7614 S GODDARD AVE 90045
Certificate Information: 7614 S GODDARD AVE 90045
- Application / Permit
- 23010-10000-02456
- Plan Check / Job No.
- B23LA10796
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: (N) 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33.(c)-(d)
- Permit Issued
- Issued on 2/19/2024
- Issuing Office
- Current Status
- CofO Issued on 2/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/29/2023 | DANIEL YIP |
| Corrections Issued | 7/3/2023 | DANIEL YIP |
| Quality Review Completed | 7/6/2023 | GARO TELMI |
| Plan Check Approved | 1/30/2024 | DANIEL YIP |
| Issued | 2/19/2024 | APPLICANT |
| CofO in Progress | 1/30/2025 | BOBBY KEY |
| Permit Finaled | 2/19/2025 | RICHARD STEINBACH |
| CofO Issued | 2/19/2025 | RICHARD STEINBACH |
| Permit Finaled | 2/19/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Specific Plan | Cleared | 7/12/2023 | ALESSANDRO MERCURI |
| Address approval | Cleared | 7/13/2023 | KIMBERLY HERNANDEZ |
| Construction near power lines | Cleared | 9/1/2023 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 9/21/2023 | AHMED AMARRAGY |
| Eng Process Fee Ord 176,300 | Cleared | 1/22/2024 | VLADIMIR ARUTYUNYAN |
| Sewer availability | Cleared | 1/22/2024 | VLADIMIR ARUTYUNYAN |
| Grading Pre-Inspection | Cleared | 1/30/2024 | DANIEL YIP |
Contact Information
| Architect | Hefner,, Charles David; Lic. No.: C23963 | 6320 VAN NUYS BOULEVARD #225 VAN NUYS, CA 91401 |
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/9/2024 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2024 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 5/20/2024 | Approved | BOBBY KEY |
| PLUMBING-Rough | 5/20/2024 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/23/2024 | Partial Approval | BOBBY KEY |
| Sewer | 7/8/2024 | Approved | JESUS PINEDA |
| Underground Mechanical | 7/8/2024 | Partial Approval | JESUS PINEDA |
| ELECTRICAL-Rough | 7/31/2024 | Not Ready for Inspection | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/31/2024 | Corrections Issued | BOBBY KEY |
| HVAC-Rough | 7/31/2024 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Rough | 7/31/2024 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 8/7/2024 | Not Ready for Inspection | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2024 | Approved | BOBBY KEY |
| HVAC-Rough | 8/7/2024 | Corrections Issued | BOBBY KEY |
| MERV13>=Rough | 8/7/2024 | Approved | BOBBY KEY |
| PLUMBING-Rough | 8/7/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 8/13/2024 | Approved | BOBBY KEY |
| HVAC-Rough | 8/13/2024 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 8/20/2024 | Approved | BOBBY KEY |
| Green Building Rough | 8/20/2024 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 8/20/2024 | Approved | BOBBY KEY |
| Insulation | 8/26/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Pre-Inspection | 9/9/2024 | Partial Inspection | BOBBY KEY |
| Drywall Nailing | 9/16/2024 | Approved | TEMISTOCLES CAAL |
| Insulation | 9/16/2024 | Approved | TEMISTOCLES CAAL |
| Shower Pan | 9/16/2024 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 9/18/2024 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 12/24/2024 | Corrections Issued | BOBBY KEY |
| HVAC-Final | 12/24/2024 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 12/24/2024 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Final | 1/2/2025 | Not Ready for Inspection | JESUS PINEDA |
| HVAC-Final | 1/2/2025 | Approved | JESUS PINEDA |
| PLUMBING-Final | 1/2/2025 | Not Ready for Inspection | JESUS PINEDA |
| Service/Power Release | 1/2/2025 | Not Ready for Inspection | JESUS PINEDA |
| Special/Order Compliance | 1/2/2025 | Corrections Issued | JESUS PINEDA |
| ELECTRICAL-Final | 1/23/2025 | Approved | EVAN COOPER |
| Final | 1/23/2025 | Not Ready for Inspection | EVAN COOPER |
| Green Building Final | 1/23/2025 | Approved | EVAN COOPER |
| MERV13>=Final | 1/23/2025 | Approved | EVAN COOPER |
| PLUMBING-Final | 1/23/2025 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 1/23/2025 | SGSOV Approved | EVAN COOPER |
| Service/Power Release | 1/23/2025 | Approved | EVAN COOPER |
| Smoke Detectors | 1/23/2025 | Approved | EVAN COOPER |
| Final | 1/30/2025 | OK to Issue CofO | BOBBY KEY |
| Service/Power Release | 1/30/2025 | Approved | BOBBY KEY |