5717 E OMAHA ST 90042

Certificate Information: 5717 E OMAHA ST 90042

Application / Permit
23010-10000-02535
Plan Check / Job No.
B23LA11181
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 2-STORY DETACHED ADU PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 5/21/2024
Issuing Office
Metro
Current Status
CofO Issued on 5/12/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/15/2023 APPLICANT
Assigned to Plan Check Engineer 7/6/2023 MAHNAZ NOURHASHEMI
Corrections Issued 7/17/2023 MAHNAZ NOURHASHEMI
Quality Review Completed 7/28/2023 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 8/11/2023 APPLICANT
Applicant returned to address corrections 10/4/2023 MAHNAZ NOURHASHEMI
Plan Check Approved 5/16/2024 MAHNAZ NOURHASHEMI
Issued 5/21/2024 APPLICANT
CofO in Progress 5/11/2026 LILIANA PORTILLO
Permit Finaled 5/12/2026 DEROLD HAUFF
CofO Issued 5/12/2026 DEROLD HAUFF
Permit Finaled 5/12/2026 DEROLD HAUFF

Permit Application Clearance Information

GPI Written Notices Cleared 7/17/2023 MAHNAZ NOURHASHEMI
Grading Pre-Inspection Cleared 7/17/2023 MAHNAZ NOURHASHEMI
Address approval Cleared 10/4/2023 CHRISTINA BRACO
Eng Process Fee Ord 176,300 Cleared 12/1/2023 CHRISTINA BRACO
Sewer availability Cleared 12/1/2023 CHRISTINA BRACO
Hydrant and Access approval Cleared 1/13/2024 MATTHEW CRAIG
ZA Case Cleared 1/18/2024 JASON CHAN
Low Impact Development (LID) Cleared 4/10/2024 PATRICK LOPEZ
Roof/Waste drainage to street Cleared 4/15/2024 CELINA MORENO

Contact Information

Contractor J Z J B Cnst Inv; Lic. No.: 1013600-B 345 W LORAINE ST 3      GLENDALE, CA 91202

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 6/26/2024 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 7/17/2024 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 9/10/2024 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 10/17/2024 Partial Approval LILIANA PORTILLO
ELECTRICAL-Rough 12/30/2024 Corrections Issued BRENDAN MORELLI
HVAC-Rough 12/30/2024 Corrections Issued BRENDAN MORELLI
PLUMBING-Rough 12/30/2024 Corrections Issued BRENDAN MORELLI
ELECTRICAL-Rough 1/31/2025 Not Ready for Inspection BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 1/31/2025 Approved BRENDAN MORELLI
HVAC-Rough 1/31/2025 Not Ready for Inspection BRENDAN MORELLI
PLUMBING-Rough 1/31/2025 Not Ready for Inspection BRENDAN MORELLI
ELECTRICAL-Rough 3/6/2025 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 3/6/2025 Corrections Issued LILIANA PORTILLO
HVAC-Rough 3/6/2025 Approved LILIANA PORTILLO
PLUMBING-Rough 3/6/2025 Not Ready for Inspection LILIANA PORTILLO
BUILDING-Rough-Frame 3/10/2025 Conditional Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 3/10/2025 Approved LILIANA PORTILLO
Green Building Rough 3/10/2025 Not Ready for Inspection LILIANA PORTILLO
MERV13>=Rough 3/10/2025 Approved LILIANA PORTILLO
PLUMBING-Rough 3/10/2025 Approved LILIANA PORTILLO
Verify Sprinkler Sign Off 3/10/2025 Approved LILIANA PORTILLO
Interior/Exterior Lathing 3/18/2025 Partial Approval JOSH MEISTER
Insulation 3/26/2025 Corrections Issued LILIANA PORTILLO
Insulation 4/11/2025 Approved REGINA MENDEZ
Drywall Nailing 4/23/2025 Approved NICHOLAS LOPEZ
Shower Pan 5/27/2025 Approved REGINA MENDEZ
Interior/Exterior Lathing 6/2/2025 Approved LILIANA PORTILLO
Sewer 10/8/2025 Approved DAVID WILLIAMS
Underground Mechanical 10/8/2025 Approved DAVID WILLIAMS
ELECTRICAL-Rough 10/21/2025 Approved LILIANA PORTILLO
ELECTRICAL-Final 3/6/2026 Not Ready for Inspection LILIANA PORTILLO
Final 3/6/2026 Corrections Issued LILIANA PORTILLO
HVAC-Final 3/6/2026 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Final 3/6/2026 Not Ready for Inspection LILIANA PORTILLO
BUILDING-Rough-Frame 4/3/2026 Approved LILIANA PORTILLO
ELECTRICAL-Final 4/3/2026 Not Ready for Inspection LILIANA PORTILLO
Final 4/3/2026 Not Ready for Inspection LILIANA PORTILLO
Green Building Final 4/3/2026 Not Ready for Inspection LILIANA PORTILLO
Green Building Rough 4/3/2026 Approved LILIANA PORTILLO
HVAC-Final 4/3/2026 Not Ready for Inspection LILIANA PORTILLO
MERV13>=Final 4/3/2026 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Final 4/3/2026 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 4/3/2026 SGSOV No Gas LILIANA PORTILLO
Service/Power Release 4/3/2026 Not Ready for Inspection LILIANA PORTILLO
Smoke Detectors 4/3/2026 Approved LILIANA PORTILLO
ELECTRICAL-Final 5/6/2026 Approved LILIANA PORTILLO
Final 5/6/2026 OK to Issue CofO LILIANA PORTILLO
Green Building Final 5/6/2026 Approved LILIANA PORTILLO
HVAC-Final 5/6/2026 Approved LILIANA PORTILLO
MERV13>=Final 5/6/2026 Approved LILIANA PORTILLO
PLUMBING-Final 5/6/2026 Approved LILIANA PORTILLO
Service/Power Release 5/6/2026 Approved LILIANA PORTILLO