4219 N COSTELLO AVE 91423

Certificate Information: 4219 N COSTELLO AVE 91423

Application / Permit
23010-10000-02349
Plan Check / Job No.
B23LA09289
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
ePlan. New 1-story 13'x19'6" recreation room with exterior full bathroom for pool access.
Permit Issued
Issued on 4/10/2024
Issuing Office
Current Status
CofO Issued on 9/26/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/18/2023 APPLICANT
Assigned to Plan Check Engineer 5/18/2023 TU HUA
Corrections Issued 6/5/2023 TU HUA
Quality Review Completed 6/13/2023 CHAD DOI
Applicant returned to address corrections 11/2/2023 TU HUA
Applicant returned to address corrections 2/1/2024 TU HUA
Applicant returned to address corrections 3/5/2024 TU HUA
Plan Check Approved 3/8/2024 TU HUA
Issued 4/10/2024 APPLICANT
CofO in Progress 9/11/2025 MISAEL ESPARZA
Permit Finaled 9/26/2025 RUBEN SALAS
CofO Issued 9/26/2025 RUBEN SALAS
Permit Finaled 9/26/2025 RUBEN SALAS

Permit Application Clearance Information

Sewer availability Cleared 6/14/2023 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 6/16/2023 DAGOVERTO GUERRERO
Construction near power lines Cleared 8/9/2023 RIDWAN HARDY
Construction within easement Cleared 8/9/2023 RIDWAN HARDY
Low Impact Development Cleared 8/29/2023 SAMUEL LINN
Roof/Waste drainage to street Cleared 8/29/2023 DAGOVERTO GUERRERO
Grading Pre-Inspection Cleared 2/2/2024 TU HUA
GPI Written Notices Cleared 3/8/2024 TU HUA

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/7/2024 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 6/21/2024 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 6/27/2024 Approved JOHN COLEMAN
Underground Mechanical 7/22/2024 Approved KEVIN BERBERYAN
Deputy Reinf. Concrete 10/15/2024 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 11/26/2024 Partial Approval MISAEL ESPARZA
PLUMBING-Rough 12/27/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
PLUMBING-Rough 12/30/2024 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 1/15/2025 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 1/27/2025 Partial Inspection MISAEL ESPARZA
Shower Pan 1/27/2025 Partial Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 1/30/2025 Partial Approval MISAEL ESPARZA
Wood Frame 1/30/2025 Partial Approval MISAEL ESPARZA
Interior/Exterior Lathing 2/6/2025 Partial Approval MISAEL ESPARZA
Shower Pan 2/6/2025 Approved MISAEL ESPARZA
Interior/Exterior Lathing 2/14/2025 Not Ready for Inspection MISAEL ESPARZA
Interior/Exterior Lathing 2/18/2025 Approved MISAEL ESPARZA
Insulation 3/5/2025 Corrections Issued MISAEL ESPARZA
Wood Frame 3/5/2025 Corrections Issued MISAEL ESPARZA
Drywall Nailing 3/13/2025 Approved JUAN VALENZUELA
BUILDING-Rough-Frame 8/15/2025 Conditional Approval MISAEL ESPARZA
ELECTRICAL-Final 8/15/2025 Not Ready for Inspection MISAEL ESPARZA
Final 8/15/2025 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Final 8/15/2025 Corrections Issued MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 8/15/2025 SGSOV Approved MISAEL ESPARZA
Service/Power Release 8/15/2025 Not Required MISAEL ESPARZA
Smoke Detectors 8/15/2025 Approved MISAEL ESPARZA
Verify Sprinkler Sign Off 8/15/2025 Partial Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 8/26/2025 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Final 8/26/2025 Approved MISAEL ESPARZA
Final 8/26/2025 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Final 8/26/2025 Approved MISAEL ESPARZA
Verify Sprinkler Sign Off 8/26/2025 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 8/29/2025 Approved MISAEL ESPARZA
Final 8/29/2025 Corrections Issued MISAEL ESPARZA
Final 9/10/2025 OK to Issue CofO MISAEL ESPARZA