1019 W 77TH ST 90044

Certificate Information: 1019 W 77TH ST 90044

Application / Permit
23010-10000-02117
Plan Check / Job No.
B23LA09365
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (d). WORK PER ENGINEER.
Permit Issued
Issued on 8/30/2023
Issuing Office
Current Status
CofO Issued on 2/7/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/22/2023 APPLICANT
Assigned to Plan Check Engineer 5/25/2023 ROSENDO MEDINA
Corrections Issued 5/25/2023 ROSENDO MEDINA
Plan Check Approved 8/2/2023 PINANK PATEL
Issued 8/30/2023 APPLICANT
CofO in Progress 2/1/2024 MICHAEL LEWIS
Permit Finaled 2/7/2024 DEROLD HAUFF
CofO Issued 2/7/2024 DEROLD HAUFF
Permit Finaled 2/7/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/14/2023 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 6/23/2023 ADRIAN SANCHEZ
Sewer availability Cleared 6/23/2023 ADRIAN SANCHEZ
Low Impact Development (LID) Cleared 7/26/2023 LUIS LUVANO
Roof/Waste drainage to street Cleared 7/26/2023 ADRIAN SANCHEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22814 DOLOROSA ST      WOODLAND HILLS, CA 91367
Engineer Sivushenka,, Mikita; Lic. No.: NA87698       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/2/2023 Approved MICHAEL LEWIS
Footing/Foundation/Slab 10/2/2023 Corrections Issued MICHAEL LEWIS
Underground Mechanical 10/2/2023 Approved MICHAEL LEWIS
Footing/Foundation/Slab 10/5/2023 Approved MICHAEL LEWIS
Deputy Wood Construction 10/25/2023 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 10/25/2023 Approved MICHAEL LEWIS
ELECTRICAL-Rough 11/6/2023 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 11/6/2023 Partial Inspection MICHAEL LEWIS
HVAC-Rough 11/6/2023 Corrections Issued MICHAEL LEWIS
Interior/Exterior Lathing 11/6/2023 Approved MICHAEL LEWIS
PLUMBING-Rough 11/6/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 11/8/2023 Approved MICHAEL LEWIS
Green Building Rough 11/8/2023 Approved MICHAEL LEWIS
Verify Sprinkler Sign Off 11/8/2023 Approved MICHAEL LEWIS
Insulation 11/14/2023 Approved MICHAEL LEWIS
Sewer 11/14/2023 Approved MICHAEL LEWIS
Underground Mechanical 11/14/2023 Approved MICHAEL LEWIS
Drywall Nailing 11/27/2023 Not Ready for Inspection RONNIE MINDANAO
Interior/Exterior Lathing 11/27/2023 Not Ready for Inspection RONNIE MINDANAO
Shower Pan 11/27/2023 Not Ready for Inspection RONNIE MINDANAO
Drywall Nailing 11/28/2023 Approved MICHAEL LEWIS
Interior/Exterior Lathing 11/28/2023 Approved MICHAEL LEWIS
Shower Pan 11/28/2023 Approved MICHAEL LEWIS
HVAC-Rough 12/11/2023 Approved MICHAEL LEWIS
Final 1/5/2024 Corrections Issued MICHAEL LEWIS
Green Building Final 1/5/2024 Corrections Issued MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 1/5/2024 SGSOV Approved MICHAEL LEWIS
Service/Power Release 1/5/2024 Corrections Issued MICHAEL LEWIS
Smoke Detectors 1/5/2024 Corrections Issued MICHAEL LEWIS
Final 1/16/2024 Corrections Issued MICHAEL LEWIS
Green Building Final 1/16/2024 Approved MICHAEL LEWIS
Service/Power Release 1/16/2024 Approved MICHAEL LEWIS
Smoke Detectors 1/16/2024 Approved MICHAEL LEWIS
Final 1/31/2024 OK to Issue CofO MICHAEL LEWIS
Service/Power Release 2/1/2024 Approved MICHAEL LEWIS