906-906 1/2 E 50TH ST 90011
Certificate Information: 906-906 1/2 E 50TH ST 90011
- Application / Permit
- 23010-10000-02571
- Plan Check / Job No.
- B23LA11346
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2-UNIT 1-STORY ACCESSORY DWELLING UNITS PER GCS 65852.2(e)(1)(D) AND LAMC 12.22 A.33(c)(d) AND (g).
- Permit Issued
- Issued on 1/8/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 7/6/2023 | KHEDER ALRAZAA |
| Corrections Issued | 7/10/2023 | KHEDER ALRAZAA |
| Disabled Access Plans Picked Up | 7/19/2023 | APPLICANT |
| Quality Review Completed | 7/20/2023 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 7/24/2023 | APPLICANT |
| Applicant returned to address corrections | 1/3/2024 | JOHNNY WU |
| Plan Check Approved | 1/3/2024 | JOHNNY WU |
| Issued | 1/8/2024 | APPLICANT |
| CofO in Progress | 4/16/2025 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 4/17/2025 | DEROLD HAUFF |
| CofO Issued | 4/17/2025 | DEROLD HAUFF |
| Permit Finaled | 4/17/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/27/2023 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 7/28/2023 | ERIK BEASLEY |
| Sewer availability | Cleared | 7/28/2023 | ERIK BEASLEY |
| Hydrant and Access approval | Cleared | 9/1/2023 | JOHN CONNEALLY |
| Low Impact Development (LID) | Cleared | 11/2/2023 | MELINEH AGHAKHABIAN |
| DAS Clearance | Cleared | 11/3/2023 | SHINE LIN |
| Roof/Waste drainage to street | Cleared | 12/13/2023 | JUSTIN BICOL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kim,, Hong Kook; Lic. No.: C64529 | 3600 WILSHIRE BLVD STE 1903 LOS ANGELES, CA 90010 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/26/2024 | Corrections Issued | CRAIG DAVIS |
| Footing/Foundation/Slab | 4/1/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 4/4/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 4/4/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 8/20/2024 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 9/13/2024 | No Access for Inspection | WILLIAM SIERRA |
| BUILDING-Rough-Frame | 9/17/2024 | Partial Approval | WILLIAM SIERRA |
| Sewer | 9/17/2024 | Corrections Issued | WILLIAM SIERRA |
| Underground Mechanical | 9/17/2024 | Approved | WILLIAM SIERRA |
| Insulation | 9/19/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 9/23/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 10/28/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 10/28/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 10/28/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 10/31/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 10/31/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 10/31/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 10/31/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 10/31/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 11/5/2024 | Not Ready for Inspection | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 11/5/2024 | Partial Approval | JOHN QUINTANILLA |
| Green Building Rough | 11/5/2024 | Not Ready for Inspection | JOHN QUINTANILLA |
| HVAC-Rough | 11/5/2024 | Not Ready for Inspection | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 11/5/2024 | Approved | JOHN QUINTANILLA |
| PLUMBING-Rough | 11/5/2024 | Partial Approval | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 11/7/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 11/7/2024 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 11/7/2024 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 11/15/2024 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 11/15/2024 | Approved | ALEJANDRO DE ARTOLA |
| Deputy Drilled-In Anchors | 11/18/2024 | Conditional Approval | JOSH MEISTER |
| Drywall Nailing | 11/20/2024 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 11/20/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 11/25/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 2/26/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 2/26/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 2/26/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 2/26/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 2/26/2025 | SGSOV Not Required | ALEJANDRO DE ARTOLA |
| HVAC-Final | 2/27/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 2/27/2025 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 3/6/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 3/6/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 3/6/2025 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 3/6/2025 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 3/6/2025 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 3/6/2025 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 4/15/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 4/15/2025 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| Service/Power Release | 4/15/2025 | Approved | ALEJANDRO DE ARTOLA |