1019 W 77TH ST 90044
Certificate Information: 1019 W 77TH ST 90044
- Application / Permit
- 23010-10000-02117
- Plan Check / Job No.
- B23LA09365
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (d). WORK PER ENGINEER.
- Permit Issued
- Issued on 8/30/2023
- Issuing Office
- Current Status
- CofO Issued on 2/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/25/2023 | ROSENDO MEDINA |
| Corrections Issued | 5/25/2023 | ROSENDO MEDINA |
| Plan Check Approved | 8/2/2023 | PINANK PATEL |
| Issued | 8/30/2023 | APPLICANT |
| CofO in Progress | 2/1/2024 | MICHAEL LEWIS |
| Permit Finaled | 2/7/2024 | DEROLD HAUFF |
| CofO Issued | 2/7/2024 | DEROLD HAUFF |
| Permit Finaled | 2/7/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/14/2023 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/23/2023 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 6/23/2023 | ADRIAN SANCHEZ |
| Low Impact Development (LID) | Cleared | 7/26/2023 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 7/26/2023 | ADRIAN SANCHEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
| Engineer | Sivushenka,, Mikita; Lic. No.: NA87698 | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/2/2023 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 10/2/2023 | Corrections Issued | MICHAEL LEWIS |
| Underground Mechanical | 10/2/2023 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 10/5/2023 | Approved | MICHAEL LEWIS |
| Deputy Wood Construction | 10/25/2023 | Partial Approval | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/25/2023 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 11/6/2023 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 11/6/2023 | Partial Inspection | MICHAEL LEWIS |
| HVAC-Rough | 11/6/2023 | Corrections Issued | MICHAEL LEWIS |
| Interior/Exterior Lathing | 11/6/2023 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 11/6/2023 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 11/8/2023 | Approved | MICHAEL LEWIS |
| Green Building Rough | 11/8/2023 | Approved | MICHAEL LEWIS |
| Verify Sprinkler Sign Off | 11/8/2023 | Approved | MICHAEL LEWIS |
| Insulation | 11/14/2023 | Approved | MICHAEL LEWIS |
| Sewer | 11/14/2023 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 11/14/2023 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 11/27/2023 | Not Ready for Inspection | RONNIE MINDANAO |
| Interior/Exterior Lathing | 11/27/2023 | Not Ready for Inspection | RONNIE MINDANAO |
| Shower Pan | 11/27/2023 | Not Ready for Inspection | RONNIE MINDANAO |
| Drywall Nailing | 11/28/2023 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 11/28/2023 | Approved | MICHAEL LEWIS |
| Shower Pan | 11/28/2023 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 12/11/2023 | Approved | MICHAEL LEWIS |
| Final | 1/5/2024 | Corrections Issued | MICHAEL LEWIS |
| Green Building Final | 1/5/2024 | Corrections Issued | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 1/5/2024 | SGSOV Approved | MICHAEL LEWIS |
| Service/Power Release | 1/5/2024 | Corrections Issued | MICHAEL LEWIS |
| Smoke Detectors | 1/5/2024 | Corrections Issued | MICHAEL LEWIS |
| Final | 1/16/2024 | Corrections Issued | MICHAEL LEWIS |
| Green Building Final | 1/16/2024 | Approved | MICHAEL LEWIS |
| Service/Power Release | 1/16/2024 | Approved | MICHAEL LEWIS |
| Smoke Detectors | 1/16/2024 | Approved | MICHAEL LEWIS |
| Final | 1/31/2024 | OK to Issue CofO | MICHAEL LEWIS |
| Service/Power Release | 2/1/2024 | Approved | MICHAEL LEWIS |