1855 S CRENSHAW BLVD 90019
Certificate Information: 1855 S CRENSHAW BLVD 90019
- Application / Permit
- 23010-10000-02541
- Plan Check / Job No.
- B23LA11212
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SFD (FRONT LOT) -BLDG SPRINKLERED THRU-OUT
- Permit Issued
- Issued on 7/1/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/16/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/22/2023 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 6/27/2023 | MAHNAZ NOURHASHEMI |
| Disabled Access Plans Picked Up | 6/30/2023 | APPLICANT |
| Green Plans Picked Up | 7/5/2023 | APPLICANT |
| Quality Review Completed | 7/7/2023 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 7/11/2023 | APPLICANT |
| Applicant returned to address corrections | 10/23/2023 | MAHNAZ NOURHASHEMI |
| Applicant returned to address corrections | 11/30/2023 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 7/1/2024 | MAHNAZ NOURHASHEMI |
| Issued | 7/1/2024 | APPLICANT |
| CofO in Progress | 8/25/2025 | JUSTIN HAWLEY |
| Permit Finaled | 8/27/2025 | DEROLD HAUFF |
| CofO Issued | 8/27/2025 | DEROLD HAUFF |
| Permit Finaled | 8/27/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/23/2023 | MSTAFA AL-MSARI |
| Address approval | Cleared | 8/24/2023 | MSTAFA AL-MSARI |
| SB8 RUD | Cleared | 8/31/2023 | PATRICIA ALFARO |
| Hydrant and Access approval | Cleared | 9/7/2023 | LAVEON RIDER |
| Sewer availability | Cleared | 10/18/2023 | CHRISTINA BRACO |
| Opn space landscape/Water mgmt | Cleared | 10/26/2023 | MAXFIELD VERMY |
| Highway dedication | Cleared | 11/2/2023 | ADRIAN SANCHEZ |
| Permit | Cleared | 11/2/2023 | ADRIAN SANCHEZ |
| Low Impact Development (LID) | Cleared | 11/14/2023 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 11/15/2023 | ADRIAN SANCHEZ |
| Green Code | Cleared | 11/30/2023 | MICHAEL MARTINEZ |
Contact Information
| Contractor | Residential Alchemists; Lic. No.: 1098394-B | 2088 S ATLANTIC BLVD #276 MONTEREY PARK, CA 91754 |
| Engineer | Nuno,, Arnulfo; Lic. No.: C88425 | 7057 DWIGHT WAY SAN BERNARDINO, CA 92404 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/22/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Sewer | 8/22/2024 | Approved | JUSTIN HAWLEY |
| Underground Mechanical | 8/22/2024 | Partial Approval | JUSTIN HAWLEY |
| Excavation/Setback/Form/Re-Bar | 8/28/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 8/28/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| METHANE-Barrier | 8/28/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Excavation/Setback/Form/Re-Bar | 9/6/2024 | Corrections Issued | JOHN QUINTANILLA |
| Excavation/Setback/Form/Re-Bar | 9/10/2024 | Approved | JUSTIN HAWLEY |
| METHANE-Rough | 9/10/2024 | Approved | JUSTIN HAWLEY |
| Deputy Methane Barrier | 9/20/2024 | Conditional Approval | JOSE MACIAS |
| Deputy Reinf. Concrete | 9/23/2024 | Partial Approval | JEFFREY MEAD |
| Deputy Methane Barrier | 9/26/2024 | Conditional Approval | JUSTIN HAWLEY |
| Excavation/Setback/Form/Re-Bar | 9/26/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 9/26/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| METHANE-Barrier | 9/26/2024 | Approved | JUSTIN HAWLEY |
| METHANE-Subgrade | 9/26/2024 | Approved | JUSTIN HAWLEY |
| Excavation/Setback/Form/Re-Bar | 9/27/2024 | Approved | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2024 | Partial Approval | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2024 | Partial Approval | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/17/2024 | Partial Approval | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/2/2025 | Partial Approval | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 1/7/2025 | Not Ready for Inspection | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 1/14/2025 | Not Ready for Inspection | JUSTIN HAWLEY |
| ELECTRICAL-Rough | 1/14/2025 | Not Ready for Inspection | JUSTIN HAWLEY |
| Green Building Rough | 1/14/2025 | Not Ready for Inspection | JUSTIN HAWLEY |
| HVAC-Rough | 1/14/2025 | Corrections Issued | JUSTIN HAWLEY |
| PLUMBING-Rough | 1/14/2025 | Not Ready for Inspection | JUSTIN HAWLEY |
| Verify Sprinkler Sign Off | 1/14/2025 | Not Ready for Inspection | JUSTIN HAWLEY |
| ELECTRICAL-Rough | 1/15/2025 | Approved | JUSTIN HAWLEY |
| HVAC-Rough | 1/15/2025 | Approved | JUSTIN HAWLEY |
| PLUMBING-Rough | 1/15/2025 | Corrections Issued | JUSTIN HAWLEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2025 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 1/22/2025 | Not Ready for Inspection | JUSTIN HAWLEY |
| PLUMBING-Rough | 1/22/2025 | Not Ready for Inspection | JUSTIN HAWLEY |
| Verify Sprinkler Sign Off | 1/22/2025 | Not Ready for Inspection | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 1/29/2025 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 1/29/2025 | Not Ready for Inspection | JUSTIN HAWLEY |
| PLUMBING-Rough | 1/29/2025 | Approved | JUSTIN HAWLEY |
| Shower Pan | 1/29/2025 | Approved | JUSTIN HAWLEY |
| Verify Sprinkler Sign Off | 1/29/2025 | Approved | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 2/7/2025 | Approved | JUSTIN HAWLEY |
| Green Building Rough | 2/7/2025 | Approved | JUSTIN HAWLEY |
| Insulation | 2/7/2025 | Conditional Approval | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 2/7/2025 | Approved | JUSTIN HAWLEY |
| Shower Pan | 2/7/2025 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 3/4/2025 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 6/26/2025 | Not Ready for Inspection | JUSTIN HAWLEY |
| HVAC-Final | 6/26/2025 | Not Ready for Inspection | JUSTIN HAWLEY |
| PLUMBING-Final | 6/26/2025 | Approved | JUSTIN HAWLEY |
| Service/Power Release | 6/26/2025 | Not Ready for Inspection | JUSTIN HAWLEY |
| ELECTRICAL-Final | 7/1/2025 | Approved | JUSTIN HAWLEY |
| HVAC-Final | 7/1/2025 | Not Ready for Inspection | JUSTIN HAWLEY |
| Service/Power Release | 7/1/2025 | Approved | JUSTIN HAWLEY |
| HVAC-Final | 7/11/2025 | Approved | JUSTIN HAWLEY |
| Final | 8/18/2025 | Not Ready for Inspection | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 8/18/2025 | Approved | JUSTIN HAWLEY |
| Green Building Final | 8/18/2025 | Approved | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 8/18/2025 | SGSOV Not Required | JUSTIN HAWLEY |
| Service/Power Release | 8/18/2025 | Approved | JUSTIN HAWLEY |
| Smoke Detectors | 8/18/2025 | Approved | JUSTIN HAWLEY |
| Final | 8/21/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| Service/Power Release | 8/21/2025 | No Access for Inspection | WILLIAM SIERRA |
| Final | 8/25/2025 | OK to Issue CofO | JUSTIN HAWLEY |