10000 W PICO BLVD BLDG 1b 90064
Certificate Information: 10000 W PICO BLVD BLDG 1b 90064
- Application / Permit
- 23010-10000-02601
- Plan Check / Job No.
- B23LA11462
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- ePlan: (N) DETACHED COMFORT STRUCTURE INCLUDING KITCHEN PREP AREA W/ COVERED PATIO, RESTROOM AND OFFICE. (BLDG 1)
- Permit Issued
- Issued on 2/22/2024
- Issuing Office
- Current Status
- CofO Issued on 12/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/21/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/22/2023 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 6/27/2023 | FARSHAD ALIMOHAMADI |
| Quality Review Completed | 6/29/2023 | TU HUA |
| Applicant returned to address corrections | 7/28/2023 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 7/31/2023 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 9/13/2023 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 9/24/2023 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 11/6/2023 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 11/7/2023 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 11/24/2023 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 12/4/2023 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 12/5/2023 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 12/19/2023 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 12/21/2023 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 1/1/2024 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 1/2/2024 | FARSHAD ALIMOHAMADI |
| Issued | 2/22/2024 | APPLICANT |
| CofO in Progress | 12/24/2025 | PAUL DAVIDSON |
| Permit Finaled | 12/29/2025 | HENRY BAGHDASSARIAN |
| CofO Issued | 12/29/2025 | HENRY BAGHDASSARIAN |
| Permit Finaled | 12/29/2025 | HENRY BAGHDASSARIAN |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 6/23/2023 | FARSHAD ALIMOHAMADI |
| Address approval | Cleared | 6/29/2023 | JASON NG |
| Sewer availability | Cleared | 6/29/2023 | JASON NG |
| Eng Process Fee Ord 176,300 | Cleared | 6/30/2023 | JASON NG |
| Abandoned oil well | Cleared | 8/18/2023 | GILBERT URREA |
| Hydrant and Access approval | Cleared | 8/18/2023 | GILBERT URREA |
| Low Impact Development (LID) | Cleared | 9/6/2023 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 9/8/2023 | JASON NG |
| Fire Marshal Fire Life Safety | Cleared | 9/12/2023 | MENOA AGHAJANI |
| Specific Plan | Cleared | 9/19/2023 | ALESSANDRO MERCURI |
| Food Service Establishment | Cleared | 9/26/2023 | KENNETH BROWNE |
| Miscellaneous | Cleared | 9/26/2023 | RUBEN VASQUEZ |
| ZA Case | Cleared | 9/26/2023 | RUBEN VASQUEZ |
| DAS Clearance | Cleared | 10/5/2023 | Ricardo Ramirez Solis |
| GPI Written Notices | Cleared | 11/7/2023 | FARSHAD ALIMOHAMADI |
| Green Code | Cleared | 11/27/2023 | Ricardo Ramirez Solis |
| Food establishment approval | Cleared | 12/22/2023 | LACDHS APPROVED |
Contact Information
| Architect | Hawkins,, Eric Shea; Lic. No.: NA36205 | , |
| Contractor | Refined Construction; Lic. No.: 925393-B | , |
| Engineer | Zangoli,, Fabio; Lic. No.: S6191 | 13245 FIJI WY UNIT J MARINA DEL REY, CA 90292 |
Inspector Information
| PAUL DAVIDSON, (310) 914-3914 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/8/2024 | Not Ready for Inspection | PAUL DAVIDSON |
| Piling/Pier/Caisson | 3/8/2024 | Not Ready for Inspection | PAUL DAVIDSON |
| Pre-Inspection | 3/8/2024 | Partial Inspection | PAUL DAVIDSON |
| Piling/Pier/Caisson | 3/12/2024 | Partial Approval | PAUL DAVIDSON |
| Excavation/Setback/Form/Re-Bar | 3/13/2024 | Partial Approval | PAUL DAVIDSON |
| Piling/Pier/Caisson | 3/13/2024 | Partial Approval | PAUL DAVIDSON |
| Deputy Reinf. Concrete | 3/14/2024 | Conditional Approval | PAUL DAVIDSON |
| Excavation/Setback/Form/Re-Bar | 3/15/2024 | Partial Approval | PAUL DAVIDSON |
| Piling/Pier/Caisson | 3/15/2024 | Partial Approval | PAUL DAVIDSON |
| Deputy Reinf. Concrete | 3/18/2024 | Conditional Approval | PAUL DAVIDSON |
| Deputy Reinf. Concrete | 4/29/2024 | Conditional Approval | PAUL DAVIDSON |
| Footing/Foundation/Slab | 5/1/2024 | Conditional Approval | PAUL DAVIDSON |
| METHANE-Barrier | 5/1/2024 | Not Ready for Inspection | PAUL DAVIDSON |
| METHANE-Subgrade | 5/1/2024 | Approved | PAUL DAVIDSON |
| Deputy Reinf. Concrete | 6/5/2024 | Conditional Approval | PAUL DAVIDSON |
| Deputy Reinf. Concrete | 6/7/2024 | Conditional Approval | PAUL DAVIDSON |
| Deputy Reinf. Concrete | 6/14/2024 | Conditional Approval | PAUL DAVIDSON |
| Deputy Reinf. Concrete | 6/21/2024 | Conditional Approval | PAUL DAVIDSON |
| Footing/Foundation/Slab | 6/21/2024 | Partial Approval | PAUL DAVIDSON |
| METHANE-Barrier | 6/21/2024 | Not Ready for Inspection | PAUL DAVIDSON |
| Deputy Reinf. Concrete | 7/2/2024 | Conditional Approval | PAUL DAVIDSON |
| Deputy Methane Barrier | 7/11/2024 | Conditional Approval | PAUL DAVIDSON |
| Deputy Reinf. Concrete | 7/11/2024 | Conditional Approval | PAUL DAVIDSON |
| Deputy Reinf. Concrete | 7/18/2024 | Conditional Approval | PAUL DAVIDSON |
| Deputy Reinf. Concrete | 7/19/2024 | Conditional Approval | PAUL DAVIDSON |
| Excavation/Setback/Form/Re-Bar | 7/19/2024 | Partial Approval | PAUL DAVIDSON |
| Footing/Foundation/Slab | 7/19/2024 | Partial Approval | PAUL DAVIDSON |
| METHANE-Barrier | 7/19/2024 | Partial Approval | PAUL DAVIDSON |
| Deputy Steel/Welding | 7/26/2024 | Conditional Approval | PAUL DAVIDSON |
| Excavation/Setback/Form/Re-Bar | 8/9/2024 | Not Ready for Inspection | PAUL DAVIDSON |
| Deputy Reinf. Concrete | 8/12/2024 | Conditional Approval | PAUL DAVIDSON |
| Deputy Drilled-In Anchors | 8/20/2024 | Conditional Approval | PAUL DAVIDSON |
| Excavation/Setback/Form/Re-Bar | 8/22/2024 | Partial Approval | PAUL DAVIDSON |
| METHANE-Final | 8/22/2024 | Partial Approval | PAUL DAVIDSON |
| Deputy Reinf. Concrete | 8/23/2024 | Conditional Approval | PAUL DAVIDSON |
| Deputy Steel/Welding | 8/27/2024 | Conditional Approval | DAVID TSAU |
| Green Building Rough | 9/18/2024 | Not Ready for Inspection | DANIEL VARNUM |
| METHANE-Rough | 9/18/2024 | Not Ready for Inspection | DANIEL VARNUM |
| Verify Sprinkler Sign Off | 9/18/2024 | Not Ready for Inspection | DANIEL VARNUM |
| Wood Frame | 9/18/2024 | Not Ready for Inspection | DANIEL VARNUM |
| Floor/Roof Diaphrgm/Shear Wall | 9/23/2024 | Not Ready for Inspection | DANIEL VARNUM |
| Green Building Rough | 9/23/2024 | Not Ready for Inspection | DANIEL VARNUM |
| METHANE-Rough | 9/23/2024 | Not Ready for Inspection | DANIEL VARNUM |
| Verify Sprinkler Sign Off | 9/23/2024 | Not Ready for Inspection | DANIEL VARNUM |
| Wall Anchors | 9/23/2024 | Corrections Issued | DANIEL VARNUM |
| Wood Frame | 9/23/2024 | Not Ready for Inspection | DANIEL VARNUM |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2024 | Partial Approval | DANIEL VARNUM |
| Wall Anchors | 9/25/2024 | Not Ready for Inspection | DANIEL VARNUM |
| Green Building Rough | 10/3/2024 | Not Ready for Inspection | DANIEL VARNUM |
| METHANE-Rough | 10/3/2024 | Not Ready for Inspection | DANIEL VARNUM |
| Verify Sprinkler Sign Off | 10/3/2024 | Not Ready for Inspection | DANIEL VARNUM |
| Wood Frame | 10/3/2024 | Not Ready for Inspection | DANIEL VARNUM |
| Interior/Exterior Lathing | 10/16/2024 | Partial Approval | DANIEL VARNUM |
| Green Building Rough | 11/21/2024 | Approved | PAUL DAVIDSON |
| METHANE-Rough | 11/21/2024 | Approved | PAUL DAVIDSON |
| Verify Sprinkler Sign Off | 11/21/2024 | Not Ready for Inspection | PAUL DAVIDSON |
| Wood Frame | 11/21/2024 | Not Ready for Inspection | PAUL DAVIDSON |
| Verify Sprinkler Sign Off | 11/27/2024 | Not Ready for Inspection | DANIEL VARNUM |
| Wall Anchors | 11/27/2024 | Approved | DANIEL VARNUM |
| Wood Frame | 11/27/2024 | Partial Approval | DANIEL VARNUM |
| Insulation | 12/11/2024 | Partial Approval | PAUL DAVIDSON |
| Insulation | 12/17/2024 | Approved | DANIEL VARNUM |
| Drywall Nailing | 2/12/2025 | Approved | PAUL DAVIDSON |
| Drywall Nailing | 2/26/2025 | Approved | DANIEL VARNUM |
| T-Bar Ceiling | 5/8/2025 | Partial Approval | DANIEL VARNUM |
| T-Bar Ceiling | 8/6/2025 | Conditional Approval | PAUL DAVIDSON |
| Final | 10/2/2025 | Not Ready for Inspection | DANIEL VARNUM |
| Footing/Foundation/Slab | 10/2/2025 | Partial Inspection | DANIEL VARNUM |
| Green Building Final | 10/2/2025 | Not Ready for Inspection | DANIEL VARNUM |
| METHANE-Barrier | 10/2/2025 | Not Ready for Inspection | DANIEL VARNUM |
| Pre-Inspection | 10/2/2025 | Not Ready for Inspection | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 10/2/2025 | SGSOV Approved | DANIEL VARNUM |
| Smoke Detectors | 10/2/2025 | Not Ready for Inspection | DANIEL VARNUM |
| Verify Sprinkler Sign Off | 10/2/2025 | Not Ready for Inspection | DANIEL VARNUM |
| Wood Frame | 10/2/2025 | Partial Inspection | DANIEL VARNUM |
| Final | 11/3/2025 | Not Ready for Inspection | DERRICK SPENCER |
| Footing/Foundation/Slab | 11/3/2025 | Approved | DERRICK SPENCER |
| Green Building Final | 11/3/2025 | Approved | DERRICK SPENCER |
| METHANE-Barrier | 11/3/2025 | Approved | DERRICK SPENCER |
| Pre-Inspection | 11/3/2025 | Approved | DERRICK SPENCER |
| Smoke Detectors | 11/3/2025 | Approved | DERRICK SPENCER |
| Verify Sprinkler Sign Off | 11/3/2025 | Approved | DERRICK SPENCER |
| Wood Frame | 11/3/2025 | Approved | DERRICK SPENCER |
| Final | 11/26/2025 | Not Ready for Inspection | PAUL DAVIDSON |
| Pre-Inspection | 12/5/2025 | Partial Inspection | PAUL DAVIDSON |
| Pre-Inspection | 12/8/2025 | Not Ready for Inspection | PAUL DAVIDSON |
| Pre-Inspection | 12/12/2025 | Not Ready for Inspection | PAUL DAVIDSON |
| Pre-Inspection | 12/16/2025 | Not Ready for Inspection | PAUL DAVIDSON |
| Pre-Inspection | 12/19/2025 | Partial Inspection | PAUL DAVIDSON |
| Final | 12/24/2025 | OK to Issue CofO | PAUL DAVIDSON |