7042 N CHIMINEAS AVE 91335

Certificate Information: 7042 N CHIMINEAS AVE 91335

Application / Permit
23010-10000-02218
Plan Check / Job No.
B23LA09800
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE AND ADDITION TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (b)(1).
Permit Issued
Issued on 12/8/2025
Issuing Office
Valley
Current Status
Issued on 12/8/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/25/2023 APPLICANT
Assigned to Plan Check Engineer 6/5/2023 JOSEPH RAFOLS
Corrections Issued 6/8/2023 JOSEPH RAFOLS
Building Plans Picked Up 6/20/2023 APPLICANT
Plan Check Approved 9/25/2025 YAQUB MIRZA
Issued 12/8/2025 APPLICANT

Permit Application Clearance Information

Low Impact Development (LID) Cleared 3/1/2024 MELINEH AGHAKHABIAN
Address approval Cleared 3/19/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 3/19/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 3/19/2024 CARLOS AGUILERA
Sewer availability Cleared 3/19/2024 CARLOS AGUILERA
Construction near power lines Cleared 10/9/2024 RIDWAN HARDY
Construction within easement Cleared 10/9/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

ELECTRICAL-Rough 7/23/2026    Time Frame: 1-3
Floor/Roof Diaphrgm/Shear Wall 7/23/2026    Time Frame: 1-3
PLUMBING-Rough 7/23/2026    Time Frame: 1-3
HVAC-Rough 7/23/2026    Time Frame: 1-3

Inspection Request History

Underground Mechanical 3/25/2026 Approved JEFFREY HARTLINE
Deputy Drilled-In Anchors 3/31/2026 Conditional Approval DAVID SCANTLIN
Footing/Foundation/Slab 4/1/2026 Corrections Issued JACK KARGODORIAN
Footing/Foundation/Slab 4/6/2026 Not Ready for Inspection ARUTYUN MADATYAN
Footing/Foundation/Slab 4/24/2026 Corrections Issued JUAN ALVARADO
Footing/Foundation/Slab 4/28/2026 Approved JUAN ALVARADO
Rough-Elec/Plmb/HVAC 6/23/2026 Corrections Issued JUAN ALVARADO