1596-1598 W 36TH ST 90018

Certificate Information: 1596-1598 W 36TH ST 90018

Application / Permit
23010-10000-02159
Plan Check / Job No.
B23LA09528
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
ePLAN. NEW 4-STORY DUPLEX WITH ATTACHED GARAGE.
Permit Issued
Issued on 8/31/2023
Issuing Office
Current Status
CofO Issued on 5/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/23/2023 APPLICANT
Assigned to Plan Check Engineer 5/25/2023 KEVIN MORALES
Corrections Issued 5/31/2023 KEVIN MORALES
Quality Review Completed 6/5/2023 EUGENE BARBEAU
Plan Check Approved 8/22/2023 KEVIN MORALES
Issued 8/31/2023 APPLICANT
CofO in Progress 5/5/2025 SABAS ALONSO
Permit Finaled 5/6/2025 DEROLD HAUFF
CofO Issued 5/6/2025 DEROLD HAUFF
Permit Finaled 5/6/2025 DEROLD HAUFF

Permit Application Clearance Information

SB8 RUD Cleared 6/8/2023 NICHOLAS KAWAZOE
Address approval Cleared 6/22/2023 ADRIAN SANCHEZ
Highway dedication Cleared 6/22/2023 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 6/28/2023 ADRIAN SANCHEZ
Sewer availability Cleared 6/28/2023 ADRIAN SANCHEZ
Frnt yard landscape/Water mgmt Cleared 7/12/2023 JAZMIN ROQUE
Low Impact Development (LID) Cleared 7/18/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 7/19/2023 ADRIAN SANCHEZ
Hydrant and Access approval Cleared 8/7/2023 KURT CORRAL

Contact Information

Contractor Emerald Builders And Developers; Lic. No.: 1068007-B 1412 W 22ND STREET      LOS ANGELES, CA 90007

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 1/17/2024 Approved SABAS ALONSO
Underground Mechanical 1/17/2024 Partial Approval SABAS ALONSO
Excavation/Setback/Form/Re-Bar 1/30/2024 Approved SABAS ALONSO
Footing/Foundation/Slab 1/30/2024 Approved SABAS ALONSO
METHANE-Barrier 1/30/2024 Approved SABAS ALONSO
METHANE-Final 1/30/2024 Approved SABAS ALONSO
METHANE-Rough 1/30/2024 Approved SABAS ALONSO
METHANE-Subgrade 1/30/2024 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 3/27/2024 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 4/16/2024 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 5/2/2024 Partial Approval SABAS ALONSO
Deputy Wood Construction 7/3/2024 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 7/3/2024 Partial Approval SABAS ALONSO
Shower Pan 7/3/2024 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 7/8/2024 Approved SABAS ALONSO
PLUMBING-Rough 7/8/2024 Conditional Approval SABAS ALONSO
BUILDING-Rough-Frame 8/19/2024 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 8/19/2024 Approved SABAS ALONSO
Green Building Rough 8/19/2024 Approved SABAS ALONSO
HVAC-Rough 8/19/2024 Approved SABAS ALONSO
Verify Sprinkler Sign Off 8/19/2024 Approved SABAS ALONSO
PLUMBING-Rough 8/20/2024 Corrections Issued CRAIG DAVIS
BUILDING-Rough-Frame 8/28/2024 Approved SABAS ALONSO
Insulation 9/5/2024 Approved SABAS ALONSO
Drywall Nailing 9/16/2024 Approved SABAS ALONSO
Interior/Exterior Lathing 9/16/2024 Partial Approval SABAS ALONSO
Interior/Exterior Lathing 10/15/2024 Approved SABAS ALONSO
Final 4/16/2025 Corrections Issued SABAS ALONSO
Green Building Final 4/16/2025 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 4/16/2025 SGSOV Approved SABAS ALONSO
Service/Power Release 4/16/2025 Approved SABAS ALONSO
Smoke Detectors 4/16/2025 Approved SABAS ALONSO
Final 4/24/2025 Corrections Issued SABAS ALONSO
Final 4/30/2025 Not Ready for Inspection SABAS ALONSO
Final 5/2/2025 OK to Issue CofO SABAS ALONSO