3517 S ROSEWOOD AVE 90066

Certificate Information: 3517 S ROSEWOOD AVE 90066

Application / Permit
23010-10000-02674
Plan Check / Job No.
B23LA11776
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
(N) DETACHED GARAGE
Permit Issued
Issued on 10/25/2023
Issuing Office
Metro
Current Status
CofO Issued on 10/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/26/2023 APPLICANT
Assigned to Plan Check Engineer 7/13/2023 DANIEL YIP
Corrections Issued 7/21/2023 DANIEL YIP
Quality Review Completed 7/25/2023 KEN GILL
Building Plans Picked Up 7/28/2023 APPLICANT
Applicant returned to address corrections 9/21/2023 DANIEL YIP
Plan Check Approved 10/25/2023 DANIEL YIP
Issued 10/25/2023 APPLICANT
CofO in Progress 10/22/2024 JESUS PINEDA
CofO Issued 10/22/2024 RICHARD STEINBACH
Permit Finaled 10/22/2024 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/2/2023 JASON NG
Specific Plan Cleared 8/3/2023 FREDDY GARCIA
Low Impact Development (LID) Cleared 8/14/2023 TOMMY YIN
Roof/Waste drainage to street Cleared 8/30/2023 JASON NG
GPI Written Notices Cleared 9/25/2023 DANIEL YIP
Grading Pre-Inspection Cleared 9/25/2023 DANIEL YIP
Construction near power lines Cleared 10/2/2023 RIDWAN HARDY

Contact Information

Architect Rezvani,, Farbod; Lic. No.: C32315 9055 ALCOTT STREET #1      LOS ANGELES, CA 90035
Contractor Di Nalli Construction; Lic. No.: 942979-B 9055 ALCOTT STREET #1      LOS ANGELES, CA 90035
Engineer Askarian,, Soroosh; Lic. No.: C83413 22287 MULHOLLAND HWY 163      CALABASAS, CA 91302

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/3/2023 Partial Approval HERBERT GIRON
Excavation/Setback/Form/Re-Bar 11/29/2023 Not Ready for Inspection JESUS RODRIGUEZ
Footing/Foundation/Slab 12/7/2023 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 12/15/2023 Conditional Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 1/29/2024 Corrections Issued JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 1/30/2024 Conditional Approval JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 2/12/2024 Approved HERBERT GIRON
Footing/Foundation/Slab 2/12/2024 Approved HERBERT GIRON
Interior/Exterior Lathing 2/12/2024 Not Ready for Inspection HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 2/15/2024 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 2/15/2024 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 2/23/2024 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 2/26/2024 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 2/29/2024 Approved JESUS RODRIGUEZ
Green Building Rough 2/29/2024 Approved JESUS RODRIGUEZ
Insulation 3/12/2024 Approved JESUS RODRIGUEZ
Drywall Nailing 3/15/2024 Approved HERBERT GIRON
Interior/Exterior Lathing 4/9/2024 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 10/2/2024 Approved JESUS PINEDA
Final 10/18/2024 OK to Issue CofO JESUS PINEDA
Green Building Final 10/18/2024 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 10/18/2024 SGSOV Approved JESUS PINEDA
Service/Power Release 10/18/2024 Not Required JESUS PINEDA
Smoke Detectors 10/18/2024 Approved JESUS PINEDA