233-233 1/2 W 98TH ST 90003

Certificate Information: 233-233 1/2 W 98TH ST 90003

Application / Permit
23010-10000-02397
Plan Check / Job No.
B23LA10595
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
ePLan - (n) 2-story duplex w/ attached garage R3/U Occupancy NFPA 13R sprinklered throughout
Permit Issued
Issued on 12/12/2023
Issuing Office
Current Status
CofO Issued on 8/9/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/8/2023 APPLICANT
Assigned to Plan Check Engineer 6/8/2023 KELVIN CHUONG
Corrections Issued 6/12/2023 KELVIN CHUONG
Quality Review Completed 6/13/2023 RODOLFO ARIAS
Applicant returned to address corrections 9/22/2023 KELVIN CHUONG
Applicant returned to address corrections 11/6/2023 KELVIN CHUONG
Applicant returned to address corrections 11/21/2023 KELVIN CHUONG
Plan Check Approved 11/30/2023 KELVIN CHUONG
Issued 12/12/2023 APPLICANT
CofO in Progress 6/27/2024 BEN MOLSTAD
Permit Finaled 8/9/2024 ANSON MAGLASANG
CofO Issued 8/9/2024 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 6/29/2023 JESSICA OPINION
Low Impact Development (LID) Cleared 6/30/2023 VICTOR MENDOZA
Sewer availability Cleared 7/3/2023 JESSICA OPINION
Frnt yard landscape/Water mgmt Cleared 7/6/2023 MAYELA VILLA
Roof/Waste drainage to street Cleared 7/9/2023 AHMED AMARRAGY
Trees in Parkway Cleared 7/11/2023 ADALBERTO VERA
SB8 RUD Cleared 7/25/2023 PETER MONTI
Eng Process Fee Ord 176,300 Cleared 7/30/2023 AHMED AMARRAGY
Hydrant and Access approval Cleared 8/30/2023 KURT CORRAL

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: NA81695       ,

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/16/2024 Approved JAMES CHAVEZ
Footing/Foundation/Slab 1/16/2024 Approved JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 2/2/2024 Partial Approval JOHN KLARIN
Insulation 2/2/2024 Partial Approval JOHN KLARIN
Underground Mechanical 2/2/2024 Partial Approval JOHN KLARIN
Wood Frame 2/2/2024 Partial Approval JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 2/14/2024 Partial Approval JAMES CHAVEZ
HVAC-Rough 2/29/2024 No Access for Inspection BEN MOLSTAD
PLUMBING-Rough 2/29/2024 No Access for Inspection BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 3/11/2024 Partial Approval JAMES CHAVEZ
HVAC-Rough 3/18/2024 Not Ready for Inspection BEN MOLSTAD
PLUMBING-Rough 3/18/2024 Approved BEN MOLSTAD
BUILDING-Rough-Frame 3/19/2024 Not Ready for Inspection BEN MOLSTAD
ELECTRICAL-Rough 3/19/2024 Not Ready for Inspection BEN MOLSTAD
Green Building Rough 3/19/2024 Not Ready for Inspection BEN MOLSTAD
HVAC-Rough 3/19/2024 Corrections Issued BEN MOLSTAD
MERV13>=Rough 3/19/2024 Not Ready for Inspection BEN MOLSTAD
Verify Sprinkler Sign Off 3/19/2024 Not Ready for Inspection BEN MOLSTAD
ELECTRICAL-Rough 3/20/2024 Approved JAMES CHAVEZ
ELECTRICAL-Rough 3/22/2024 Not Ready for Inspection BEN MOLSTAD
HVAC-Rough 3/22/2024 Corrections Issued BEN MOLSTAD
HVAC-Rough 3/26/2024 Approved BEN MOLSTAD
Insulation 3/26/2024 Not Ready for Inspection BEN MOLSTAD
Special/Order Compliance 3/26/2024 Not Ready for Inspection BEN MOLSTAD
BUILDING-Rough-Frame 3/27/2024 Partial Approval BEN MOLSTAD
Green Building Rough 3/27/2024 Approved BEN MOLSTAD
MERV13>=Rough 3/27/2024 Approved BEN MOLSTAD
Verify Sprinkler Sign Off 3/27/2024 Approved BEN MOLSTAD
Wood Frame 3/27/2024 Not Ready for Inspection BEN MOLSTAD
Insulation 4/1/2024 Approved BEN MOLSTAD
Interior/Exterior Lathing 4/2/2024 Partial Approval BEN MOLSTAD
Interior/Exterior Lathing 4/8/2024 Partial Approval JAMES CHAVEZ
Drywall Nailing 4/17/2024 Approved BEN MOLSTAD
ELECTRICAL-Final 5/23/2024 Corrections Issued BEN MOLSTAD
Pre-Inspection 5/24/2024 Corrections Issued BEN MOLSTAD
Special/Order Compliance 5/28/2024 Conditional Approval JAMES CHAVEZ
BUILDING-Rough-Frame 6/21/2024 Approved BEN MOLSTAD
ELECTRICAL-Final 6/21/2024 Corrections Issued BEN MOLSTAD
Final 6/21/2024 Not Ready for Inspection BEN MOLSTAD
Green Building Final 6/21/2024 Approved BEN MOLSTAD
HVAC-Final 6/21/2024 Corrections Issued BEN MOLSTAD
MERV13>=Final 6/21/2024 Approved BEN MOLSTAD
PLUMBING-Final 6/21/2024 Corrections Issued BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 6/21/2024 SGSOV Approved BEN MOLSTAD
Service/Power Release 6/21/2024 Not Ready for Inspection BEN MOLSTAD
Smoke Detectors 6/21/2024 Corrections Issued BEN MOLSTAD
ELECTRICAL-Final 6/26/2024 Approved BEN MOLSTAD
Final 6/26/2024 OK to Issue CofO BEN MOLSTAD
HVAC-Final 6/26/2024 Approved BEN MOLSTAD
PLUMBING-Final 6/26/2024 Approved BEN MOLSTAD
Service/Power Release 6/26/2024 Approved BEN MOLSTAD
Smoke Detectors 6/26/2024 Approved BEN MOLSTAD
Special/Order Compliance 6/26/2024 Approved BEN MOLSTAD