4219 N COSTELLO AVE 91423
Certificate Information: 4219 N COSTELLO AVE 91423
- Application / Permit
- 23010-10000-02104
- Plan Check / Job No.
- B23LA09289
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan. New 2-story single family dwelling with a basement and 2-car attached garage.
- Permit Issued
- Issued on 4/10/2024
- Issuing Office
- Current Status
- CofO Issued on 9/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/18/2023 | TU HUA |
| Corrections Issued | 6/5/2023 | TU HUA |
| Quality Review Completed | 6/13/2023 | CHAD DOI |
| Applicant returned to address corrections | 11/2/2023 | TU HUA |
| Applicant returned to address corrections | 2/1/2024 | TU HUA |
| Applicant returned to address corrections | 3/5/2024 | TU HUA |
| Plan Check Approved | 3/8/2024 | TU HUA |
| Issued | 4/10/2024 | APPLICANT |
| CofO in Progress | 9/11/2025 | MISAEL ESPARZA |
| Permit Finaled | 9/26/2025 | RUBEN SALAS |
| CofO Issued | 9/26/2025 | RUBEN SALAS |
| Permit Finaled | 9/26/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/14/2023 | DAGOVERTO GUERRERO |
| Permit | Cleared | 6/14/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 6/16/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 6/16/2023 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 7/12/2023 | LAVEON RIDER |
| Trees in Parkway | Cleared | 8/15/2023 | ADALBERTO VERA |
| Low Impact Development | Cleared | 8/29/2023 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 8/29/2023 | DAGOVERTO GUERRERO |
| Grading Pre-Inspection | Cleared | 2/2/2024 | TU HUA |
| GPI Written Notices | Cleared | 3/6/2024 | TU HUA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Grading | 5/8/2024 | Conditional Approval | MISAEL ESPARZA |
| Deputy Grading | 5/9/2024 | Conditional Approval | JUAN VALENZUELA |
| Deputy Grading | 5/13/2024 | Conditional Approval | JUAN VALENZUELA |
| Deputy Grading | 5/14/2024 | Conditional Approval | JUAN VALENZUELA |
| Deputy Other (see comments) | 5/17/2024 | Conditional Approval | JUAN VALENZUELA |
| Deputy Grading | 5/28/2024 | Conditional Approval | DAVID MATSON |
| Deputy Grading | 6/3/2024 | Conditional Approval | JUAN VALENZUELA |
| Deputy Grading | 6/7/2024 | Conditional Approval | MISAEL ESPARZA |
| Deputy Grading | 6/18/2024 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 8/8/2024 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 8/12/2024 | Partial Approval | MISAEL ESPARZA |
| PLUMBING-Rough | 8/26/2024 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 9/5/2024 | Partial Approval | MISAEL ESPARZA |
| Reinforced Concrete Frame | 10/2/2024 | Partial Approval | MISAEL ESPARZA |
| Reinforced Concrete Frame | 10/7/2024 | Approved | MISAEL ESPARZA |
| Deputy Drilled-In Anchors | 11/13/2024 | Conditional Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2024 | Corrections Issued | MISAEL ESPARZA |
| Deputy Drilled-In Anchors | 11/18/2024 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 11/19/2024 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 11/26/2024 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 12/23/2024 | Approved | MISAEL ESPARZA |
| HVAC-Rough | 12/23/2024 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Rough | 12/30/2024 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 12/30/2024 | Corrections Issued | MISAEL ESPARZA |
| Reinforced Concrete Frame | 1/8/2025 | Partial Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 1/15/2025 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 1/15/2025 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Rough | 1/17/2025 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 1/27/2025 | Partial Inspection | MISAEL ESPARZA |
| Shower Pan | 1/27/2025 | Partial Inspection | MISAEL ESPARZA |
| Special/Order Compliance | 1/27/2025 | Not Ready for Inspection | JUAN VALENZUELA |
| Deputy Wood Construction | 1/30/2025 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 1/30/2025 | Partial Approval | MISAEL ESPARZA |
| Wood Frame | 1/30/2025 | Partial Approval | MISAEL ESPARZA |
| Interior/Exterior Lathing | 2/6/2025 | Partial Approval | MISAEL ESPARZA |
| Shower Pan | 2/6/2025 | Approved | MISAEL ESPARZA |
| Special/Order Compliance | 2/6/2025 | Partial Inspection | JUAN VALENZUELA |
| Interior/Exterior Lathing | 2/14/2025 | Approved | MISAEL ESPARZA |
| Insulation | 3/3/2025 | Corrections Issued | MISAEL ESPARZA |
| Insulation | 3/5/2025 | Corrections Issued | MISAEL ESPARZA |
| Pre-Inspection | 3/5/2025 | Partial Inspection | MISAEL ESPARZA |
| Pre-Inspection | 3/10/2025 | Partial Inspection | JUAN VALENZUELA |
| Drywall Nailing | 3/13/2025 | Partial Inspection | JUAN VALENZUELA |
| Green Building Rough | 3/13/2025 | Partial Inspection | JUAN VALENZUELA |
| ELECTRICAL-Final | 8/15/2025 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Final | 8/15/2025 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Final | 8/26/2025 | Approved | MISAEL ESPARZA |
| HVAC-Final | 8/26/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Final | 8/26/2025 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 8/29/2025 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 8/29/2025 | Approved | MISAEL ESPARZA |
| Final | 8/29/2025 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 8/29/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 8/29/2025 | Approved | MISAEL ESPARZA |
| HVAC-Final | 8/29/2025 | Corrections Issued | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 8/29/2025 | SGSOV Not Required | MISAEL ESPARZA |
| Service/Power Release | 8/29/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Smoke Detectors | 8/29/2025 | Approved | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 8/29/2025 | Approved | MISAEL ESPARZA |
| Final | 9/10/2025 | OK to Issue CofO | MISAEL ESPARZA |
| Green Building Final | 9/10/2025 | Approved | MISAEL ESPARZA |
| Service/Power Release | 9/10/2025 | Approved | MISAEL ESPARZA |