8102 S KENYON AVE 90045

Certificate Information: 8102 S KENYON AVE 90045

Application / Permit
23010-10000-02303
Plan Check / Job No.
B23LA10180
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 13'-0"x40'-7" ACCESSORY DWELLING UNIT ATTACHED TO EXISTING GARAGE PER LAMC 12.22 A.33(c) and (d). WORK DONE PER ENGINEERING.
Permit Issued
Issued on 9/19/2023
Issuing Office
Current Status
CofO Issued on 6/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/6/2023 APPLICANT
Assigned to Plan Check Engineer 6/16/2023 KAMYAR EMAMI
Corrections Issued 7/3/2023 KAMYAR EMAMI
Quality Review Completed 7/13/2023 OMID HEDAYAT
Applicant returned to address corrections 8/14/2023 KAMYAR EMAMI
Applicant returned to address corrections 8/15/2023 KAMYAR EMAMI
Plan Check Approved 9/19/2023 KAMYAR EMAMI
Issued 9/19/2023 APPLICANT
CofO in Progress 6/5/2024 BOBBY KEY
Permit Finaled 6/6/2024 DANIEL ORRANTE
Permit Finaled 6/6/2024 DANIEL ORRANTE
CofO Issued 6/6/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 8/9/2023 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 8/9/2023 DARIN LAM
Sewer availability Cleared 8/9/2023 DARIN LAM
Low Impact Development (LID) Cleared 8/23/2023 MITESH PATEL
Roof/Waste drainage to street Cleared 8/27/2023 AHMED AMARRAGY
Construction within easement Cleared 9/6/2023 OSCAR CASTRO
Specific Plan Cleared 9/12/2023 FREDDY GARCIA

Contact Information

Contractor Owner-Builder       ,
Engineer Herrera,, Edgar E; Lic. No.: C67603 1929 GREENLEAF DR      WEST COVINA, CA 91792

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/29/2023 Partial Inspection BOBBY KEY
PLUMBING-Rough 10/25/2023 Partial Approval TEMISTOCLES CAAL
PLUMBING-Rough 10/31/2023 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 11/14/2023 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 11/21/2023 Partial Approval BOBBY KEY
Footing/Foundation/Slab 11/30/2023 Approved BOBBY KEY
Excavation/Setback/Form/Re-Bar 12/14/2023 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 1/3/2024 Partial Approval BOBBY KEY
PLUMBING-Rough 1/3/2024 Partial Approval BOBBY KEY
Wood Frame 1/11/2024 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 1/31/2024 Partial Approval BOBBY KEY
Underground Mechanical 1/31/2024 Partial Approval BOBBY KEY
Pre-Inspection 2/8/2024 Partial Inspection BOBBY KEY
ELECTRICAL-Rough 2/14/2024 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 2/16/2024 Approved BOBBY KEY
PLUMBING-Rough 2/16/2024 Approved BOBBY KEY
Shower Pan 2/20/2024 Approved TEMISTOCLES CAAL
BUILDING-Rough-Frame 2/22/2024 Approved BOBBY KEY
Green Building Rough 2/22/2024 Approved BOBBY KEY
Interior/Exterior Lathing 2/22/2024 Approved BOBBY KEY
Insulation 2/26/2024 Corrections Issued HERBERT GIRON
Insulation 2/29/2024 Approved BOBBY KEY
Drywall Nailing 3/4/2024 Approved BOBBY KEY
Gas Test 3/14/2024 Not Ready for Inspection BOBBY KEY
Gas Test 3/18/2024 Approved BOBBY KEY
ELECTRICAL-Final 4/12/2024 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 4/26/2024 SGSOV Not Ready TEMISTOCLES CAAL
Final 5/21/2024 Corrections Issued BOBBY KEY
HVAC-Final 5/21/2024 Approved BOBBY KEY
PLUMBING-Final 5/21/2024 Corrections Issued BOBBY KEY
SGSOV-Seismic Gas S/O Valve 5/21/2024 SGSOV Approved BOBBY KEY
Smoke Detectors 5/21/2024 Approved BOBBY KEY
Final 6/4/2024 OK to Issue CofO BOBBY KEY
PLUMBING-Final 6/4/2024 Approved BOBBY KEY
Service/Power Release 6/4/2024 Approved BOBBY KEY