10820 W WESTMINSTER AVE 90034

Certificate Information: 10820 W WESTMINSTER AVE 90034

Application / Permit
23010-10000-02487
Plan Check / Job No.
B23LA10968
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: NEW 2-STORY SFD OVER BASEMENT
Permit Issued
Issued on 6/24/2024
Issuing Office
Current Status
Issued on 6/24/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/15/2023 APPLICANT
Assigned to Plan Check Engineer 7/6/2023 MAHNAZ NOURHASHEMI
Corrections Issued 7/14/2023 MAHNAZ NOURHASHEMI
Quality Review Completed 7/20/2023 TEODORO DIAZ RODRIGUEZ
Plan Check Approved 5/17/2024 MAHNAZ NOURHASHEMI
Plan Check Approved 5/24/2024 MAHNAZ NOURHASHEMI
Issued 6/24/2024 APPLICANT

Permit Application Clearance Information

Specific Plan Cleared 8/3/2023 ALESSANDRO MERCURI
Hydrant and Access approval Cleared 8/25/2023 JOHN CONNEALLY
Low Impact Development (LID) Cleared 3/20/2024 MITESH PATEL
GPI Written Notices Cleared 4/17/2024 MAHNAZ NOURHASHEMI
Grading Pre-Inspection Cleared 4/17/2024 MAHNAZ NOURHASHEMI
Eng Process Fee Ord 176,300 Cleared 4/18/2024 DARIN LAM
Sewer availability Cleared 4/18/2024 DARIN LAM
Roof/Waste drainage to street Cleared 4/22/2024 DARIN LAM

Contact Information

Contractor Bless It Construction Inc; Lic. No.: 1048746-B       ,
Engineer Koma,, Shahram Javadi; Lic. No.: NA69497       ,

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 9/17/2024 Approved DANIEL VERA
Footing/Foundation/Slab 10/30/2024 Partial Approval ARAM AVEDISIAN
Footing/Foundation/Slab 12/6/2024 Partial Approval BOBBY KEY
PLUMBING-Rough 12/19/2024 Partial Approval BOBBY KEY
Special/Order Compliance 12/19/2024 Partial Inspection JAYLIN GRAVITTE
Underground Mechanical 12/24/2024 Partial Approval DANIEL VERA
Footing/Foundation/Slab 12/31/2024 Approved BOBBY KEY
Deputy Drilled-In Anchors 1/22/2025 Conditional Approval DANIEL VERA
Deputy Steel/Welding 1/22/2025 Conditional Approval DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 1/28/2025 Corrections Issued EVAN COOPER
Structural Steel Frame 1/28/2025 Approved EVAN COOPER
Deputy Wood Construction 2/18/2025 Approved DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 2/18/2025 Conditional Approval DANIEL VERA
Deputy Shotcrete 3/7/2025 Conditional Approval MICHAEL PELHAM
Special/Order Compliance 3/11/2025 Partial Inspection MICHAEL PELHAM
Deputy Wood Construction 3/25/2025 Conditional Approval WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 3/25/2025 Corrections Issued WILBER ROSALES
Special/Order Compliance 3/25/2025 Partial Inspection TEMISTOCLES CAAL
PLUMBING-Rough 4/15/2025 Corrections Issued ARAM AVEDISIAN
BUILDING-Rough-Frame 7/9/2025 Corrections Issued WILBER ROSALES
ELECTRICAL-Rough 7/9/2025 Approved WILBER ROSALES
HVAC-Rough 7/9/2025 Approved WILBER ROSALES
PLUMBING-Rough 7/9/2025 Approved WILBER ROSALES
Verify Sprinkler Sign Off 7/9/2025 Not Ready for Inspection WILBER ROSALES
BUILDING-Rough-Frame 7/18/2025 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 7/18/2025 Partial Approval ARAM AVEDISIAN
Verify Sprinkler Sign Off 7/18/2025 Approved ARAM AVEDISIAN
Insulation 7/24/2025 Conditional Approval KIRK SANDERS
Special/Order Compliance 7/24/2025 Corrections Issued KIRK SANDERS
Drywall Nailing 7/30/2025 Approved MICHAEL ALLEN
Shower Pan 8/19/2025 Approved MEL KHACHATOURIAN
Interior/Exterior Lathing 9/3/2025 Approved JAYLIN GRAVITTE
Special/Order Compliance 3/13/2026 Corrections Issued ARAM AVEDISIAN
ELECTRICAL-Final 4/21/2026 Corrections Issued RYAN SALAZAR
HVAC-Final 4/21/2026 Approved RYAN SALAZAR
PLUMBING-Final 4/21/2026 Approved RYAN SALAZAR