8102 S KENYON AVE 90045
Certificate Information: 8102 S KENYON AVE 90045
- Application / Permit
- 23010-10000-02303
- Plan Check / Job No.
- B23LA10180
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 13'-0"x40'-7" ACCESSORY DWELLING UNIT ATTACHED TO EXISTING GARAGE PER LAMC 12.22 A.33(c) and (d). WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 9/19/2023
- Issuing Office
- Current Status
- CofO Issued on 6/6/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/6/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/16/2023 | KAMYAR EMAMI |
| Corrections Issued | 7/3/2023 | KAMYAR EMAMI |
| Quality Review Completed | 7/13/2023 | OMID HEDAYAT |
| Applicant returned to address corrections | 8/14/2023 | KAMYAR EMAMI |
| Applicant returned to address corrections | 8/15/2023 | KAMYAR EMAMI |
| Plan Check Approved | 9/19/2023 | KAMYAR EMAMI |
| Issued | 9/19/2023 | APPLICANT |
| CofO in Progress | 6/5/2024 | BOBBY KEY |
| Permit Finaled | 6/6/2024 | DANIEL ORRANTE |
| Permit Finaled | 6/6/2024 | DANIEL ORRANTE |
| CofO Issued | 6/6/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 8/9/2023 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 8/9/2023 | DARIN LAM |
| Sewer availability | Cleared | 8/9/2023 | DARIN LAM |
| Low Impact Development (LID) | Cleared | 8/23/2023 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 8/27/2023 | AHMED AMARRAGY |
| Construction within easement | Cleared | 9/6/2023 | OSCAR CASTRO |
| Specific Plan | Cleared | 9/12/2023 | FREDDY GARCIA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Herrera,, Edgar E; Lic. No.: C67603 | 1929 GREENLEAF DR WEST COVINA, CA 91792 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/29/2023 | Partial Inspection | BOBBY KEY |
| PLUMBING-Rough | 10/25/2023 | Partial Approval | TEMISTOCLES CAAL |
| PLUMBING-Rough | 10/31/2023 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2023 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2023 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 11/30/2023 | Approved | BOBBY KEY |
| Excavation/Setback/Form/Re-Bar | 12/14/2023 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/3/2024 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 1/3/2024 | Partial Approval | BOBBY KEY |
| Wood Frame | 1/11/2024 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2024 | Partial Approval | BOBBY KEY |
| Underground Mechanical | 1/31/2024 | Partial Approval | BOBBY KEY |
| Pre-Inspection | 2/8/2024 | Partial Inspection | BOBBY KEY |
| ELECTRICAL-Rough | 2/14/2024 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 2/16/2024 | Approved | BOBBY KEY |
| PLUMBING-Rough | 2/16/2024 | Approved | BOBBY KEY |
| Shower Pan | 2/20/2024 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 2/22/2024 | Approved | BOBBY KEY |
| Green Building Rough | 2/22/2024 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 2/22/2024 | Approved | BOBBY KEY |
| Insulation | 2/26/2024 | Corrections Issued | HERBERT GIRON |
| Insulation | 2/29/2024 | Approved | BOBBY KEY |
| Drywall Nailing | 3/4/2024 | Approved | BOBBY KEY |
| Gas Test | 3/14/2024 | Not Ready for Inspection | BOBBY KEY |
| Gas Test | 3/18/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 4/12/2024 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 4/26/2024 | SGSOV Not Ready | TEMISTOCLES CAAL |
| Final | 5/21/2024 | Corrections Issued | BOBBY KEY |
| HVAC-Final | 5/21/2024 | Approved | BOBBY KEY |
| PLUMBING-Final | 5/21/2024 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 5/21/2024 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 5/21/2024 | Approved | BOBBY KEY |
| Final | 6/4/2024 | OK to Issue CofO | BOBBY KEY |
| PLUMBING-Final | 6/4/2024 | Approved | BOBBY KEY |
| Service/Power Release | 6/4/2024 | Approved | BOBBY KEY |