4219 N COSTELLO AVE 91423
Certificate Information: 4219 N COSTELLO AVE 91423
- Application / Permit
- 23010-10000-02349
- Plan Check / Job No.
- B23LA09289
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- ePlan. New 1-story 13'x19'6" recreation room with exterior full bathroom for pool access.
- Permit Issued
- Issued on 4/10/2024
- Issuing Office
- Current Status
- CofO Issued on 9/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/18/2023 | TU HUA |
| Corrections Issued | 6/5/2023 | TU HUA |
| Quality Review Completed | 6/13/2023 | CHAD DOI |
| Applicant returned to address corrections | 11/2/2023 | TU HUA |
| Applicant returned to address corrections | 2/1/2024 | TU HUA |
| Applicant returned to address corrections | 3/5/2024 | TU HUA |
| Plan Check Approved | 3/8/2024 | TU HUA |
| Issued | 4/10/2024 | APPLICANT |
| CofO in Progress | 9/11/2025 | MISAEL ESPARZA |
| Permit Finaled | 9/26/2025 | RUBEN SALAS |
| CofO Issued | 9/26/2025 | RUBEN SALAS |
| Permit Finaled | 9/26/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Sewer availability | Cleared | 6/14/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 6/16/2023 | DAGOVERTO GUERRERO |
| Construction near power lines | Cleared | 8/9/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 8/9/2023 | RIDWAN HARDY |
| Low Impact Development | Cleared | 8/29/2023 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 8/29/2023 | DAGOVERTO GUERRERO |
| Grading Pre-Inspection | Cleared | 2/2/2024 | TU HUA |
| GPI Written Notices | Cleared | 3/8/2024 | TU HUA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/7/2024 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 6/21/2024 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 6/27/2024 | Approved | JOHN COLEMAN |
| Underground Mechanical | 7/22/2024 | Approved | KEVIN BERBERYAN |
| Deputy Reinf. Concrete | 10/15/2024 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 11/26/2024 | Partial Approval | MISAEL ESPARZA |
| PLUMBING-Rough | 12/27/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 12/30/2024 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 1/15/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 1/27/2025 | Partial Inspection | MISAEL ESPARZA |
| Shower Pan | 1/27/2025 | Partial Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 1/30/2025 | Partial Approval | MISAEL ESPARZA |
| Wood Frame | 1/30/2025 | Partial Approval | MISAEL ESPARZA |
| Interior/Exterior Lathing | 2/6/2025 | Partial Approval | MISAEL ESPARZA |
| Shower Pan | 2/6/2025 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 2/14/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Interior/Exterior Lathing | 2/18/2025 | Approved | MISAEL ESPARZA |
| Insulation | 3/5/2025 | Corrections Issued | MISAEL ESPARZA |
| Wood Frame | 3/5/2025 | Corrections Issued | MISAEL ESPARZA |
| Drywall Nailing | 3/13/2025 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 8/15/2025 | Conditional Approval | MISAEL ESPARZA |
| ELECTRICAL-Final | 8/15/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 8/15/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Final | 8/15/2025 | Corrections Issued | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 8/15/2025 | SGSOV Approved | MISAEL ESPARZA |
| Service/Power Release | 8/15/2025 | Not Required | MISAEL ESPARZA |
| Smoke Detectors | 8/15/2025 | Approved | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 8/15/2025 | Partial Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 8/26/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Final | 8/26/2025 | Approved | MISAEL ESPARZA |
| Final | 8/26/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Final | 8/26/2025 | Approved | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 8/26/2025 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 8/29/2025 | Approved | MISAEL ESPARZA |
| Final | 8/29/2025 | Corrections Issued | MISAEL ESPARZA |
| Final | 9/10/2025 | OK to Issue CofO | MISAEL ESPARZA |