1452 1/2 W 83RD ST 90047

Certificate Information: 1452 1/2 W 83RD ST 90047

Application / Permit
23010-10000-02521
Plan Check / Job No.
B23LA11080
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan CONVERSION OF GARAGE TO 1 STORY ADU WITH ADDITION ADU PER CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)
Permit Issued
Issued on 9/14/2023
Issuing Office
Current Status
CofO Issued on 10/25/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/15/2023 APPLICANT
Assigned to Plan Check Engineer 6/22/2023 JAD BASMA
Corrections Issued 6/25/2023 JAD BASMA
Quality Review Completed 7/5/2023 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 8/23/2023 JAD BASMA
Applicant returned to address corrections 9/7/2023 JAD BASMA
Plan Check Approved 9/7/2023 JAD BASMA
Issued 9/14/2023 APPLICANT
CofO in Progress 10/15/2024 CRAIG DAVIS
CofO in Progress 10/21/2024 CRAIG DAVIS
CofO in Progress 10/21/2024 CRAIG DAVIS
Permit Finaled 10/25/2024 RUBEN SALAS
CofO Issued 10/25/2024 RUBEN SALAS
Permit Finaled 10/25/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/2/2023 HUGO LOPEZ
Roof/Waste drainage to street Cleared 7/2/2023 HUGO LOPEZ
Eng Process Fee Ord 176,300 Cleared 7/6/2023 HUGO LOPEZ
Sewer availability Cleared 7/6/2023 HUGO LOPEZ

Contact Information

Contractor J Z J B Cnst Inv; Lic. No.: 1013600-B       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/26/2023 Corrections Issued CRAIG DAVIS
Underground Mechanical 12/26/2023 Not Ready for Inspection CRAIG DAVIS
PLUMBING-Rough 12/28/2023 Not Ready for Inspection MICHAEL LEWIS
Underground Mechanical 12/28/2023 Approved MICHAEL LEWIS
Footing/Foundation/Slab 1/9/2024 Corrections Issued MICHAEL LEWIS
Excavation/Setback/Form/Re-Bar 1/29/2024 Approved MICHAEL LEWIS
Footing/Foundation/Slab 1/29/2024 Approved MICHAEL LEWIS
PLUMBING-Rough 3/18/2024 Approved MICHAEL LEWIS
ELECTRICAL-Rough 4/3/2024 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 4/3/2024 Approved MICHAEL LEWIS
HVAC-Rough 4/3/2024 Corrections Issued MICHAEL LEWIS
Shower Pan 5/17/2024 Approved MICHAEL LEWIS
Insulation 5/23/2024 Partial Approval MICHAEL LEWIS
BUILDING-Rough-Frame 5/29/2024 Approved CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 5/29/2024 Approved CRAIG DAVIS
Green Building Rough 5/29/2024 Approved CRAIG DAVIS
Wood Frame 5/29/2024 Approved CRAIG DAVIS
Drywall Nailing 6/7/2024 Approved MICHAEL LEWIS
Insulation 6/7/2024 Approved MICHAEL LEWIS
Interior/Exterior Lathing 7/23/2024 Approved MICHAEL LEWIS
Sewer 8/5/2024 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 8/5/2024 Approved ALEJANDRO DE ARTOLA
Final 10/1/2024 Corrections Issued SABAS ALONSO
Green Building Final 10/1/2024 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 10/1/2024 SGSOV Not Ready SABAS ALONSO
Service/Power Release 10/1/2024 Not Ready for Inspection SABAS ALONSO
Smoke Detectors 10/1/2024 Approved SABAS ALONSO
ELECTRICAL-Final 10/7/2024 Corrections Issued CRAIG DAVIS
Final 10/7/2024 Not Ready for Inspection CRAIG DAVIS
HVAC-Final 10/7/2024 Approved CRAIG DAVIS
PLUMBING-Final 10/7/2024 Corrections Issued CRAIG DAVIS
SGSOV-Seismic Gas S/O Valve 10/7/2024 SGSOV Approved CRAIG DAVIS
ELECTRICAL-Final 10/8/2024 Approved CRAIG DAVIS
Final 10/8/2024 OK to Issue CofO CRAIG DAVIS
HVAC-Final 10/8/2024 Approved CRAIG DAVIS
PLUMBING-Final 10/8/2024 Approved CRAIG DAVIS
Service/Power Release 10/15/2024 Approved CRAIG DAVIS