- Work Description
- ePlan CONVERSTION OF (E) DETACHED GARAGE TO AN ADU WITH A 2ND STORY ADDITION AND GROUND FLOOR STORAGE. DETACHED ADU PER LAMC 12.22 (c) and (d).
- Permit Issued
- Issued on 4/8/2025
- Issuing Office
- Current Status
- Issued on 4/8/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/23/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/13/2023 | ADRIANA LOPEZ |
| Corrections Issued | 7/24/2023 | ADRIANA LOPEZ |
| Quality Review Completed | 8/8/2023 | FARUK SEZER |
| Applicant returned to address corrections | 12/3/2024 | ADRIANA LOPEZ |
| Applicant returned to address corrections | 2/28/2025 | ADRIANA LOPEZ |
| Plan Check Approved | 4/7/2025 | ADRIANA LOPEZ |
| Issued | 4/8/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 4/24/2024 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 4/30/2024 | WALLIE JONG |
| Sewer availability | Cleared | 4/30/2024 | WALLIE JONG |
| Construction near power lines | Cleared | 8/28/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 8/28/2024 | RIDWAN HARDY |
| Low Impact Development (LID) | Cleared | 11/7/2024 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 11/14/2024 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21731 VENTURA BLVD SUITE 110 WOODLAND HILLS, CA 91364 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/4/2025 | Corrections Issued | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 11/19/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| METHANE-Barrier | 11/19/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| METHANE-Subgrade | 11/19/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| Pre-Inspection | 5/5/2026 | Corrections Issued | SCOTT FINNILA |
| METHANE-Subgrade | 5/18/2026 | Partial Approval | CRAIG VAUGHAN |
| PLUMBING-Rough | 5/18/2026 | Partial Approval | CRAIG VAUGHAN |