1230 1/2 W 58TH PL 90044

Certificate Information: 1230 1/2 W 58TH PL 90044

Application / Permit
23010-10000-02316
Plan Check / Job No.
B23LA10230
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1 STORY DETACHED ADU AT REAR OF THE PROPERTY PER ENGINEER DESIGN (1,200 SF max per Ordinance, LAMC 12.22 A.33 (c)-(d))
Permit Issued
Issued on 6/14/2024
Issuing Office
Metro
Current Status
Issued on 6/14/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/2/2023 APPLICANT
Assigned to Plan Check Engineer 6/8/2023 AUNG SOE
Corrections Issued 6/12/2023 AUNG SOE
Applicant returned to address corrections 3/15/2024 ALEXANDER JOO
Applicant returned to address corrections 4/29/2024 CRISTINA SALAZAR
Plan Check Approved 6/14/2024 DANIEL SMILEY
Issued 6/14/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 9/5/2023 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 9/6/2023 WALLIE JONG
Sewer availability Cleared 9/6/2023 WALLIE JONG
Low Impact Development (LID) Cleared 2/15/2024 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 2/21/2024 ERIK BEASLEY

Contact Information

Contractor Owner-Builder       ,
Engineer Dorta,, Michael Rohrs; Lic. No.: C72538 2445 VIA SONOMA      PALOS VERDES ESTATES, CA 90274

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Green Building Rough 10/31/2024 Not Ready for Inspection CRAIG DAVIS
Pre-Inspection 10/31/2024 Not Ready for Inspection CRAIG DAVIS
PLUMBING-Rough 11/26/2024 Corrections Issued CRAIG DAVIS
Excavation/Setback/Form/Re-Bar 12/31/2024 Corrections Issued BARRY HACHE
Underground Mechanical 12/31/2024 Corrections Issued BARRY HACHE
Excavation/Setback/Form/Re-Bar 1/7/2025 Partial Approval BARRY HACHE
Sewer 1/7/2025 Approved BARRY HACHE
Excavation/Setback/Form/Re-Bar 1/23/2025 Approved BARRY HACHE
Green Building Rough 2/28/2025 Corrections Issued BARRY HACHE
PLUMBING-Rough 2/28/2025 Corrections Issued BARRY HACHE
Sewer 2/28/2025 Approved BARRY HACHE
ELECTRICAL-Rough 7/2/2025 Corrections Issued BARRY HACHE
Floor/Roof Diaphrgm/Shear Wall 7/2/2025 Corrections Issued BARRY HACHE
PLUMBING-Rough 7/2/2025 Approved BARRY HACHE
Interior/Exterior Lathing 8/11/2025 Approved WAYNE REGESTER
Rough-Elec/Plmb/HVAC 8/11/2025 Corrections Issued WAYNE REGESTER
Shower Pan 8/11/2025 Approved WAYNE REGESTER
BUILDING-Rough-Frame 8/26/2025 Not Ready for Inspection BARRY HACHE
Green Building Rough 8/26/2025 Approved BARRY HACHE
Verify Sprinkler Sign Off 8/26/2025 Approved BARRY HACHE
ELECTRICAL-Final 9/4/2025 Corrections Issued BARRY HACHE
Insulation 9/4/2025 Approved BARRY HACHE
Drywall Nailing 9/10/2025 Approved BARRY HACHE
Interior/Exterior Lathing 9/10/2025 Approved BARRY HACHE