7922 N AMESTOY AVE 91406
Certificate Information: 7922 N AMESTOY AVE 91406
- Application / Permit
- 23010-10000-02164
- Plan Check / Job No.
- B23LA09569
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ONE-STORY SINGLE FAMILY DWELLING PER SB9, SECTION.65852.21.
- Permit Issued
- Issued on 10/17/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/23/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/25/2023 | TSE MING HUANG |
| Corrections Issued | 6/2/2023 | TSE MING HUANG |
| Quality Review Completed | 6/2/2023 | KEN GILL |
| Building Plans Picked Up | 6/6/2023 | APPLICANT |
| Applicant returned to address corrections | 6/28/2023 | TSE MING HUANG |
| Plan Check Approved | 9/21/2023 | TSE MING HUANG |
| Issued | 10/17/2023 | APPLICANT |
| CofO in Progress | 11/25/2024 | SALVADOR MARTINEZ |
| CofO in Progress | 12/3/2024 | RAUL OLAGI |
| CofO in Progress | 2/18/2025 | RAUL OLAGI |
| CofO Issued | 2/19/2025 | RUBEN SALAS |
| Permit Finaled | 2/19/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 6/14/2023 | RICARDO BOHORQUEZ |
| Senate Bill 9 | Cleared | 8/20/2023 | RYAN LY |
| Address approval | Cleared | 8/25/2023 | NIKKI ZULUETA |
| Eng Process Fee Ord 176,300 | Cleared | 8/28/2023 | NIKKI ZULUETA |
| Sewer availability | Cleared | 8/29/2023 | NIKKI ZULUETA |
| Low Impact Development (LID) | Cleared | 9/14/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 9/15/2023 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 9/18/2023 | LAVEON RIDER |
Contact Information
| Contractor | Express Construction Group Inc; Lic. No.: 625249-B | 537 HAMPTON RD BURBANK, CA 91504 |
| Engineer | Karapetian,, Arbi; Lic. No.: C79953 | 6854 FOOTHILL BLVD TUJUNGA, CA 91042 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/9/2023 | Conditional Approval | RAUL OLAGI |
| Special/Order Compliance | 11/9/2023 | Corrections Issued | RAUL OLAGI |
| Footing/Foundation/Slab | 11/28/2023 | Approved | RAUL OLAGI |
| Underground Mechanical | 12/19/2023 | Not Ready for Inspection | RAUL OLAGI |
| BUILDING-Rough-Frame | 12/29/2023 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 12/29/2023 | Corrections Issued | RAUL OLAGI |
| HVAC-Rough | 12/29/2023 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 12/29/2023 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 3/6/2024 | Not Ready for Inspection | RAUL OLAGI |
| ELECTRICAL-Rough | 3/6/2024 | Approved | RAUL OLAGI |
| Green Building Rough | 3/6/2024 | Not Ready for Inspection | RAUL OLAGI |
| Verify Sprinkler Sign Off | 3/6/2024 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 3/8/2024 | Approved | RAUL OLAGI |
| Green Building Rough | 3/8/2024 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 3/8/2024 | Partial Approval | RAUL OLAGI |
| Sewer | 3/8/2024 | Not Ready for Inspection | RAUL OLAGI |
| Insulation | 3/19/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Shower Pan | 3/19/2024 | Approved | SALVADOR MARTINEZ |
| Drywall Nailing | 3/27/2024 | Approved | SALVADOR MARTINEZ |
| Service/Power Release | 9/27/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 10/30/2024 | Corrections Issued | SALVADOR MARTINEZ |
| HVAC-Final | 10/30/2024 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Final | 10/30/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Smoke Detectors | 10/30/2024 | Approved | SALVADOR MARTINEZ |
| Final | 11/4/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Final | 11/4/2024 | Corrections Issued | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 11/4/2024 | SGSOV No Gas | SALVADOR MARTINEZ |
| Service/Power Release | 11/4/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Final | 11/22/2024 | OK to Issue CofO | SALVADOR MARTINEZ |
| Green Building Final | 11/22/2024 | Approved | SALVADOR MARTINEZ |
| Service/Power Release | 11/22/2024 | Approved | SALVADOR MARTINEZ |
| Special/Order Compliance | 12/3/2024 | Corrections Issued | SALVADOR MARTINEZ |