1942 N CANYON DR 90068

Certificate Information: 1942 N CANYON DR 90068

Application / Permit
23010-10000-02453
Plan Check / Job No.
B23LA10795
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
**eplan** Addition and convert (E) rec room to detached ADU per LAMC 12.22A.33 (c) and (d). Remove existing carport
Permit Issued
Issued on 1/9/2024
Issuing Office
Current Status
CofO Issued on 12/18/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/19/2023 APPLICANT
Assigned to Plan Check Engineer 8/3/2023 MARCELA FRANQUEZ
Corrections Issued 8/11/2023 MARCELA FRANQUEZ
Quality Review Completed 8/23/2023 TU HUA
Applicant returned to address corrections 10/11/2023 MARCELA FRANQUEZ
Plan Check Approved 11/2/2023 MARCELA FRANQUEZ
Issued 1/9/2024 APPLICANT
CofO in Progress 10/29/2024 CRAIG VAUGHAN
No Progress 11/16/2024 DEROLD HAUFF
CofO in Progress 11/16/2024 DEROLD HAUFF
CofO Issued 12/18/2024 DEROLD HAUFF
Permit Finaled 12/18/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/19/2023 TERRY PHAN
Roof/Waste drainage to street Cleared 8/19/2023 TERRY PHAN
Miscellaneous Cleared 8/21/2023 YINGSHI HUANG
HPOZ Cleared 8/30/2023 MICAELA TORRES-GIL
Miscellaneous Cleared 8/30/2023 MICAELA TORRES-GIL
ZI Cleared 8/30/2023 MICAELA TORRES-GIL
Grading Pre-Inspection Cleared 9/1/2023 RUSSELL BONVOULOIR
Eng Process Fee Ord 176,300 Cleared 9/14/2023 TERRY PHAN
Sewer availability Cleared 9/14/2023 TERRY PHAN
Watercourse Cleared 9/14/2023 TERRY PHAN
Miscellaneous Cleared 10/11/2023 MICAELA TORRES-GIL

Contact Information

Contractor M D H Builders / Design / Development; Lic. No.: 1067773-B       ,
Engineer Yamini,, Soly; Lic. No.: C33719 540 WARNER AVE      LOS ANGELES, CA 90024

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/18/2024 Approved BRIAN SULLIVAN
Deputy Steel/Welding 2/16/2024 Conditional Approval ROY SPAULDING
Floor/Roof Diaphrgm/Shear Wall 2/22/2024 Approved ROY SPAULDING
Deputy Wood Construction 2/23/2024 Conditional Approval ROY SPAULDING
ELECTRICAL-Rough 3/22/2024 Approved ROY SPAULDING
HVAC-Rough 3/22/2024 Approved ROY SPAULDING
PLUMBING-Rough 3/22/2024 Approved ROY SPAULDING
BUILDING-Rough-Frame 3/29/2024 Partial Approval ROY SPAULDING
Green Building Rough 3/29/2024 Not Ready for Inspection ROY SPAULDING
Interior/Exterior Lathing 4/15/2024 Partial Approval ROY SPAULDING
Shower Pan 4/15/2024 Approved ROY SPAULDING
BUILDING-Rough-Frame 5/20/2024 Corrections Issued BRIAN SULLIVAN
Green Building Rough 5/20/2024 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 5/23/2024 Partial Approval BRIAN SULLIVAN
Insulation 6/5/2024 Approved ROY SPAULDING
Interior/Exterior Lathing 6/5/2024 Approved ROY SPAULDING
Drywall Nailing 6/12/2024 Approved ROY SPAULDING
BUILDING-Rough-Frame 9/27/2024 Approved CRAIG VAUGHAN
Final 9/27/2024 Corrections Issued CRAIG VAUGHAN
Green Building Final 9/27/2024 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 9/27/2024 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 9/27/2024 Approved CRAIG VAUGHAN
Final 10/2/2024 Corrections Issued CRAIG VAUGHAN
Final 10/9/2024 Corrections Issued BRIAN SULLIVAN
Final 10/15/2024 Corrections Issued CRAIG VAUGHAN
Final 10/28/2024 OK to Issue CofO CRAIG VAUGHAN