2836-2836 1/2 N MARSH ST 90039

Certificate Information: 2836-2836 1/2 N MARSH ST 90039

Application / Permit
23010-10000-02198
Plan Check / Job No.
B23LA09024
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
DETACHED 2-STORY, 2-UNIT ADU AT REAR OF LOT.
Permit Issued
Issued on 3/14/2024
Issuing Office
Current Status
CofO Issued on 3/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/18/2023 APPLICANT
Assigned to Plan Check Engineer 5/18/2023 JOE VO
Corrections Issued 5/21/2023 JOE VO
Quality Review Completed 5/31/2023 GARO TELMI
Applicant returned to address corrections 10/17/2023 JOE VO
Applicant returned to address corrections 12/7/2023 JOE VO
Plan Check Approved 1/12/2024 JOE VO
Issued 3/14/2024 APPLICANT
CofO in Progress 3/12/2025 HAMIK HARTOUNIAN
Permit Finaled 3/13/2025 DEROLD HAUFF
CofO Issued 3/13/2025 DEROLD HAUFF
Permit Finaled 3/13/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/25/2023 TREVOR QUAN
Permit Cleared 5/25/2023 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 6/1/2023 TREVOR QUAN
Sewer availability Cleared 6/1/2023 TREVOR QUAN
Trees in Parkway Cleared 6/5/2023 ADALBERTO VERA
ZI Cleared 6/14/2023 JAZMIN ROQUE
Hydrant and Access approval Cleared 8/1/2023 KURT CORRAL
Low Impact Development (LID) Cleared 8/22/2023 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 8/23/2023 ADRIAN SANCHEZ
SB8 RUD Cleared 8/23/2023 BLAKE BOULIGNY
ZI Cleared 8/24/2023 DANIEL CORONADO

Contact Information

Contractor Owner-Builder       ,
Engineer Dweab,, Shadi; Lic. No.: C91184 16760 GREEN TREE BLVD APT #17      VICTORVILLE, CA 92395
Engineer Pinzon,, Eduardo Andres; Lic. No.: C74869 821 W SPRUCE ST      WEST COVINA, CA 91790

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Wood Construction 5/8/2024 No Access for Inspection HAMIK HARTOUNIAN
Underground Mechanical 5/8/2024 Approved HAMIK HARTOUNIAN
Deputy Reinf. Concrete 5/16/2024 Conditional Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 5/16/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 5/20/2024 Approved HAMIK HARTOUNIAN
Deputy Reinf. Concrete 5/24/2024 Conditional Approval FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 5/24/2024 Partial Inspection SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 6/3/2024 Partial Approval THOMAS LOGRASSO
Deputy Wood Construction 6/4/2024 Conditional Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 7/31/2024 Partial Approval HAMIK HARTOUNIAN
Underground Mechanical 8/13/2024 Partial Approval HAMIK HARTOUNIAN
Deputy Wood Construction 8/27/2024 Conditional Approval HAMIK HARTOUNIAN
Green Building Rough 9/11/2024 Approved LUIS CASTRO
HVAC-Rough 9/11/2024 Corrections Issued LUIS CASTRO
MERV13>=Rough 9/11/2024 Approved LUIS CASTRO
PLUMBING-Rough 9/11/2024 Corrections Issued LUIS CASTRO
Verify Sprinkler Sign Off 9/11/2024 Corrections Issued LUIS CASTRO
ELECTRICAL-Rough 9/13/2024 Approved ROY SPAULDING
HVAC-Rough 9/13/2024 Approved ROY SPAULDING
Floor/Roof Diaphrgm/Shear Wall 9/18/2024 Approved HAMIK HARTOUNIAN
Verify Sprinkler Sign Off 9/18/2024 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 10/9/2024 Approved ROY SPAULDING
Interior/Exterior Lathing 10/9/2024 Approved ROY SPAULDING
Insulation 10/15/2024 Approved LUIS CASTRO
Drywall Nailing 10/25/2024 Approved LUIS CASTRO
Shower Pan 10/25/2024 Approved LUIS CASTRO
ELECTRICAL-Final 2/19/2025 Approved WILLIAM SIERRA
Gas Test 2/19/2025 Approved WILLIAM SIERRA
PLUMBING-Final 2/19/2025 Corrections Issued WILLIAM SIERRA
Service/Power Release 2/19/2025 Not Ready for Inspection WILLIAM SIERRA
Final 2/20/2025 Corrections Issued WILLIAM SIERRA
Green Building Final 2/20/2025 Corrections Issued WILLIAM SIERRA
HVAC-Final 2/20/2025 Approved WILLIAM SIERRA
MERV13>=Final 2/20/2025 Corrections Issued WILLIAM SIERRA
SGSOV-Seismic Gas S/O Valve 2/20/2025 SGSOV Not Required WILLIAM SIERRA
Smoke Detectors 2/20/2025 Approved WILLIAM SIERRA
Final 2/24/2025 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 2/24/2025 Corrections Issued HAMIK HARTOUNIAN
MERV13>=Final 2/24/2025 Approved HAMIK HARTOUNIAN
Service/Power Release 2/24/2025 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Final 3/6/2025 Approved WILLIAM SIERRA
Final 3/10/2025 OK to Issue CofO HAMIK HARTOUNIAN
Green Building Final 3/10/2025 Approved HAMIK HARTOUNIAN
Service/Power Release 3/10/2025 Not Required HAMIK HARTOUNIAN
Special/Order Compliance 3/10/2025 Partial Inspection OSVALDO PARAMO