Approved
|
RAFAEL ESPINOZA
|
|
Special/Order Compliance
|
10/9/2024
|
Partial Inspection
|
RAFAEL ESPINOZA
|
|
Excavation/Setback/Form/Re-Bar
|
10/24/2024
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Footing/Foundation/Slab
|
10/24/2024
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Footing/Foundation/Slab
|
10/25/2024
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/2/2024
|
No Access for Inspection
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/3/2024
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/18/2024
|
Corrections Issued
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/26/2024
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/14/2025
|
Partial Approval
|
RAFAEL CORTES
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/31/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Interior/Exterior Lathing
|
1/31/2025
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Pre-Inspection
|
2/25/2025
|
Approved
|
RAFAEL CORTES
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/3/2025
|
Partial Approval
|
RAFAEL CORTES
|
|
Wall Anchors
|
3/3/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Insulation
|
3/7/2025
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Interior/Exterior Lathing
|
4/15/2025
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/29/2025
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
4/29/2025
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Green Building Rough
|
5/5/2025
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
5/5/2025
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Wood Frame
|
5/5/2025
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Green Building Rough
|
5/8/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Insulation
|
5/8/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Verify Sprinkler Sign Off
|
5/8/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Wood Frame
|
5/8/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Green Building Rough
|
5/21/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Verify Sprinkler Sign Off
|
5/21/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Wood Frame
|
5/21/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Insulation
|
6/17/2025
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Verify Sprinkler Sign Off
|
6/17/2025
|
Partial Inspection
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
6/17/2025
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/23/2025
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Green Building Rough
|
6/23/2025
|
Approved
|
RAFAEL ESPINOZA
|
|
Insulation
|
6/23/2025
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
6/23/2025
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/2/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
7/2/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
7/2/2025
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Insulation
|
7/7/2025
|
Partial Approval
|
LARRY ARNICK
|
|
Verify Sprinkler Sign Off
|
7/15/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Wood Frame
|
7/15/2025
|
Partial Approval
|
RAFAEL CORTES
|
|
Insulation
|
7/18/2025
|
Partial Approval
|
RAFAEL CORTES
|
|
Drywall Nailing
|
7/21/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Drywall Nailing
|
7/29/2025
|
Partial Approval
|
JOEY BUCHANAN
|
|
Drywall Nailing
|
8/6/2025
|
Partial Approval
|
RAFAEL CORTES
|
|
Drywall Nailing
|
8/12/2025
|
Partial Approval
|
RAFAEL CORTES
|
|
Light Gage Steel Frame
|
9/11/2025
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Light Gage Steel Frame
|
9/23/2025
|
Partial Approval
|
JOEY BUCHANAN
|
|
Drywall Nailing
|
10/7/2025
|
Approved
|
JOEY BUCHANAN
|
|
Final
|
1/9/2026
|
Corrections Issued
|
RAFAEL ESPINOZA
|
|
Footing/Foundation/Slab
|
1/9/2026
|
Approved
|
RAFAEL ESPINOZA
|
|
Green Building Final
|
1/9/2026
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
SGSOV-Seismic Gas S/O Valve
|
1/9/2026
|
SGSOV Not Ready
|
RAFAEL ESPINOZA
|
|
Smoke Detectors
|
1/9/2026
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Verify Sprinkler Sign Off
|
1/9/2026
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
1/9/2026
|
Not Ready for Inspection
|
RAFAEL ESPINOZA
|
|
Green Building Final
|
1/15/2026
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
SGSOV-Seismic Gas S/O Valve
|
1/15/2026
|
SGSOV Not Ready
|
RAFAEL CORTES
|
|
Smoke Detectors
|
1/15/2026
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Special/Order Compliance
|
1/15/2026
|
Approved
|
RAFAEL CORTES
|
|
Verify Sprinkler Sign Off
|
1/15/2026
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Wood Frame
|
1/15/2026
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Final
|
2/4/2026
|
Corrections Issued
|
RAFAEL ESPINOZA
|
|
Green Building Final
|
2/4/2026
|
Approved
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
2/4/2026
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Final
|
2/12/2026
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
SGSOV-Seismic Gas S/O Valve
|
2/12/2026
|
SGSOV Not Ready
|
RAFAEL CORTES
|
|
Smoke Detectors
|
2/12/2026
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Verify Sprinkler Sign Off
|
2/12/2026
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Wood Frame
|
2/12/2026
|
No Access for Inspection
|
RAFAEL CORTES
|
|
Final
|
2/18/2026
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
SGSOV-Seismic Gas S/O Valve
|
2/18/2026
|
SGSOV Not Ready
|
RAFAEL CORTES
|
|
Smoke Detectors
|
2/18/2026
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Verify Sprinkler Sign Off
|
2/18/2026
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
Wood Frame
|
2/18/2026
|
Not Ready for Inspection
|
RAFAEL CORTES
|
|
SGSOV-Seismic Gas S/O Valve
|
2/25/2026
|
SGSOV No Gas
|
RAFAEL ESPINOZA
|
|
Final
|
3/19/2026
|
Partial Inspection
|
RAFAEL ESPINOZA
|
|
Smoke Detectors
|
3/19/2026
|
Approved
|
RAFAEL ESPINOZA
|
|
Verify Sprinkler Sign Off
|
3/19/2026
|
Approved
|
RAFAEL ESPINOZA
|
|
Wood Frame
|
3/19/2026
|
Approved
|
RAFAEL ESPINOZA
|
|
Final
|
3/27/2026
|
Partial Inspection
|
RAFAEL ESPINOZA
|
|
Final
|
4/1/2026
|
OK to Issue CofO
|
RAFAEL ESPINOZA
|