9412-9412 1/2 S SPRING ST 90003
Certificate Information: 9412-9412 1/2 S SPRING ST 90003
- Application / Permit
- 23010-10000-02275
- Plan Check / Job No.
- B23LA10006
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- ePlan - (n) 2-story duplex with attached garage R3/U occupancy NFPA 13D sprinklered throughout
- Permit Issued
- Issued on 12/18/2023
- Issuing Office
- Current Status
- CofO Issued on 7/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/31/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/1/2023 | KELVIN CHUONG |
| Corrections Issued | 6/6/2023 | KELVIN CHUONG |
| Quality Review Completed | 6/9/2023 | RODOLFO ARIAS |
| Applicant returned to address corrections | 7/11/2023 | KELVIN CHUONG |
| Applicant returned to address corrections | 9/22/2023 | KELVIN CHUONG |
| Applicant returned to address corrections | 10/30/2023 | KELVIN CHUONG |
| Applicant returned to address corrections | 11/6/2023 | KELVIN CHUONG |
| Applicant returned to address corrections | 11/21/2023 | KELVIN CHUONG |
| Plan Check Approved | 11/30/2023 | KELVIN CHUONG |
| Issued | 12/18/2023 | APPLICANT |
| CofO in Progress | 7/3/2024 | JAMES CHAVEZ |
| Permit Finaled | 7/5/2024 | ANSON MAGLASANG |
| CofO Issued | 7/5/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| Trees in Parkway | Cleared | 6/26/2023 | ADALBERTO VERA |
| Address approval | Cleared | 6/28/2023 | JESSICA OPINION |
| Frnt yard landscape/Water mgmt | Cleared | 6/28/2023 | NATHAN ROMINE |
| Permit | Cleared | 6/29/2023 | JESSICA OPINION |
| Hydrant and Access approval | Cleared | 7/12/2023 | LAVEON RIDER |
| Low Impact Development (LID) | Cleared | 7/17/2023 | MEGAN PINKUS |
| Eng Process Fee Ord 176,300 | Cleared | 7/19/2023 | JESSICA OPINION |
| Roof/Waste drainage to street | Cleared | 7/25/2023 | JESSICA OPINION |
| Sewer availability | Cleared | 7/25/2023 | JESSICA OPINION |
| SB8 RUD | Cleared | 8/23/2023 | SAMANTHA RIVERA |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: NA81695 | , |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/29/2024 | Approved | JAMES CHAVEZ |
| Footing/Foundation/Slab | 1/29/2024 | Approved | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 2/9/2024 | Partial Approval | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2024 | Not Ready for Inspection | BEN MOLSTAD |
| PLUMBING-Rough | 2/9/2024 | Corrections Issued | BEN MOLSTAD |
| Underground Mechanical | 2/9/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2024 | Partial Approval | JAMES CHAVEZ |
| Insulation | 2/12/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| PLUMBING-Rough | 2/12/2024 | Partial Approval | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/13/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Insulation | 2/13/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 2/14/2024 | Partial Approval | JAMES CHAVEZ |
| Insulation | 2/14/2024 | Partial Approval | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/23/2024 | Partial Approval | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/13/2024 | Partial Approval | BEN MOLSTAD |
| PLUMBING-Rough | 4/2/2024 | Approved | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2024 | Partial Approval | JAMES CHAVEZ |
| HVAC-Rough | 4/3/2024 | Approved | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 4/4/2024 | Approved | JAMES CHAVEZ |
| ELECTRICAL-Rough | 4/4/2024 | Approved | JAMES CHAVEZ |
| Green Building Rough | 4/4/2024 | Approved | JAMES CHAVEZ |
| MERV13>=Rough | 4/4/2024 | Approved | JAMES CHAVEZ |
| Verify Sprinkler Sign Off | 4/4/2024 | Approved | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 4/8/2024 | Approved | JAMES CHAVEZ |
| Green Building Rough | 4/8/2024 | Approved | JAMES CHAVEZ |
| Insulation | 4/8/2024 | Approved | JAMES CHAVEZ |
| MERV13>=Rough | 4/8/2024 | Approved | JAMES CHAVEZ |
| Verify Sprinkler Sign Off | 4/8/2024 | Approved | JAMES CHAVEZ |
| Drywall Nailing | 4/25/2024 | Approved | BEN MOLSTAD |
| Interior/Exterior Lathing | 4/25/2024 | Approved | BEN MOLSTAD |
| ELECTRICAL-Final | 6/5/2024 | Partial Approval | BEN MOLSTAD |
| ELECTRICAL-Final | 7/1/2024 | Approved | JAMES CHAVEZ |
| Final | 7/1/2024 | OK to Issue CofO | JAMES CHAVEZ |
| Green Building Final | 7/1/2024 | Approved | JAMES CHAVEZ |
| HVAC-Final | 7/1/2024 | Approved | JAMES CHAVEZ |
| MERV13>=Final | 7/1/2024 | Approved | JAMES CHAVEZ |
| PLUMBING-Final | 7/1/2024 | Approved | JAMES CHAVEZ |
| SGSOV-Seismic Gas S/O Valve | 7/1/2024 | SGSOV Approved | JAMES CHAVEZ |
| Service/Power Release | 7/1/2024 | Approved | JAMES CHAVEZ |
| Smoke Detectors | 7/1/2024 | Approved | JAMES CHAVEZ |
| Service/Power Release | 7/2/2024 | Approved | JAMES CHAVEZ |