13659 W PINNEY ST 91331
Certificate Information: 13659 W PINNEY ST 91331
- Application / Permit
- 23010-10000-02534
- Plan Check / Job No.
- B23LA11179
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU PER ENGINEER DETAIL PER CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g))
- Permit Issued
- Issued on 6/25/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/1/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/15/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/23/2023 | AUNG SOE |
| Building Plans Picked Up | 6/29/2023 | APPLICANT |
| Corrections Issued | 7/24/2023 | AUNG SOE |
| Applicant returned to address corrections | 12/28/2023 | NEHEMIAS RAMOS |
| Plan Check Approved | 2/13/2024 | NEHEMIAS RAMOS |
| Issued | 6/25/2024 | APPLICANT |
| CofO in Progress | 3/13/2025 | MICHEL ABAJAN |
| Permit Finaled | 4/1/2025 | RUBEN SALAS |
| CofO Issued | 4/1/2025 | RUBEN SALAS |
| Permit Finaled | 4/1/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/18/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 7/18/2023 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 7/18/2023 | ROMAN GUTIERREZ |
| Clean Up Green Up | Cleared | 8/2/2023 | ERICK MARCHENA |
| Construction near power lines | Cleared | 8/3/2023 | TINA MIRANDA |
| Construction within easement | Cleared | 8/3/2023 | TINA MIRANDA |
| Low Impact Development (LID) | Cleared | 12/26/2023 | TRISH PARAS |
| Roof/Waste drainage to street | Cleared | 12/28/2023 | EDGAR ALCARAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Guh,, Jeff; Lic. No.: S3218 | 705 SAN VICENTE BLVD SANTA MONICA, CA 90402 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/23/2024 | No Access for Inspection | MICHEL ABAJAN |
| Footing/Foundation/Slab | 7/23/2024 | No Access for Inspection | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 7/24/2024 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/29/2024 | Partial Approval | MICHEL ABAJAN |
| PLUMBING-Rough | 7/31/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 8/14/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| ELECTRICAL-Rough | 8/14/2024 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/14/2024 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 8/14/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| HVAC-Rough | 8/14/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 8/14/2024 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 9/23/2024 | Approved | MICHEL ABAJAN |
| Green Building Rough | 9/23/2024 | Approved | MICHEL ABAJAN |
| Insulation | 10/9/2024 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 10/9/2024 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 10/22/2024 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 2/12/2025 | Approved | MICHEL ABAJAN |
| Final | 2/12/2025 | Corrections Issued | MICHEL ABAJAN |
| Footing/Foundation/Slab | 2/12/2025 | Approved | MICHEL ABAJAN |
| Green Building Final | 2/12/2025 | Approved | MICHEL ABAJAN |
| HVAC-Final | 2/12/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| PLUMBING-Final | 2/12/2025 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 2/12/2025 | SGSOV Not Required | MICHEL ABAJAN |
| Service/Power Release | 2/12/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 2/12/2025 | Approved | MICHEL ABAJAN |
| Final | 2/21/2025 | Corrections Issued | MICHEL ABAJAN |
| Service/Power Release | 2/21/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| Final | 3/12/2025 | OK to Issue CofO | MICHEL ABAJAN |