1431 W 58TH ST 90062

Certificate Information: 1431 W 58TH ST 90062

Application / Permit
23010-10000-02133
Plan Check / Job No.
B23LA09428
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN NEW DETACHED ADU APPROX. 625 S.F. PER STATE LAW
Permit Issued
Issued on 3/22/2024
Issuing Office
Current Status
CofO Issued on 8/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/24/2023 APPLICANT
Assigned to Plan Check Engineer 6/1/2023 WEIJIAN HUANG
Corrections Issued 6/2/2023 WEIJIAN HUANG
Applicant returned to address corrections 3/15/2024 KHUONG TRUONG
Plan Check Approved 3/19/2024 KHUONG TRUONG
Issued 3/22/2024 APPLICANT
CofO in Progress 8/13/2025 SABAS ALONSO
Permit Finaled 8/16/2025 DEROLD HAUFF
CofO Issued 8/16/2025 DEROLD HAUFF
Permit Finaled 8/16/2025 DEROLD HAUFF

Permit Application Clearance Information

Low Impact Development (LID) Cleared 8/17/2023 SHAHIN KHAZEY
Address approval Cleared 8/22/2023 JOSEPH RHYU
Eng Process Fee Ord 176,300 Cleared 8/22/2023 JOSEPH RHYU
Roof/Waste drainage to street Cleared 8/22/2023 JOSEPH RHYU
Sewer availability Cleared 8/22/2023 JOSEPH RHYU
Construction near power lines Cleared 9/12/2023 RIDWAN HARDY
Community Plan Implem. Overlay Cleared 2/6/2024 MANERI ROMAN
Community Plan Implem. Overlay Cleared 2/27/2024 DYNL MIRANDA
Community Plan Implem. Overlay Cleared 2/27/2024 RIDWAN HARDY
Community Plan Implem. Overlay Cleared 2/28/2024 JESSICA OPINION

Contact Information

Contractor Owner-Builder       ,
Engineer Acciani,, Mark; Lic. No.: C83929 PO BOX 1390      RUNNING SPRINGS, CA 92382

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/9/2024 Partial Approval SABAS ALONSO
Footing/Foundation/Slab 7/9/2024 Partial Approval SABAS ALONSO
Sewer 7/9/2024 Not Ready for Inspection SABAS ALONSO
Footing/Foundation/Slab 7/22/2024 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 8/1/2024 Not Ready for Inspection SABAS ALONSO
Insulation 8/1/2024 Partial Approval SABAS ALONSO
Sewer 8/1/2024 Not Ready for Inspection SABAS ALONSO
Underground Mechanical 8/1/2024 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 8/27/2024 Corrections Issued SABAS ALONSO
Sewer 8/27/2024 Approved SABAS ALONSO
Underground Mechanical 8/27/2024 Approved SABAS ALONSO
ELECTRICAL-Rough 9/5/2024 Partial Approval MICHAEL LEWIS
HVAC-Rough 9/5/2024 Partial Approval MICHAEL LEWIS
PLUMBING-Rough 9/5/2024 Approved MICHAEL LEWIS
ELECTRICAL-Rough 9/9/2024 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 9/9/2024 Corrections Issued SABAS ALONSO
Underground Mechanical 9/9/2024 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 9/11/2024 Approved SABAS ALONSO
Green Building Rough 9/19/2024 Approved SABAS ALONSO
HVAC-Rough 9/19/2024 Approved SABAS ALONSO
Interior/Exterior Lathing 9/19/2024 Partial Approval SABAS ALONSO
BUILDING-Rough-Frame 9/23/2024 Approved SABAS ALONSO
Interior/Exterior Lathing 9/30/2024 Approved SABAS ALONSO
Insulation 10/7/2024 Approved ALEX COLIN
Drywall Nailing 10/15/2024 Approved SABAS ALONSO
Interior/Exterior Lathing 10/15/2024 Approved SABAS ALONSO
ELECTRICAL-Final 12/9/2024 Corrections Issued SABAS ALONSO
Final 12/9/2024 Corrections Issued SABAS ALONSO
Green Building Final 12/9/2024 Approved SABAS ALONSO
HVAC-Final 12/9/2024 Approved SABAS ALONSO
PLUMBING-Final 12/9/2024 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 12/9/2024 SGSOV Approved SABAS ALONSO
Smoke Detectors 12/9/2024 Approved SABAS ALONSO
ELECTRICAL-Final 12/17/2024 Not Ready for Inspection SABAS ALONSO
Final 12/17/2024 Not Ready for Inspection SABAS ALONSO
Service/Power Release 12/17/2024 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Final 12/19/2024 Approved SABAS ALONSO
Service/Power Release 4/9/2025 Not Ready for Inspection SABAS ALONSO
Final 5/12/2025 Not Ready for Inspection SABAS ALONSO
Service/Power Release 5/12/2025 Not Ready for Inspection SABAS ALONSO
Final 6/2/2025 Not Ready for Inspection DAVID WILLIAMS
Service/Power Release 6/2/2025 Not Ready for Inspection DAVID WILLIAMS
Service/Power Release 7/7/2025 Corrections Issued LUIS CASTRO
Final 8/11/2025 OK to Issue CofO SABAS ALONSO
Service/Power Release 8/11/2025 Approved SABAS ALONSO