522-522 1/2 W 75TH ST 90044

Certificate Information: 522-522 1/2 W 75TH ST 90044

Application / Permit
23010-10000-02519
Plan Check / Job No.
B23LA11074
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
NEW 3-STORY DUPLEX WITH ATTACHED 8-CAR GARAGE AT THE REAR OF LOT. NFPA 13D SOLAR INSTALLATION REQUIRED PER TITLE 24 TO MEET 3.5 KW EACH UNIT (7 KW TOTAL) PRIOR TO COFO.
Permit Issued
Issued on 2/28/2024
Issuing Office
Metro
Current Status
CofO Issued on 2/26/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/14/2023 APPLICANT
Assigned to Plan Check Engineer 6/29/2023 VIVIAN LAO
Corrections Issued 7/7/2023 VIVIAN LAO
Quality Review Completed 7/14/2023 KEN GILL
Building Plans Picked Up 7/17/2023 APPLICANT
Plan Check Approved 10/11/2023 VIVIAN LAO
Issued 2/28/2024 APPLICANT
CofO in Progress 2/25/2025 JOHN QUINTANILLA
Permit Finaled 2/26/2025 DEROLD HAUFF
CofO Issued 2/26/2025 DEROLD HAUFF
Permit Finaled 2/26/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/15/2023 CELINA MORENO
Highway dedication Cleared 7/15/2023 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 7/18/2023 CELINA MORENO
Sewer availability Cleared 7/18/2023 CELINA MORENO
"Q" conditions Cleared 7/26/2023 SPENCER WEJROWSKI
Frnt yard landscape/Water mgmt Cleared 7/31/2023 SPENCER WEJROWSKI
SB8 RUD Cleared 8/15/2023 JULIE LIEU
Low Impact Development (LID) Cleared 9/8/2023 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 9/10/2023 AHMED AMARRAGY
Hydrant and Access approval Cleared 9/28/2023 LAVEON RIDER

Contact Information

Contractor Lajoma Construction Inc; Lic. No.: 864461-B PO BOX 39459      DOWNEY, CA 90241
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240
Engineer Shubeck,, Christopher Robert; Lic. No.: C66775 23705 VANOWEN ST 101      WEST HILLS, CA 91307

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/17/2024 Approved MICHAEL LEWIS
Underground Mechanical 5/17/2024 Approved MICHAEL LEWIS
Footing/Foundation/Slab 5/29/2024 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 6/26/2024 Partial Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 7/10/2024 Partial Approval ALEJANDRO DE ARTOLA
Deputy Wood Construction 8/28/2024 Approved MICHAEL LEWIS
ELECTRICAL-Rough 9/18/2024 Corrections Issued MICHAEL LEWIS
PLUMBING-Rough 9/18/2024 Corrections Issued MICHAEL LEWIS
ELECTRICAL-Rough 9/19/2024 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 9/19/2024 Partial Approval SABAS ALONSO
HVAC-Rough 9/19/2024 Approved SABAS ALONSO
BUILDING-Rough-Frame 9/20/2024 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 9/20/2024 Approved MICHAEL LEWIS
MERV13>=Rough 9/20/2024 Approved MICHAEL LEWIS
Verify Sprinkler Sign Off 9/20/2024 Approved MICHAEL LEWIS
Insulation 10/1/2024 Approved SABAS ALONSO
Interior/Exterior Lathing 10/1/2024 Partial Approval SABAS ALONSO
Drywall Nailing 10/10/2024 Approved JOSH MEISTER
Green Building Rough 10/10/2024 Approved JOSH MEISTER
HVAC-Final 2/10/2025 Approved JOHN QUINTANILLA
PLUMBING-Final 2/10/2025 Approved JOHN QUINTANILLA
ELECTRICAL-Final 2/18/2025 Approved JOHN QUINTANILLA
Final 2/18/2025 Conditional Approval JOHN QUINTANILLA
Green Building Final 2/18/2025 Approved JOHN QUINTANILLA
MERV13>=Final 2/18/2025 Approved JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 2/18/2025 SGSOV Not Required JOHN QUINTANILLA
Service/Power Release 2/18/2025 Approved JOHN QUINTANILLA
Smoke Detectors 2/18/2025 Approved JOHN QUINTANILLA
Final 2/21/2025 OK to Issue CofO JOHN QUINTANILLA