7705 N BAIRD AVE 91335
Certificate Information: 7705 N BAIRD AVE 91335
- Application / Permit
- 23010-10000-02176
- Plan Check / Job No.
- B23LA09616
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: (N) 20'-10" X 41'-4" DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c), (d), and (g)
- Permit Issued
- Issued on 9/21/2023
- Issuing Office
- Current Status
- CofO Issued on 3/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/23/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/30/2023 | ALEC MOUSAKHANIAN |
| Corrections Issued | 5/31/2023 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 9/19/2023 | OMAR GARNICA |
| Issued | 9/21/2023 | APPLICANT |
| CofO in Progress | 2/7/2025 | ARUTYUN MADATYAN |
| Permit Finaled | 3/10/2025 | JOHN JANSON |
| CofO Issued | 3/10/2025 | JOHN JANSON |
| Permit Finaled | 3/10/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 6/22/2023 | TAL SHEMEN |
| Eng Process Fee Ord 176,300 | Cleared | 6/28/2023 | TAL SHEMEN |
| Sewer availability | Cleared | 7/5/2023 | TAL SHEMEN |
| Low Impact Development (LID) | Cleared | 9/14/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 9/14/2023 | TAL SHEMEN |
Contact Information
| Architect | Hanna,, Remon; Lic. No.: NA36271 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/21/2023 | Partial Approval | ALEXANDER HANDY |
| Sewer | 11/21/2023 | Approved | ALEXANDER HANDY |
| Footing/Foundation/Slab | 11/28/2023 | Approved | JEFFREY BULL |
| Special/Order Compliance | 11/28/2023 | Corrections Issued | JEFFREY BULL |
| BUILDING-Rough-Frame | 2/20/2024 | Approved | HENRY KIM |
| Drywall Nailing | 2/20/2024 | Approved | HENRY KIM |
| Green Building Rough | 2/20/2024 | Approved | HENRY KIM |
| Rough-Elec/Plmb/HVAC | 2/20/2024 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 2/23/2024 | Approved | HENRY KIM |
| Shower Pan | 2/23/2024 | Corrections Issued | HENRY KIM |
| BUILDING-Rough-Frame | 2/27/2024 | Not Ready for Inspection | HENRY KIM |
| Green Building Rough | 2/27/2024 | Not Ready for Inspection | HENRY KIM |
| Shower Pan | 2/27/2024 | Corrections Issued | HENRY KIM |
| Shower Pan | 3/5/2024 | Approved | HENRY KIM |
| BUILDING-Rough-Frame | 12/2/2024 | Approved | ARUTYUN MADATYAN |
| Final | 12/2/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 12/2/2024 | SGSOV Not Ready | ARUTYUN MADATYAN |
| Service/Power Release | 12/2/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Smoke Detectors | 12/2/2024 | Approved | ARUTYUN MADATYAN |
| Final | 12/12/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Sewer | 12/12/2024 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 2/6/2025 | Approved | ARUTYUN MADATYAN |
| Final | 2/6/2025 | OK to Issue CofO | ARUTYUN MADATYAN |
| HVAC-Final | 2/6/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Final | 2/6/2025 | Approved | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 2/6/2025 | SGSOV Approved | ARUTYUN MADATYAN |
| Service/Power Release | 2/6/2025 | Approved | ARUTYUN MADATYAN |