8843 W CASHIO ST 90035
Certificate Information: 8843 W CASHIO ST 90035
- Application / Permit
- 23010-10000-02616
- Plan Check / Job No.
- B23LA11516
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2 STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE AND ROOF DECK. NFPA 13D Sprinklers throughout
- Permit Issued
- Issued on 10/30/2023
- Issuing Office
- Current Status
- CofO Issued on 7/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/6/2023 | RACHEL BEYENE |
| Corrections Issued | 7/13/2023 | RACHEL BEYENE |
| Quality Review Completed | 8/4/2023 | KEN GILL |
| Building Plans Picked Up | 8/7/2023 | APPLICANT |
| Applicant returned to address corrections | 10/2/2023 | RACHEL BEYENE |
| Plan Check Approved | 10/24/2023 | RAHEL BEYENE |
| Issued | 10/30/2023 | APPLICANT |
| CofO in Progress | 7/11/2024 | MEL KHACHATOURIAN |
| Permit Finaled | 7/12/2024 | DANIEL ORRANTE |
| CofO Issued | 7/12/2024 | DANIEL ORRANTE |
| Permit Finaled | 7/12/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/21/2023 | HUGO LOPEZ |
| Sewer availability | Cleared | 8/21/2023 | HUGO LOPEZ |
| Low Impact Development (LID) | Cleared | 9/6/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 9/10/2023 | AHMED AMARRAGY |
| Hydrant and Access approval | Cleared | 9/15/2023 | KURT CORRAL |
| Permit | Cleared | 10/3/2023 | AHMED AMARRAGY |
Contact Information
| Architect | Rezvani,, Farbod; Lic. No.: C32315 | 9055 ALCOTT STREET #1 LOS ANGELES, CA 90035 |
| Contractor | Di Nalli Construction; Lic. No.: 942979-B | 9055 ALCOTT STREET #1 LOS ANGELES, CA 90035 |
| Engineer | Askarian,, Soroosh; Lic. No.: C83413 | 22287 MULHOLLAND HWY 163 CALABASAS, CA 91302 |
| Engineer | Nester,, Melvin Russell; Lic. No.: C26324 | 2902 TYLER CT SIMI VALLEY, CA 93063 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/1/2023 | Partial Approval | KENNETH NAGLE |
| METHANE-Subgrade | 11/7/2023 | Approved | MEL KHACHATOURIAN |
| Deputy Methane Barrier | 11/9/2023 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 11/15/2023 | Approved | MEL KHACHATOURIAN |
| METHANE-Barrier | 11/15/2023 | Approved | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/29/2023 | Partial Approval | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2023 | Partial Approval | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/7/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Deputy Wood Construction | 1/4/2024 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 1/8/2024 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 1/26/2024 | Corrections Issued | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 2/7/2024 | Partial Approval | MEL KHACHATOURIAN |
| HVAC-Rough | 2/7/2024 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Rough | 2/7/2024 | Approved | MEL KHACHATOURIAN |
| Shower Pan | 2/7/2024 | Approved | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 2/9/2024 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 2/9/2024 | Approved | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 2/12/2024 | Approved | MEL KHACHATOURIAN |
| Green Building Rough | 2/12/2024 | Approved | MEL KHACHATOURIAN |
| METHANE-Rough | 2/12/2024 | Approved | MEL KHACHATOURIAN |
| Verify Sprinkler Sign Off | 2/12/2024 | Approved | MEL KHACHATOURIAN |
| Insulation | 2/21/2024 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 2/26/2024 | Approved | MEL KHACHATOURIAN |
| Excavation/Setback/Form/Re-Bar | 5/23/2024 | Approved | MEL KHACHATOURIAN |
| Gas Test | 6/3/2024 | Approved | MEL KHACHATOURIAN |
| HVAC-Final | 6/3/2024 | Partial Approval | MEL KHACHATOURIAN |
| ELECTRICAL-Final | 6/11/2024 | Approved | MEL KHACHATOURIAN |
| HVAC-Final | 6/11/2024 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Final | 6/11/2024 | Approved | MEL KHACHATOURIAN |
| Final | 7/10/2024 | OK to Issue CofO | MEL KHACHATOURIAN |
| Green Building Final | 7/10/2024 | Approved | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 7/10/2024 | SGSOV Approved | MEL KHACHATOURIAN |
| Service/Power Release | 7/10/2024 | Approved | MEL KHACHATOURIAN |
| Smoke Detectors | 7/10/2024 | Approved | MEL KHACHATOURIAN |