2803 S HOBART BLVD 90018

Certificate Information: 2803 S HOBART BLVD 90018

Application / Permit
23010-10000-02477
Plan Check / Job No.
B23LA10925
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan New Detached ADU 24'-5" by 27'-5"
Permit Issued
Issued on 10/25/2023
Issuing Office
Current Status
CofO Issued on 9/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/12/2023 APPLICANT
Assigned to Plan Check Engineer 6/15/2023 ARSALAN SHABESTARI
Corrections Issued 6/17/2023 ARSALAN SHABESTARI
Quality Review Completed 6/27/2023 GARO TELMI
Plan Check Approved 10/24/2023 ARSALAN SHABESTARI
Issued 10/25/2023 APPLICANT
CofO Issued 9/17/2024 DEROLD HAUFF
Permit Finaled 9/17/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/7/2023 CHRISTINA BRACO
Eng Process Fee Ord 176,300 Cleared 7/11/2023 CHRISTINA BRACO
Sewer availability Cleared 7/11/2023 CHRISTINA BRACO
Community Plan Implem. Overlay Cleared 8/3/2023 MANERI ROMAN
Low Impact Development (LID) Cleared 8/3/2023 MITESH PATEL
Roof/Waste drainage to street Cleared 8/4/2023 CHRISTINA BRACO
Construction near power lines Cleared 10/16/2023 RIDWAN HARDY

Contact Information

Contractor Maestro Construction Inc; Lic. No.: 1060987-B       ,

Inspector Information

WILLIAM SIERRA, (213) 202-3122 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

METHANE-Barrier 11/13/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
METHANE-Subgrade 11/13/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
PLUMBING-Rough 11/13/2023 Partial Approval KATHRYN BUTTERWORTH
Sewer 11/13/2023 Corrections Issued KATHRYN BUTTERWORTH
Footing/Foundation/Slab 12/4/2023 Corrections Issued KATHRYN BUTTERWORTH
METHANE-Barrier 12/4/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
METHANE-Subgrade 12/4/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
Footing/Foundation/Slab 12/7/2023 Corrections Issued ALIZAH MAYAGOITIA
METHANE-Barrier 12/7/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
METHANE-Subgrade 12/7/2023 Approved ALIZAH MAYAGOITIA
Footing/Foundation/Slab 12/15/2023 Partial Approval KATHRYN BUTTERWORTH
METHANE-Barrier 12/15/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
Deputy Methane Barrier 1/3/2024 Conditional Approval KATHRYN BUTTERWORTH
Deputy Methane Barrier 1/4/2024 Conditional Approval KATHRYN BUTTERWORTH
Deputy Methane Barrier 1/8/2024 Approved KATHRYN BUTTERWORTH
Footing/Foundation/Slab 1/8/2024 Approved KATHRYN BUTTERWORTH
METHANE-Barrier 1/8/2024 Approved KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 3/18/2024 Approved ARTHUR NEGRETE
ELECTRICAL-Rough 3/18/2024 Approved ARTHUR NEGRETE
HVAC-Rough 3/18/2024 Approved ARTHUR NEGRETE
METHANE-Rough 3/18/2024 Approved ARTHUR NEGRETE
PLUMBING-Rough 3/18/2024 Approved ARTHUR NEGRETE
Verify Sprinkler Sign Off 3/18/2024 Approved ARTHUR NEGRETE
Insulation 3/28/2024 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 3/28/2024 Approved ARTHUR NEGRETE
Drywall Nailing 4/3/2024 Approved ARTHUR NEGRETE
PLUMBING-Rough 4/3/2024 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 4/10/2024 Approved BRENDAN MORELLI
Shower Pan 4/10/2024 Approved BRENDAN MORELLI
Underground Mechanical 4/10/2024 Partial Approval BRENDAN MORELLI
ELECTRICAL-Final 6/17/2024 Approved JOSEPH MCGARRY
Final 6/17/2024 Corrections Issued JOSEPH MCGARRY
PLUMBING-Final 6/17/2024 Corrections Issued JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 6/17/2024 SGSOV Approved JOSEPH MCGARRY
Service/Power Release 6/17/2024 Not Required JOSEPH MCGARRY
Smoke Detectors 6/17/2024 Approved JOSEPH MCGARRY
Final 6/25/2024 Corrections Issued JOSEPH MCGARRY
Final 7/9/2024 Corrections Issued JOSEPH MCGARRY
Final 8/9/2024 Corrections Issued WILLIAM SIERRA
Final 8/22/2024 Conditional Approval WILLIAM SIERRA
Service/Power Release 8/26/2024 Approved WILLIAM SIERRA