522-522 1/2 W 75TH ST 90044
Certificate Information: 522-522 1/2 W 75TH ST 90044
- Application / Permit
- 23010-10000-02519
- Plan Check / Job No.
- B23LA11074
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 3-STORY DUPLEX WITH ATTACHED 8-CAR GARAGE AT THE REAR OF LOT. NFPA 13D SOLAR INSTALLATION REQUIRED PER TITLE 24 TO MEET 3.5 KW EACH UNIT (7 KW TOTAL) PRIOR TO COFO.
- Permit Issued
- Issued on 2/28/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/29/2023 | VIVIAN LAO |
| Corrections Issued | 7/7/2023 | VIVIAN LAO |
| Quality Review Completed | 7/14/2023 | KEN GILL |
| Building Plans Picked Up | 7/17/2023 | APPLICANT |
| Plan Check Approved | 10/11/2023 | VIVIAN LAO |
| Issued | 2/28/2024 | APPLICANT |
| CofO in Progress | 2/25/2025 | JOHN QUINTANILLA |
| Permit Finaled | 2/26/2025 | DEROLD HAUFF |
| CofO Issued | 2/26/2025 | DEROLD HAUFF |
| Permit Finaled | 2/26/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/15/2023 | CELINA MORENO |
| Highway dedication | Cleared | 7/15/2023 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 7/18/2023 | CELINA MORENO |
| Sewer availability | Cleared | 7/18/2023 | CELINA MORENO |
| "Q" conditions | Cleared | 7/26/2023 | SPENCER WEJROWSKI |
| Frnt yard landscape/Water mgmt | Cleared | 7/31/2023 | SPENCER WEJROWSKI |
| SB8 RUD | Cleared | 8/15/2023 | JULIE LIEU |
| Low Impact Development (LID) | Cleared | 9/8/2023 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 9/10/2023 | AHMED AMARRAGY |
| Hydrant and Access approval | Cleared | 9/28/2023 | LAVEON RIDER |
Contact Information
| Contractor | Lajoma Construction Inc; Lic. No.: 864461-B | PO BOX 39459 DOWNEY, CA 90241 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
| Engineer | Shubeck,, Christopher Robert; Lic. No.: C66775 | 23705 VANOWEN ST 101 WEST HILLS, CA 91307 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/17/2024 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 5/17/2024 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 5/29/2024 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2024 | Partial Approval | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Deputy Wood Construction | 8/28/2024 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 9/18/2024 | Corrections Issued | MICHAEL LEWIS |
| PLUMBING-Rough | 9/18/2024 | Corrections Issued | MICHAEL LEWIS |
| ELECTRICAL-Rough | 9/19/2024 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2024 | Partial Approval | SABAS ALONSO |
| HVAC-Rough | 9/19/2024 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 9/20/2024 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2024 | Approved | MICHAEL LEWIS |
| MERV13>=Rough | 9/20/2024 | Approved | MICHAEL LEWIS |
| Verify Sprinkler Sign Off | 9/20/2024 | Approved | MICHAEL LEWIS |
| Insulation | 10/1/2024 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 10/1/2024 | Partial Approval | SABAS ALONSO |
| Drywall Nailing | 10/10/2024 | Approved | JOSH MEISTER |
| Green Building Rough | 10/10/2024 | Approved | JOSH MEISTER |
| HVAC-Final | 2/10/2025 | Approved | JOHN QUINTANILLA |
| PLUMBING-Final | 2/10/2025 | Approved | JOHN QUINTANILLA |
| ELECTRICAL-Final | 2/18/2025 | Approved | JOHN QUINTANILLA |
| Final | 2/18/2025 | Conditional Approval | JOHN QUINTANILLA |
| Green Building Final | 2/18/2025 | Approved | JOHN QUINTANILLA |
| MERV13>=Final | 2/18/2025 | Approved | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 2/18/2025 | SGSOV Not Required | JOHN QUINTANILLA |
| Service/Power Release | 2/18/2025 | Approved | JOHN QUINTANILLA |
| Smoke Detectors | 2/18/2025 | Approved | JOHN QUINTANILLA |
| Final | 2/21/2025 | OK to Issue CofO | JOHN QUINTANILLA |