1431 W 58TH ST 90062
Certificate Information: 1431 W 58TH ST 90062
- Application / Permit
- 23010-10000-02133
- Plan Check / Job No.
- B23LA09428
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN NEW DETACHED ADU APPROX. 625 S.F. PER STATE LAW
- Permit Issued
- Issued on 3/22/2024
- Issuing Office
- Current Status
- CofO Issued on 8/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/24/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/1/2023 | WEIJIAN HUANG |
| Corrections Issued | 6/2/2023 | WEIJIAN HUANG |
| Applicant returned to address corrections | 3/15/2024 | KHUONG TRUONG |
| Plan Check Approved | 3/19/2024 | KHUONG TRUONG |
| Issued | 3/22/2024 | APPLICANT |
| CofO in Progress | 8/13/2025 | SABAS ALONSO |
| Permit Finaled | 8/16/2025 | DEROLD HAUFF |
| CofO Issued | 8/16/2025 | DEROLD HAUFF |
| Permit Finaled | 8/16/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 8/17/2023 | SHAHIN KHAZEY |
| Address approval | Cleared | 8/22/2023 | JOSEPH RHYU |
| Eng Process Fee Ord 176,300 | Cleared | 8/22/2023 | JOSEPH RHYU |
| Roof/Waste drainage to street | Cleared | 8/22/2023 | JOSEPH RHYU |
| Sewer availability | Cleared | 8/22/2023 | JOSEPH RHYU |
| Construction near power lines | Cleared | 9/12/2023 | RIDWAN HARDY |
| Community Plan Implem. Overlay | Cleared | 2/6/2024 | MANERI ROMAN |
| Community Plan Implem. Overlay | Cleared | 2/27/2024 | DYNL MIRANDA |
| Community Plan Implem. Overlay | Cleared | 2/27/2024 | RIDWAN HARDY |
| Community Plan Implem. Overlay | Cleared | 2/28/2024 | JESSICA OPINION |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Acciani,, Mark; Lic. No.: C83929 | PO BOX 1390 RUNNING SPRINGS, CA 92382 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/9/2024 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 7/9/2024 | Partial Approval | SABAS ALONSO |
| Sewer | 7/9/2024 | Not Ready for Inspection | SABAS ALONSO |
| Footing/Foundation/Slab | 7/22/2024 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2024 | Not Ready for Inspection | SABAS ALONSO |
| Insulation | 8/1/2024 | Partial Approval | SABAS ALONSO |
| Sewer | 8/1/2024 | Not Ready for Inspection | SABAS ALONSO |
| Underground Mechanical | 8/1/2024 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 8/27/2024 | Corrections Issued | SABAS ALONSO |
| Sewer | 8/27/2024 | Approved | SABAS ALONSO |
| Underground Mechanical | 8/27/2024 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 9/5/2024 | Partial Approval | MICHAEL LEWIS |
| HVAC-Rough | 9/5/2024 | Partial Approval | MICHAEL LEWIS |
| PLUMBING-Rough | 9/5/2024 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 9/9/2024 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 9/9/2024 | Corrections Issued | SABAS ALONSO |
| Underground Mechanical | 9/9/2024 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 9/11/2024 | Approved | SABAS ALONSO |
| Green Building Rough | 9/19/2024 | Approved | SABAS ALONSO |
| HVAC-Rough | 9/19/2024 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 9/19/2024 | Partial Approval | SABAS ALONSO |
| BUILDING-Rough-Frame | 9/23/2024 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 9/30/2024 | Approved | SABAS ALONSO |
| Insulation | 10/7/2024 | Approved | ALEX COLIN |
| Drywall Nailing | 10/15/2024 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 10/15/2024 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 12/9/2024 | Corrections Issued | SABAS ALONSO |
| Final | 12/9/2024 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 12/9/2024 | Approved | SABAS ALONSO |
| HVAC-Final | 12/9/2024 | Approved | SABAS ALONSO |
| PLUMBING-Final | 12/9/2024 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 12/9/2024 | SGSOV Approved | SABAS ALONSO |
| Smoke Detectors | 12/9/2024 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 12/17/2024 | Not Ready for Inspection | SABAS ALONSO |
| Final | 12/17/2024 | Not Ready for Inspection | SABAS ALONSO |
| Service/Power Release | 12/17/2024 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Final | 12/19/2024 | Approved | SABAS ALONSO |
| Service/Power Release | 4/9/2025 | Not Ready for Inspection | SABAS ALONSO |
| Final | 5/12/2025 | Not Ready for Inspection | SABAS ALONSO |
| Service/Power Release | 5/12/2025 | Not Ready for Inspection | SABAS ALONSO |
| Final | 6/2/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| Service/Power Release | 6/2/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| Service/Power Release | 7/7/2025 | Corrections Issued | LUIS CASTRO |
| Final | 8/11/2025 | OK to Issue CofO | SABAS ALONSO |
| Service/Power Release | 8/11/2025 | Approved | SABAS ALONSO |