3517 S ROSEWOOD AVE 90066
Certificate Information: 3517 S ROSEWOOD AVE 90066
- Application / Permit
- 23010-10000-02674
- Plan Check / Job No.
- B23LA11776
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- (N) DETACHED GARAGE
- Permit Issued
- Issued on 10/25/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/26/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/13/2023 | DANIEL YIP |
| Corrections Issued | 7/21/2023 | DANIEL YIP |
| Quality Review Completed | 7/25/2023 | KEN GILL |
| Building Plans Picked Up | 7/28/2023 | APPLICANT |
| Applicant returned to address corrections | 9/21/2023 | DANIEL YIP |
| Plan Check Approved | 10/25/2023 | DANIEL YIP |
| Issued | 10/25/2023 | APPLICANT |
| CofO in Progress | 10/22/2024 | JESUS PINEDA |
| CofO Issued | 10/22/2024 | RICHARD STEINBACH |
| Permit Finaled | 10/22/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/2/2023 | JASON NG |
| Specific Plan | Cleared | 8/3/2023 | FREDDY GARCIA |
| Low Impact Development (LID) | Cleared | 8/14/2023 | TOMMY YIN |
| Roof/Waste drainage to street | Cleared | 8/30/2023 | JASON NG |
| GPI Written Notices | Cleared | 9/25/2023 | DANIEL YIP |
| Grading Pre-Inspection | Cleared | 9/25/2023 | DANIEL YIP |
| Construction near power lines | Cleared | 10/2/2023 | RIDWAN HARDY |
Contact Information
| Architect | Rezvani,, Farbod; Lic. No.: C32315 | 9055 ALCOTT STREET #1 LOS ANGELES, CA 90035 |
| Contractor | Di Nalli Construction; Lic. No.: 942979-B | 9055 ALCOTT STREET #1 LOS ANGELES, CA 90035 |
| Engineer | Askarian,, Soroosh; Lic. No.: C83413 | 22287 MULHOLLAND HWY 163 CALABASAS, CA 91302 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/3/2023 | Partial Approval | HERBERT GIRON |
| Excavation/Setback/Form/Re-Bar | 11/29/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 12/7/2023 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 12/15/2023 | Conditional Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/29/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/30/2024 | Conditional Approval | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 2/12/2024 | Approved | HERBERT GIRON |
| Footing/Foundation/Slab | 2/12/2024 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 2/12/2024 | Not Ready for Inspection | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 2/15/2024 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 2/15/2024 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 2/23/2024 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 2/26/2024 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 2/29/2024 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 2/29/2024 | Approved | JESUS RODRIGUEZ |
| Insulation | 3/12/2024 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 3/15/2024 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 4/9/2024 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 10/2/2024 | Approved | JESUS PINEDA |
| Final | 10/18/2024 | OK to Issue CofO | JESUS PINEDA |
| Green Building Final | 10/18/2024 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 10/18/2024 | SGSOV Approved | JESUS PINEDA |
| Service/Power Release | 10/18/2024 | Not Required | JESUS PINEDA |
| Smoke Detectors | 10/18/2024 | Approved | JESUS PINEDA |