6459 N SATSUMA AVE 91606
Certificate Information: 6459 N SATSUMA AVE 91606
- Application / Permit
- 23010-10000-02482
- Plan Check / Job No.
- B23LA10949
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) DETACHED ADU PER LAMC 12.22A.33 (c) AND (d) "COMPLY WITH DEPARTMENT ORDER effective date 05/10/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
- Permit Issued
- Issued on 3/1/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/13/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/29/2023 | MARCELA FRANQUEZ |
| Corrections Issued | 7/12/2023 | MARCELA FRANQUEZ |
| Quality Review Completed | 7/20/2023 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 7/31/2023 | APPLICANT |
| Plan Check Approved | 2/28/2024 | MARCELA FRANQUEZ |
| Issued | 3/1/2024 | APPLICANT |
| CofO in Progress | 11/26/2024 | THOMAS WOODS |
| CofO Issued | 12/5/2024 | DAVID JAMES |
| Permit Finaled | 12/5/2024 | DAVID JAMES |
Permit Application Clearance Information
| Address approval | Cleared | 8/2/2023 | MEGAN GODINEZ |
| Roof/Waste drainage to street | Cleared | 8/2/2023 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/15/2023 | MEGAN GODINEZ |
| Sewer availability | Cleared | 9/15/2023 | MEGAN GODINEZ |
| Construction near power lines | Cleared | 10/3/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 10/3/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HAGOP BADOSSIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIO CUEVAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/21/2024 | Corrections Issued | THOMAS WOODS |
| Footing/Foundation/Slab | 4/4/2024 | Corrections Issued | THOMAS WOODS |
| BUILDING-Rough-Frame | 6/26/2024 | Not Ready for Inspection | THOMAS WOODS |
| ELECTRICAL-Rough | 6/26/2024 | Approved | THOMAS WOODS |
| Footing/Foundation/Slab | 6/26/2024 | Approved | THOMAS WOODS |
| Green Building Rough | 6/26/2024 | Approved | THOMAS WOODS |
| HVAC-Rough | 6/26/2024 | Approved | THOMAS WOODS |
| PLUMBING-Rough | 6/26/2024 | Approved | THOMAS WOODS |
| Rough-Elec/Plmb/HVAC | 6/26/2024 | Approved | THOMAS WOODS |
| Verify Sprinkler Sign Off | 6/26/2024 | Not Ready for Inspection | THOMAS WOODS |
| Wood Frame | 6/26/2024 | Approved | THOMAS WOODS |
| Insulation | 7/11/2024 | Approved | THOMAS WOODS |
| Underground Mechanical | 7/11/2024 | Approved | THOMAS WOODS |
| Floor/Roof Diaphrgm/Shear Wall | 7/22/2024 | Partial Approval | THOMAS WOODS |
| Sewer | 7/22/2024 | Approved | THOMAS WOODS |
| Wood Frame | 8/8/2024 | Approved | THOMAS WOODS |
| Insulation | 8/12/2024 | Approved | THOMAS WOODS |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2024 | Approved | THOMAS WOODS |
| Interior/Exterior Lathing | 9/16/2024 | Approved | THOMAS WOODS |
| BUILDING-Rough-Frame | 11/12/2024 | Not Ready for Inspection | THOMAS WOODS |
| Drywall Nailing | 11/12/2024 | Approved | THOMAS WOODS |
| Final | 11/12/2024 | Not Ready for Inspection | THOMAS WOODS |
| Green Building Final | 11/12/2024 | Approved | THOMAS WOODS |
| SGSOV-Seismic Gas S/O Valve | 11/12/2024 | SGSOV Approved | THOMAS WOODS |
| Service/Power Release | 11/12/2024 | Not Ready for Inspection | THOMAS WOODS |
| Smoke Detectors | 11/12/2024 | Corrections Issued | THOMAS WOODS |
| Verify Sprinkler Sign Off | 11/12/2024 | Not Ready for Inspection | THOMAS WOODS |
| BUILDING-Rough-Frame | 11/20/2024 | Approved | THOMAS WOODS |
| ELECTRICAL-Final | 11/20/2024 | Approved | THOMAS WOODS |
| Final | 11/20/2024 | OK to Issue CofO | THOMAS WOODS |
| HVAC-Final | 11/20/2024 | Approved | THOMAS WOODS |
| PLUMBING-Final | 11/20/2024 | Approved | THOMAS WOODS |
| Service/Power Release | 11/20/2024 | Approved | THOMAS WOODS |
| Smoke Detectors | 11/20/2024 | Approved | THOMAS WOODS |
| Deputy Drilled-In Anchors | 11/21/2024 | Approved | THOMAS WOODS |