1898 S CLYDE AVE 90019
Certificate Information: 1898 S CLYDE AVE 90019
- Application / Permit
- 23010-10000-02420
- Plan Check / Job No.
- B23LA10687
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan New 2-story detached ADU 26'x19'
- Permit Issued
- Issued on 9/3/2023
- Issuing Office
- Current Status
- CofO Issued on 4/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/8/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/22/2023 | ARSALAN SHABESTARI |
| Corrections Issued | 7/20/2023 | ARSALAN SHABESTARI |
| Quality Review Completed | 8/8/2023 | FARUK SEZER |
| Plan Check Approved | 9/2/2023 | ARSALAN SHABESTARI |
| Issued | 9/3/2023 | APPLICANT |
| CofO in Progress | 4/9/2024 | ALIZAH MAYAGOITIA |
| Permit Finaled | 4/16/2024 | DEROLD HAUFF |
| CofO Issued | 4/16/2024 | DEROLD HAUFF |
| Permit Finaled | 4/16/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/12/2023 | TERRY PHAN |
| Eng Process Fee Ord 176,300 | Cleared | 8/15/2023 | TERRY PHAN |
| Sewer availability | Cleared | 8/15/2023 | TERRY PHAN |
| Roof/Waste drainage to street | Cleared | 8/16/2023 | TERRY PHAN |
Contact Information
| Contractor | Primary Design Builders Inc; Lic. No.: 1036604-B | , |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/25/2023 | Approved | JOSE AVILA |
| Footing/Foundation/Slab | 10/25/2023 | Approved | JOSE AVILA |
| PLUMBING-Rough | 10/25/2023 | Partial Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 11/17/2023 | Partial Approval | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 12/7/2023 | Conditional Approval | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 12/13/2023 | Corrections Issued | SCOTT FINNILA |
| ELECTRICAL-Rough | 12/13/2023 | Approved | SCOTT FINNILA |
| Green Building Rough | 12/13/2023 | Corrections Issued | SCOTT FINNILA |
| HVAC-Rough | 12/13/2023 | Approved | SCOTT FINNILA |
| PLUMBING-Rough | 12/13/2023 | Approved | SCOTT FINNILA |
| Verify Sprinkler Sign Off | 12/13/2023 | Partial Inspection | SCOTT FINNILA |
| BUILDING-Rough-Frame | 12/20/2023 | Not Ready for Inspection | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2023 | Not Ready for Inspection | RONNIE MINDANAO |
| Green Building Rough | 12/20/2023 | Corrections Issued | RONNIE MINDANAO |
| Interior/Exterior Lathing | 12/20/2023 | Not Ready for Inspection | RONNIE MINDANAO |
| Shower Pan | 12/20/2023 | Not Ready for Inspection | RONNIE MINDANAO |
| Verify Sprinkler Sign Off | 12/20/2023 | Not Ready for Inspection | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 12/26/2023 | Partial Approval | RONNIE MINDANAO |
| Green Building Final | 12/26/2023 | Not Ready for Inspection | RONNIE MINDANAO |
| Insulation | 12/26/2023 | Not Ready for Inspection | RONNIE MINDANAO |
| Interior/Exterior Lathing | 12/26/2023 | Conditional Approval | RONNIE MINDANAO |
| Shower Pan | 12/26/2023 | Approved | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 1/4/2024 | Approved | RONNIE MINDANAO |
| Green Building Rough | 1/4/2024 | Approved | RONNIE MINDANAO |
| Insulation | 1/9/2024 | Approved | RONNIE MINDANAO |
| Drywall Nailing | 1/12/2024 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 3/22/2024 | Not Ready for Inspection | STUART CHAPMAN |
| Final | 3/22/2024 | Corrections Issued | STUART CHAPMAN |
| Green Building Final | 3/22/2024 | Approved | STUART CHAPMAN |
| HVAC-Final | 3/22/2024 | Not Ready for Inspection | STUART CHAPMAN |
| PLUMBING-Final | 3/22/2024 | Not Ready for Inspection | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 3/22/2024 | SGSOV Not Ready | STUART CHAPMAN |
| Service/Power Release | 3/22/2024 | Not Ready for Inspection | STUART CHAPMAN |
| Smoke Detectors | 3/22/2024 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 3/27/2024 | Approved | STUART CHAPMAN |
| Final | 3/27/2024 | Corrections Issued | STUART CHAPMAN |
| HVAC-Final | 3/27/2024 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 3/27/2024 | Approved | STUART CHAPMAN |
| Service/Power Release | 3/27/2024 | Not Ready for Inspection | STUART CHAPMAN |
| Final | 4/3/2024 | Corrections Issued | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 4/3/2024 | SGSOV Approved | RICHARD DOCKUS |
| Final | 4/8/2024 | OK to Issue CofO | ALIZAH MAYAGOITIA |
| Service/Power Release | 4/8/2024 | Approved | ALIZAH MAYAGOITIA |