4938 N RUBIO AVE 91436
Certificate Information: 4938 N RUBIO AVE 91436
- Application / Permit
- 23010-10000-02492
- Plan Check / Job No.
- B23LA09241
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- eplan NEW DETACHED CABANA #1
- Permit Issued
- Issued on 9/21/2023
- Issuing Office
- Current Status
- CofO Issued on 4/25/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/30/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/1/2023 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 6/9/2023 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 6/21/2023 | TEODORO DIAZ RODRIGUEZ |
| Plan Check Approved | 8/2/2023 | MAHNAZ NOURHASHEMI |
| Issued | 9/21/2023 | APPLICANT |
| CofO in Progress | 4/1/2024 | VINCENT HANLEY |
| Permit Finaled | 4/25/2024 | JOHN JANSON |
| CofO Issued | 4/25/2024 | JOHN JANSON |
| Permit Finaled | 4/25/2024 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/30/2023 | NIKKI ZULUETA |
| Roof/Waste drainage to street | Cleared | 6/30/2023 | NIKKI ZULUETA |
| ZA Case | Cleared | 7/28/2023 | GEORGIA SMITH |
| ZA Case | Cleared | 7/28/2023 | GEORGIA SMITH |
Contact Information
| Contractor | Aqua Pool & Spa Construction Inc; Lic. No.: 1046115-B | , |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/15/2023 | Corrections Issued | VINCENT HANLEY |
| Deputy Reinf. Concrete | 11/16/2023 | Partial Approval | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 11/21/2023 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 12/5/2023 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/12/2023 | Approved | VINCENT HANLEY |
| Deputy Steel/Welding | 12/15/2023 | Partial Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 12/19/2023 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 1/4/2024 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 1/10/2024 | Approved | VINCENT HANLEY |
| Final | 1/26/2024 | Corrections Issued | VINCENT HANLEY |
| Gas Test | 1/26/2024 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 1/26/2024 | SGSOV Approved | VINCENT HANLEY |
| Service/Power Release | 1/26/2024 | Approved | VINCENT HANLEY |
| Smoke Detectors | 1/26/2024 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 3/29/2024 | Approved | VINCENT HANLEY |
| Final | 3/29/2024 | OK to Issue CofO | VINCENT HANLEY |
| PLUMBING-Final | 3/29/2024 | Approved | VINCENT HANLEY |