12923 W FERNDALE AVE 90066
Certificate Information: 12923 W FERNDALE AVE 90066
- Application / Permit
- 23010-10000-02352
- Plan Check / Job No.
- B23LA10387
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: NEW TWO STORY DETACHED ADUPER LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 12/3/2024
- Issuing Office
- Current Status
- Issued on 12/3/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/5/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/22/2023 | CRYSTEL MAALOUF |
| Corrections Issued | 6/28/2023 | KHEDER ALRAZAA |
| Quality Review Completed | 7/7/2023 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 11/9/2023 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 11/13/2023 | CRYSTEL MAALOUF |
| Plan Check Approved | 1/23/2024 | CRYSTEL MAALOUF |
| Issued | 12/3/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/11/2023 | JASON NG |
| Eng Process Fee Ord 176,300 | Cleared | 7/13/2023 | JASON NG |
| Sewer availability | Cleared | 7/13/2023 | JASON NG |
| Grading Pre-Inspection | Cleared | 7/19/2023 | MICHAEL TEMPLE |
| Miscellaneous | Cleared | 7/23/2023 | AHMED AMARRAGY |
| Specific Plan | Cleared | 8/2/2023 | JOSHUA JONES |
| Construction near power lines | Cleared | 8/21/2023 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 8/26/2023 | JOHN CONNEALLY |
| Low Impact Development (LID) | Cleared | 10/4/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 10/11/2023 | ANTHONY MAINEZ |
| GPI Written Notices | Cleared | 1/23/2024 | KHEDER ALRAZAA |
Contact Information
| Architect | Driscoll,, Christopher; Lic. No.: NA36073 | , |
| Contractor | Bless It Construction Inc; Lic. No.: 1048746-B | , |
| Engineer | Garcia,, Ricardo Ray; Lic. No.: C66957 | 27702 QUINCY ST CASTAIC, CA 91384 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Service/Power Release | 6/8/2026 Time Frame: 10-12 |
| Final | 6/8/2026 Time Frame: 10-12 |
Inspection Request History
| Sewer | 5/23/2025 | Approved | MICHAEL ALLEN |
| Underground Mechanical | 5/23/2025 | Approved | MICHAEL ALLEN |
| Excavation/Setback/Form/Re-Bar | 6/6/2025 | Approved | MICHAEL ALLEN |
| Footing/Foundation/Slab | 6/6/2025 | Approved | MICHAEL ALLEN |
| Structural Steel Frame | 6/20/2025 | Conditional Approval | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 6/25/2025 | Partial Approval | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2025 | Partial Approval | MICHAEL ALLEN |
| Deputy Wood Construction | 8/6/2025 | Conditional Approval | WILBER ROSALES |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2025 | Approved | WILBER ROSALES |
| BUILDING-Rough-Frame | 10/14/2025 | Approved | WILBER ROSALES |
| ELECTRICAL-Rough | 10/14/2025 | Partial Approval | WILBER ROSALES |
| HVAC-Rough | 10/14/2025 | Approved | WILBER ROSALES |
| Interior/Exterior Lathing | 10/14/2025 | Partial Approval | WILBER ROSALES |
| PLUMBING-Rough | 10/14/2025 | Approved | WILBER ROSALES |
| Verify Sprinkler Sign Off | 10/14/2025 | Approved | WILBER ROSALES |
| Insulation | 10/23/2025 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 10/30/2025 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 11/25/2025 | Approved | WILBER ROSALES |
| Shower Pan | 11/25/2025 | Approved | WILBER ROSALES |
| Final | 3/26/2026 | Corrections Issued | DAKOTA LOW |
| SGSOV-Seismic Gas S/O Valve | 3/26/2026 | SGSOV Not Required | DAKOTA LOW |
| Service/Power Release | 3/26/2026 | Not Ready for Inspection | DAKOTA LOW |
| Smoke Detectors | 3/26/2026 | Approved | DAKOTA LOW |
| ELECTRICAL-Final | 4/2/2026 | Approved | DAKOTA LOW |
| HVAC-Final | 4/2/2026 | Corrections Issued | DAKOTA LOW |
| PLUMBING-Final | 4/2/2026 | Corrections Issued | DAKOTA LOW |