15118 W NURMI ST 91342
Certificate Information: 15118 W NURMI ST 91342
- Application / Permit
- 23010-10000-02208
- Plan Check / Job No.
- B23LA09770
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- new detached ADU
- Permit Issued
- Issued on 11/21/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/2/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/25/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/8/2023 | ARSALAN SHABESTARI |
| Corrections Issued | 6/14/2023 | ARSALAN SHABESTARI |
| Quality Review Completed | 6/20/2023 | KEN GILL |
| Building Plans Picked Up | 6/21/2023 | APPLICANT |
| Plan Check Approved | 11/13/2024 | ARSALAN SHABESTARI |
| Issued | 11/21/2024 | APPLICANT |
| CofO in Progress | 12/10/2025 | KEVIN BERBERYAN |
| No Progress | 12/16/2025 | RAUL OLAGI |
| CofO in Progress | 12/16/2025 | RAUL OLAGI |
| CofO in Progress | 12/17/2025 | KEVIN BERBERYAN |
| CofO in Progress | 12/24/2025 | KEVIN BERBERYAN |
| Permit Finaled | 1/2/2026 | RUBEN SALAS |
| CofO Issued | 1/2/2026 | RUBEN SALAS |
| Permit Finaled | 1/2/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/10/2023 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/24/2023 | MEGAN GODINEZ |
| Sewer availability | Cleared | 7/25/2023 | MEGAN GODINEZ |
| Miscellaneous | Cleared | 8/2/2023 | KENTON TRINH |
| Miscellaneous | Cleared | 8/2/2023 | KENTON TRINH |
| Low Impact Development (LID) | Cleared | 8/7/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 8/17/2023 | JOHN LIN |
| Grading Pre-Inspection | Cleared | 9/5/2023 | ALEXANDER HELFER |
| Construction near power lines | Cleared | 3/7/2024 | WALTER RAMIREZ |
| Construction within easement | Cleared | 3/7/2024 | WALTER RAMIREZ |
| Hydrant and Access approval | Cleared | 4/12/2024 | KURT CORRAL |
| GPI Written Notices | Cleared | 11/13/2024 | ARSALAN SHABESTARI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/15/2025 | Conditional Approval | KEVIN BERBERYAN |
| Underground Mechanical | 1/15/2025 | Conditional Approval | KEVIN BERBERYAN |
| Excavation/Setback/Form/Re-Bar | 1/21/2025 | Approved | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 1/21/2025 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 3/20/2025 | Partial Approval | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2025 | Partial Approval | KEVIN BERBERYAN |
| Green Building Rough | 3/20/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Sewer | 3/20/2025 | Approved | KEVIN BERBERYAN |
| Verify Sprinkler Sign Off | 3/20/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Wood Frame | 3/20/2025 | Partial Approval | KEVIN BERBERYAN |
| Deputy Wood Construction | 6/3/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 6/10/2025 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Rough | 6/10/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Verify Sprinkler Sign Off | 6/10/2025 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 6/24/2025 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 6/24/2025 | Approved | KEVIN BERBERYAN |
| Green Building Rough | 6/24/2025 | Approved | KEVIN BERBERYAN |
| HVAC-Rough | 6/24/2025 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 6/24/2025 | Approved | KEVIN BERBERYAN |
| PLUMBING-Rough | 6/24/2025 | Approved | KEVIN BERBERYAN |
| Underground Mechanical | 6/24/2025 | Approved | KEVIN BERBERYAN |
| Insulation | 7/17/2025 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 8/5/2025 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 8/19/2025 | Corrections Issued | KEVIN BERBERYAN |
| Shower Pan | 8/19/2025 | Approved | KEVIN BERBERYAN |
| Special/Order Compliance | 8/20/2025 | Corrections Issued | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 8/28/2025 | Approved | MICHAEL CORTEZ |
| Shower Pan | 8/28/2025 | Approved | MICHAEL CORTEZ |
| Final | 11/18/2025 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Final | 11/18/2025 | Approved | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 11/18/2025 | SGSOV Not Required | KEVIN BERBERYAN |
| Service/Power Release | 11/18/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Smoke Detectors | 11/18/2025 | Approved | KEVIN BERBERYAN |
| Final | 12/10/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Service/Power Release | 12/10/2025 | Approved | KEVIN BERBERYAN |
| Special/Order Compliance | 12/17/2025 | Corrections Issued | KEVIN BERBERYAN |
| Final | 12/24/2025 | OK to Issue CofO | KEVIN BERBERYAN |