8517-8519 W MELVIL ST 90034

Certificate Information: 8517-8519 W MELVIL ST 90034

Application / Permit
23010-10000-02180
Plan Check / Job No.
B23LA09629
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
ePlan: (N) 2-STORY DUPLEX WITH ATTACEHD GARAGE
Permit Issued
Issued on 6/4/2024
Issuing Office
Current Status
CofO Issued on 7/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/23/2023 APPLICANT
Assigned to Plan Check Engineer 5/25/2023 DANIEL YIP
Corrections Issued 5/27/2023 DANIEL YIP
Quality Review Completed 5/31/2023 GARO TELMI
Applicant returned to address corrections 7/17/2023 DANIEL YIP
Applicant returned to address corrections 7/28/2023 DANIEL YIP
Applicant returned to address corrections 8/15/2023 DANIEL YIP
Applicant returned to address corrections 8/25/2023 DANIEL YIP
Plan Check Approved 6/4/2024 DANIEL YIP
Issued 6/4/2024 APPLICANT
CofO in Progress 7/22/2025 EVAN COOPER
Permit Finaled 7/29/2025 RICHARD STEINBACH
CofO Issued 7/29/2025 RICHARD STEINBACH
Permit Finaled 7/29/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 7/18/2023 JOSEPH RHYU
Eng Process Fee Ord 176,300 Cleared 7/18/2023 JOSEPH RHYU
Permit Cleared 7/18/2023 JOSEPH RHYU
Sewer availability Cleared 7/18/2023 JOSEPH RHYU
Hydrant and Access approval Cleared 8/4/2023 GILBERT URREA
SB8 RUD Cleared 10/5/2023 ALYSSA FLORES
Frnt yard landscape/Water mgmt Cleared 11/28/2023 FIPE LEILUA
Trees in Parkway Cleared 1/18/2024 ADALBERTO VERA
Low Impact Development (LID) Cleared 3/25/2024 TOMMY YIN
Roof/Waste drainage to street Cleared 3/27/2024 JUSTIN BICOL
Construction near power lines Cleared 6/1/2024 RIDWAN HARDY

Contact Information

Contractor H T A Construction & Development; Lic. No.: 1044038-B       ,
Contractor Hta Construction & Development; Lic. No.: 1044038-B       ,
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/19/2024 Partial Approval MEL KHACHATOURIAN
Excavation/Setback/Form/Re-Bar 7/22/2024 No Access for Inspection MEL KHACHATOURIAN
Underground Mechanical 7/22/2024 No Access for Inspection MEL KHACHATOURIAN
Excavation/Setback/Form/Re-Bar 7/25/2024 No Access for Inspection MEL KHACHATOURIAN
Excavation/Setback/Form/Re-Bar 7/26/2024 Corrections Issued MEL KHACHATOURIAN
Excavation/Setback/Form/Re-Bar 7/30/2024 Conditional Approval MEL KHACHATOURIAN
Footing/Foundation/Slab 7/30/2024 Conditional Approval MEL KHACHATOURIAN
Footing/Foundation/Slab 8/1/2024 Approved MEL KHACHATOURIAN
Deputy Wood Construction 8/15/2024 No Access for Inspection MEL KHACHATOURIAN
Drywall Nailing 8/19/2024 Partial Approval KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 8/19/2024 Partial Approval KIRK SANDERS
Green Building Rough 8/19/2024 Not Ready for Inspection KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 8/28/2024 No Access for Inspection MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 8/30/2024 No Access for Inspection MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 9/10/2024 Corrections Issued ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 9/13/2024 Not Ready for Inspection ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 9/17/2024 Conditional Approval ARAM AVEDISIAN
Deputy Wood Construction 9/19/2024 Conditional Approval ARAM AVEDISIAN
Drywall Nailing 9/23/2024 Partial Approval STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 9/23/2024 Corrections Issued STEPHANIE SWANSON
Green Building Rough 9/23/2024 Not Ready for Inspection STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 9/24/2024 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 10/29/2024 Partial Approval MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 11/4/2024 Not Ready for Inspection MEL KHACHATOURIAN
ELECTRICAL-Rough 11/8/2024 Not Ready for Inspection MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 11/8/2024 Approved MEL KHACHATOURIAN
HVAC-Rough 11/8/2024 Not Ready for Inspection MEL KHACHATOURIAN
PLUMBING-Rough 11/8/2024 Not Ready for Inspection MEL KHACHATOURIAN
BUILDING-Rough-Frame 11/12/2024 Not Ready for Inspection MEL KHACHATOURIAN
ELECTRICAL-Rough 11/12/2024 Not Ready for Inspection MEL KHACHATOURIAN
Green Building Rough 11/12/2024 Not Ready for Inspection MEL KHACHATOURIAN
HVAC-Rough 11/12/2024 Corrections Issued MEL KHACHATOURIAN
PLUMBING-Rough 11/12/2024 Not Ready for Inspection MEL KHACHATOURIAN
Verify Sprinkler Sign Off 11/12/2024 Not Ready for Inspection MEL KHACHATOURIAN
BUILDING-Rough-Frame 11/15/2024 No Access for Inspection MEL KHACHATOURIAN
ELECTRICAL-Rough 11/15/2024 No Access for Inspection MEL KHACHATOURIAN
Green Building Rough 11/15/2024 No Access for Inspection MEL KHACHATOURIAN
HVAC-Rough 11/15/2024 No Access for Inspection MEL KHACHATOURIAN
PLUMBING-Rough 11/15/2024 No Access for Inspection MEL KHACHATOURIAN
Verify Sprinkler Sign Off 11/15/2024 No Access for Inspection MEL KHACHATOURIAN
ELECTRICAL-Rough 11/18/2024 Not Ready for Inspection MEL KHACHATOURIAN
HVAC-Rough 11/18/2024 Not Ready for Inspection MEL KHACHATOURIAN
PLUMBING-Rough 11/18/2024 Not Ready for Inspection MEL KHACHATOURIAN
Wood Frame 11/18/2024 Not Ready for Inspection MEL KHACHATOURIAN
BUILDING-Rough-Frame 11/19/2024 Not Ready for Inspection ASHLEY THOMPSON
ELECTRICAL-Rough 11/19/2024 Corrections Issued ASHLEY THOMPSON
Green Building Rough 11/19/2024 Not Ready for Inspection ASHLEY THOMPSON
HVAC-Rough 11/19/2024 Corrections Issued ASHLEY THOMPSON
Interior/Exterior Lathing 11/19/2024 Not Ready for Inspection ASHLEY THOMPSON
PLUMBING-Rough 11/19/2024 Corrections Issued ASHLEY THOMPSON
Verify Sprinkler Sign Off 11/19/2024 Not Ready for Inspection ASHLEY THOMPSON
Wood Frame 11/19/2024 Not Ready for Inspection ASHLEY THOMPSON
ELECTRICAL-Rough 11/20/2024 No Access for Inspection MEL KHACHATOURIAN
HVAC-Rough 11/20/2024 No Access for Inspection MEL KHACHATOURIAN
Interior/Exterior Lathing 11/20/2024 No Access for Inspection MEL KHACHATOURIAN
PLUMBING-Rough 11/20/2024 No Access for Inspection MEL KHACHATOURIAN
Wood Frame 11/20/2024 No Access for Inspection MEL KHACHATOURIAN
BUILDING-Rough-Frame 11/25/2024 Partial Approval MEL KHACHATOURIAN
ELECTRICAL-Rough 11/25/2024 Approved MEL KHACHATOURIAN
Green Building Rough 11/25/2024 Approved MEL KHACHATOURIAN
HVAC-Rough 11/25/2024 Approved MEL KHACHATOURIAN
Interior/Exterior Lathing 11/25/2024 Partial Approval MEL KHACHATOURIAN
PLUMBING-Rough 11/25/2024 Approved MEL KHACHATOURIAN
Verify Sprinkler Sign Off 11/25/2024 Approved MEL KHACHATOURIAN
Insulation 12/2/2024 No Access for Inspection MEL KHACHATOURIAN
Insulation 12/4/2024 Approved MEL KHACHATOURIAN
BUILDING-Rough-Frame 12/12/2024 Approved BOBBY KEY
Drywall Nailing 12/12/2024 Approved BOBBY KEY
Special/Order Compliance 12/12/2024 Partial Inspection JAYLIN GRAVITTE
Interior/Exterior Lathing 12/16/2024 No Access for Inspection ARAM AVEDISIAN
Interior/Exterior Lathing 1/13/2025 Approved MEL KHACHATOURIAN
Shower Pan 1/13/2025 Approved MEL KHACHATOURIAN
Sewer 3/10/2025 Approved KIRK SANDERS
ELECTRICAL-Final 4/25/2025 Corrections Issued EVAN COOPER
Service/Power Release 4/25/2025 Not Ready for Inspection EVAN COOPER
ELECTRICAL-Final 5/22/2025 Approved EVAN COOPER
HVAC-Final 5/22/2025 Corrections Issued EVAN COOPER
Service/Power Release 5/22/2025 Approved EVAN COOPER
HVAC-Final 6/18/2025 Approved BOBBY KEY
PLUMBING-Final 6/18/2025 Corrections Issued BOBBY KEY
Final 7/22/2025 OK to Issue CofO EVAN COOPER
Green Building Final 7/22/2025 Approved EVAN COOPER
HVAC-Final 7/22/2025 Approved EVAN COOPER
PLUMBING-Final 7/22/2025 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 7/22/2025 SGSOV Approved EVAN COOPER
Smoke Detectors 7/22/2025 Approved EVAN COOPER