11354 W VICTORIA AVE 90066

Certificate Information: 11354 W VICTORIA AVE 90066

Application / Permit
23010-10000-02550
Plan Check / Job No.
B23LA11272
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New two story single family dwelling with attached garage
Permit Issued
Issued on 11/15/2023
Issuing Office
Current Status
CofO Issued on 4/3/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/20/2023 APPLICANT
Assigned to Plan Check Engineer 7/6/2023 JOE VO
Corrections Issued 7/13/2023 JOE VO
Quality Review Completed 7/13/2023 GARO TELMI
Applicant returned to address corrections 9/8/2023 JOE VO
Plan Check Approved 10/19/2023 JOE VO
Issued 11/15/2023 APPLICANT
CofO in Progress 3/31/2026 DAVID FEILER
Permit Finaled 4/3/2026 RICHARD STEINBACH
Permit Finaled 4/3/2026 RICHARD STEINBACH
CofO Issued 4/3/2026 RICHARD STEINBACH

Permit Application Clearance Information

Permit Cleared 7/24/2023 JASON NG
Eng Process Fee Ord 176,300 Cleared 7/25/2023 DARIN LAM
Sewer availability Cleared 7/25/2023 DARIN LAM
Construction near power lines Cleared 8/10/2023 RIDWAN HARDY
Specific Plan Cleared 8/17/2023 FREDDY GARCIA
Hydrant and Access approval Cleared 8/30/2023 LAVEON RIDER
Low Impact Development (LID) Cleared 9/22/2023 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 9/22/2023 AHMED AMARRAGY
Grading Pre-Inspection Cleared 10/19/2023 JOE VO

Contact Information

Architect Hamilton,, John Patrick; Lic. No.: NA28865       ,
Contractor Pagan Robert M Construction Company; Lic. No.: 509594-B       ,
Engineer Tuchscher,, James Todd; Lic. No.: NA77649       ,

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Grading Pre-Inspection 11/22/2023 Corrections Issued MICHAEL PELHAM
Footing/Foundation/Slab 1/30/2024 Corrections Issued JESUS PINEDA
PLUMBING-Rough 3/19/2024 Partial Approval JESUS PINEDA
Sewer 3/19/2024 Approved JESUS PINEDA
Footing/Foundation/Slab 4/4/2024 Approved TEMISTOCLES CAAL
Sewer 4/29/2024 Corrections Issued JESUS PINEDA
Sewer 4/30/2024 Partial Inspection JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 5/30/2024 Corrections Issued JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 8/5/2024 Corrections Issued JESUS PINEDA
Deputy Wood Construction 8/6/2024 Conditional Approval JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 8/20/2024 Approved DANIEL VERA
Special/Order Compliance 8/20/2024 Partial Inspection MICHAEL PELHAM
ELECTRICAL-Final 12/27/2024 Corrections Issued KIRK SANDERS
PLUMBING-Rough 12/27/2024 Corrections Issued KIRK SANDERS
HVAC-Rough 12/31/2024 Corrections Issued EVAN COOPER
ELECTRICAL-Rough 1/2/2025 Not Ready for Inspection DANIEL VERA
Interior/Exterior Lathing 1/2/2025 Not Ready for Inspection DANIEL VERA
BUILDING-Rough-Frame 1/24/2025 Not Ready for Inspection DANIEL VERA
ELECTRICAL-Rough 1/24/2025 Approved DANIEL VERA
Green Building Rough 1/24/2025 Not Ready for Inspection DANIEL VERA
HVAC-Rough 1/24/2025 Not Ready for Inspection DANIEL VERA
MERV13>=Rough 1/24/2025 Approved DANIEL VERA
PLUMBING-Rough 1/24/2025 Not Ready for Inspection DANIEL VERA
Verify Sprinkler Sign Off 1/24/2025 Approved DANIEL VERA
Interior/Exterior Lathing 2/12/2025 Partial Approval DANIEL VERA
PLUMBING-Rough 2/12/2025 Approved DANIEL VERA
BUILDING-Rough-Frame 2/14/2025 Conditional Approval DANIEL VERA
Green Building Rough 2/14/2025 Approved DANIEL VERA
HVAC-Rough 2/14/2025 Approved DANIEL VERA
Insulation 2/27/2025 Approved DANIEL VERA
Interior/Exterior Lathing 3/10/2025 Partial Approval WILBER ROSALES
Special/Order Compliance 3/10/2025 Partial Inspection BOBBY KEY
Drywall Nailing 3/11/2025 Approved WILBER ROSALES
Shower Pan 3/11/2025 Approved WILBER ROSALES
Special/Order Compliance 3/11/2025 Partial Inspection BOBBY KEY
ELECTRICAL-Final 11/13/2025 Corrections Issued KIRK SANDERS
HVAC-Final 11/13/2025 Corrections Issued KIRK SANDERS
PLUMBING-Final 11/13/2025 Corrections Issued KIRK SANDERS
BUILDING-Rough-Frame 12/2/2025 Approved KIRK SANDERS
ELECTRICAL-Final 12/2/2025 Not Ready for Inspection KIRK SANDERS
Final 12/2/2025 Corrections Issued KIRK SANDERS
Green Building Final 12/2/2025 Not Ready for Inspection KIRK SANDERS
HVAC-Final 12/2/2025 Partial Approval KIRK SANDERS
MERV13>=Final 12/2/2025 Not Ready for Inspection KIRK SANDERS
PLUMBING-Final 12/2/2025 Partial Approval KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 12/2/2025 SGSOV Not Required KIRK SANDERS
Service/Power Release 12/2/2025 Not Ready for Inspection KIRK SANDERS
Smoke Detectors 12/2/2025 Not Ready for Inspection KIRK SANDERS
ELECTRICAL-Final 12/12/2025 Partial Approval KIRK SANDERS
HVAC-Final 12/12/2025 Partial Approval KIRK SANDERS
PLUMBING-Final 12/12/2025 Approved KIRK SANDERS
Service/Power Release 12/12/2025 Not Ready for Inspection KIRK SANDERS
ELECTRICAL-Final 12/17/2025 Partial Approval ANTHONY EGSON
HVAC-Final 12/29/2025 Approved KIRK SANDERS
Service/Power Release 1/23/2026 Approved ARAM AVEDISIAN
Final 3/24/2026 OK to Issue CofO ANTHONY EGSON
Green Building Final 3/24/2026 Approved ANTHONY EGSON
MERV13>=Final 3/24/2026 Approved ANTHONY EGSON
Smoke Detectors 3/24/2026 Approved ANTHONY EGSON