1859-1859 3/4 S CRENSHAW BLVD 90019

Certificate Information: 1859-1859 3/4 S CRENSHAW BLVD 90019

Application / Permit
23010-10000-02543
Plan Check / Job No.
B23LA11212
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 3-STORY DUPLEX WITH ATTACHED GARAGE AND ADU PER LAMC 12.22A.33 (c)-(d) -BLDG SPRINKLERED THRU-OUT
Permit Issued
Issued on 7/1/2024
Issuing Office
Metro
Current Status
CofO Corrected on 5/12/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/16/2023 APPLICANT
Assigned to Plan Check Engineer 6/22/2023 MAHNAZ NOURHASHEMI
Corrections Issued 6/27/2023 MAHNAZ NOURHASHEMI
Disabled Access Plans Picked Up 6/30/2023 APPLICANT
Green Plans Picked Up 7/5/2023 APPLICANT
Quality Review Completed 7/7/2023 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 7/11/2023 APPLICANT
Applicant returned to address corrections 10/23/2023 MAHNAZ NOURHASHEMI
Applicant returned to address corrections 11/30/2023 MAHNAZ NOURHASHEMI
Plan Check Approved 6/21/2024 MAHNAZ NOURHASHEMI
Issued 7/1/2024 APPLICANT
CofO in Progress 8/25/2025 JUSTIN HAWLEY
CofO Issued-Status Void 8/27/2025 DEROLD HAUFF
Permit Finaled-Status Void 8/27/2025 DEROLD HAUFF
Re-Activate Permit 5/12/2026 DEROLD HAUFF
Permit Finaled 5/12/2026 DEROLD HAUFF
CofO Corrected 5/12/2026 DEROLD HAUFF
Permit Finaled 5/12/2026 DEROLD HAUFF

Permit Application Clearance Information

SB8 RUD Cleared 8/31/2023 PATRICIA ALFARO
Hydrant and Access approval Cleared 9/7/2023 LAVEON RIDER
Address approval Cleared 10/18/2023 CHRISTINA BRACO
Eng Process Fee Ord 176,300 Cleared 10/18/2023 CHRISTINA BRACO
Sewer availability Cleared 10/18/2023 CHRISTINA BRACO
Highway dedication Cleared 10/25/2023 ADRIAN SANCHEZ
Permit Cleared 10/25/2023 ADRIAN SANCHEZ
Low Impact Development (LID) Cleared 11/14/2023 SAMUEL LINN
Roof/Waste drainage to street Cleared 11/15/2023 ADRIAN SANCHEZ
Trees in Parkway Cleared 11/27/2023 ADALBERTO VERA
Green Code Cleared 11/30/2023 MICHAEL MARTINEZ
Methane Ordinance Cleared 2/28/2024 RONILO MULAWIN
Fire Marshal Fire Life Safety Cleared 5/29/2024 RONILO MULAWIN
DAS Clearance Cleared 6/4/2024 SHINE LIN

Contact Information

Contractor Residential Alchemists; Lic. No.: 1098394-B 2088 S ATLANTIC BLVD #276      MONTEREY PARK, CA 91754

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/28/2024 Not Ready for Inspection JUSTIN HAWLEY
Excavation/Setback/Form/Re-Bar 9/19/2024 Not Ready for Inspection WILLIAM SIERRA
Excavation/Setback/Form/Re-Bar 9/20/2024 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 9/20/2024 Partial Approval ENRIQUE MIRELES
METHANE-Barrier 9/20/2024 Not Ready for Inspection ENRIQUE MIRELES
METHANE-Subgrade 9/20/2024 Approved ENRIQUE MIRELES
Deputy Reinf. Concrete 9/23/2024 Partial Approval JEFFREY MEAD
Deputy Methane Barrier 9/26/2024 Conditional Approval JUSTIN HAWLEY
Excavation/Setback/Form/Re-Bar 9/26/2024 Not Ready for Inspection JUSTIN HAWLEY
Footing/Foundation/Slab 9/26/2024 Not Ready for Inspection JUSTIN HAWLEY
METHANE-Barrier 9/26/2024 Approved JUSTIN HAWLEY
Excavation/Setback/Form/Re-Bar 9/27/2024 Approved JUSTIN HAWLEY
Deputy Steel/Welding 10/18/2024 Conditional Approval JUSTIN HAWLEY
Deputy Steel/Welding 10/25/2024 Conditional Approval JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 10/31/2024 Partial Approval BRENDAN MORELLI
Deputy Steel/Welding 11/4/2024 Conditional Approval JUSTIN HAWLEY
Deputy Steel/Welding 11/6/2024 Conditional Approval JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 11/14/2024 Corrections Issued WILLIAM SIERRA
Floor/Roof Diaphrgm/Shear Wall 11/19/2024 Partial Approval JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 12/9/2024 Not Ready for Inspection JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 12/17/2024 Partial Approval JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 1/2/2025 Not Ready for Inspection RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 1/7/2025 Not Ready for Inspection JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 1/22/2025 Partial Approval JUSTIN HAWLEY
METHANE-Rough 1/22/2025 Approved JUSTIN HAWLEY
Insulation 2/7/2025 Conditional Approval JUSTIN HAWLEY
Interior/Exterior Lathing 2/7/2025 Approved JUSTIN HAWLEY
Drywall Nailing 3/4/2025 Not Ready for Inspection ENRIQUE MIRELES
Interior/Exterior Lathing 3/4/2025 Approved ENRIQUE MIRELES
Drywall Nailing 3/11/2025 Approved ALEX COLIN
Pre-Inspection 7/1/2025 Approved JUSTIN HAWLEY
Special/Order Compliance 7/1/2025 Corrections Issued JUSTIN HAWLEY
Special/Order Compliance 7/11/2025 Approved JUSTIN HAWLEY
Final 8/18/2025 Not Ready for Inspection JUSTIN HAWLEY
Footing/Foundation/Slab 8/18/2025 Approved JUSTIN HAWLEY
Green Building Final 8/18/2025 Approved JUSTIN HAWLEY
Green Building Rough 8/18/2025 Approved JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 8/18/2025 SGSOV Not Required JUSTIN HAWLEY
Smoke Detectors 8/18/2025 Approved JUSTIN HAWLEY
Verify Sprinkler Sign Off 8/18/2025 Approved JUSTIN HAWLEY
Wood Frame 8/18/2025 Approved JUSTIN HAWLEY
Final 8/21/2025 Not Ready for Inspection WILLIAM SIERRA
Final 8/25/2025 OK to Issue CofO JUSTIN HAWLEY