3493 S ROSEWOOD AVE 90066

Certificate Information: 3493 S ROSEWOOD AVE 90066

Application / Permit
23010-10000-02274
Plan Check / Job No.
B23LA09999
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePLAN- New construction : 2-STORY Single Family Dwelling with attached 2-car Garage NFPA13D SPRINKLERED THROUGH OUT
Permit Issued
Issued on 3/12/2024
Issuing Office
Current Status
CofO Issued on 11/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/5/2023 APPLICANT
Assigned to Plan Check Engineer 6/22/2023 JAD BASMA
Corrections Issued 6/29/2023 JAD BASMA
Quality Review Completed 7/7/2023 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 12/13/2023 JAD BASMA
Plan Check Approved 3/11/2024 JAD BASMA
Issued 3/12/2024 APPLICANT
CofO in Progress 11/6/2025 WILBER ROSALES
Permit Finaled 11/20/2025 RICHARD STEINBACH
CofO Issued 11/20/2025 RICHARD STEINBACH
Permit Finaled 11/20/2025 RICHARD STEINBACH

Permit Application Clearance Information

Permit Cleared 7/13/2023 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 7/17/2023 DARIN LAM
Sewer availability Cleared 7/17/2023 DARIN LAM
Hydrant and Access approval Cleared 8/11/2023 KURT CORRAL
GPI Written Notices Cleared 8/31/2023 JAD BASMA
Grading Pre-Inspection Cleared 8/31/2023 JAD BASMA
Low Impact Development (LID) Cleared 1/8/2024 PATRICK LOPEZ
Specific Plan Cleared 1/23/2024 JOSHUA JONES
Roof/Waste drainage to street Cleared 1/30/2024 VLADIMIR ARUTYUNYAN
Trees in Parkway Cleared 2/28/2024 ADALBERTO VERA

Contact Information

Contractor Ras-A Build Llc; Lic. No.: 1014457-B       ,

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/12/2024 Corrections Issued STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 7/16/2024 Not Ready for Inspection JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 8/2/2024 Corrections Issued JESUS RODRIGUEZ
Footing/Foundation/Slab 8/2/2024 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Rough 8/2/2024 Partial Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 8/6/2024 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 8/28/2024 Corrections Issued JESUS PINEDA
Sewer 9/12/2024 Approved JESUS PINEDA
Underground Mechanical 9/12/2024 Partial Approval JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 10/25/2024 Approved JESUS PINEDA
PLUMBING-Rough 2/20/2025 Corrections Issued JESUS PINEDA
ELECTRICAL-Rough 3/20/2025 Corrections Issued MICHAEL ALLEN
PLUMBING-Rough 3/20/2025 Approved MICHAEL ALLEN
HVAC-Rough 3/24/2025 Corrections Issued MICHAEL ALLEN
BUILDING-Rough-Frame 4/22/2025 Approved MICHAEL ALLEN
ELECTRICAL-Rough 4/22/2025 Approved MICHAEL ALLEN
Green Building Rough 4/22/2025 Approved MICHAEL ALLEN
HVAC-Rough 4/22/2025 Approved MICHAEL ALLEN
Interior/Exterior Lathing 4/22/2025 Partial Approval MICHAEL ALLEN
Verify Sprinkler Sign Off 4/22/2025 Approved MICHAEL ALLEN
Shower Pan 5/14/2025 Approved JAYLIN GRAVITTE
Insulation 5/28/2025 Approved JAYLIN GRAVITTE
Drywall Nailing 6/24/2025 Approved JAYLIN GRAVITTE
Interior/Exterior Lathing 6/26/2025 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 10/8/2025 Approved EVAN COOPER
Service/Power Release 10/8/2025 Approved EVAN COOPER
HVAC-Final 10/28/2025 Approved WILBER ROSALES
PLUMBING-Final 10/28/2025 Approved WILBER ROSALES
Final 11/3/2025 Corrections Issued WILBER ROSALES
Green Building Final 11/3/2025 Approved WILBER ROSALES
SGSOV-Seismic Gas S/O Valve 11/3/2025 SGSOV Not Required WILBER ROSALES
Smoke Detectors 11/3/2025 Approved WILBER ROSALES
Final 11/5/2025 OK to Issue CofO WILBER ROSALES