4219 N COSTELLO AVE 91423

Certificate Information: 4219 N COSTELLO AVE 91423

Application / Permit
23010-10000-02104
Plan Check / Job No.
B23LA09289
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan. New 2-story single family dwelling with a basement and 2-car attached garage.
Permit Issued
Issued on 4/10/2024
Issuing Office
Current Status
CofO Issued on 9/26/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/18/2023 APPLICANT
Assigned to Plan Check Engineer 5/18/2023 TU HUA
Corrections Issued 6/5/2023 TU HUA
Quality Review Completed 6/13/2023 CHAD DOI
Applicant returned to address corrections 11/2/2023 TU HUA
Applicant returned to address corrections 2/1/2024 TU HUA
Applicant returned to address corrections 3/5/2024 TU HUA
Plan Check Approved 3/8/2024 TU HUA
Issued 4/10/2024 APPLICANT
CofO in Progress 9/11/2025 MISAEL ESPARZA
Permit Finaled 9/26/2025 RUBEN SALAS
CofO Issued 9/26/2025 RUBEN SALAS
Permit Finaled 9/26/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/14/2023 DAGOVERTO GUERRERO
Permit Cleared 6/14/2023 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 6/16/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 6/16/2023 DAGOVERTO GUERRERO
Hydrant and Access approval Cleared 7/12/2023 LAVEON RIDER
Trees in Parkway Cleared 8/15/2023 ADALBERTO VERA
Low Impact Development Cleared 8/29/2023 SAMUEL LINN
Roof/Waste drainage to street Cleared 8/29/2023 DAGOVERTO GUERRERO
Grading Pre-Inspection Cleared 2/2/2024 TU HUA
GPI Written Notices Cleared 3/6/2024 TU HUA

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Grading 5/8/2024 Conditional Approval MISAEL ESPARZA
Deputy Grading 5/9/2024 Conditional Approval JUAN VALENZUELA
Deputy Grading 5/13/2024 Conditional Approval JUAN VALENZUELA
Deputy Grading 5/14/2024 Conditional Approval JUAN VALENZUELA
Deputy Other (see comments) 5/17/2024 Conditional Approval JUAN VALENZUELA
Deputy Grading 5/28/2024 Conditional Approval DAVID MATSON
Deputy Grading 6/3/2024 Conditional Approval JUAN VALENZUELA
Deputy Grading 6/7/2024 Conditional Approval MISAEL ESPARZA
Deputy Grading 6/18/2024 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 8/8/2024 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 8/12/2024 Partial Approval MISAEL ESPARZA
PLUMBING-Rough 8/26/2024 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 9/5/2024 Partial Approval MISAEL ESPARZA
Reinforced Concrete Frame 10/2/2024 Partial Approval MISAEL ESPARZA
Reinforced Concrete Frame 10/7/2024 Approved MISAEL ESPARZA
Deputy Drilled-In Anchors 11/13/2024 Conditional Approval ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 11/14/2024 Corrections Issued MISAEL ESPARZA
Deputy Drilled-In Anchors 11/18/2024 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 11/19/2024 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 11/26/2024 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 12/23/2024 Approved MISAEL ESPARZA
HVAC-Rough 12/23/2024 Corrections Issued MISAEL ESPARZA
HVAC-Rough 12/30/2024 Approved MISAEL ESPARZA
PLUMBING-Rough 12/30/2024 Corrections Issued MISAEL ESPARZA
Reinforced Concrete Frame 1/8/2025 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 1/15/2025 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 1/15/2025 Approved MISAEL ESPARZA
ELECTRICAL-Rough 1/17/2025 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 1/27/2025 Partial Inspection MISAEL ESPARZA
Shower Pan 1/27/2025 Partial Inspection MISAEL ESPARZA
Special/Order Compliance 1/27/2025 Not Ready for Inspection JUAN VALENZUELA
Deputy Wood Construction 1/30/2025 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 1/30/2025 Partial Approval MISAEL ESPARZA
Wood Frame 1/30/2025 Partial Approval MISAEL ESPARZA
Interior/Exterior Lathing 2/6/2025 Partial Approval MISAEL ESPARZA
Shower Pan 2/6/2025 Approved MISAEL ESPARZA
Special/Order Compliance 2/6/2025 Partial Inspection JUAN VALENZUELA
Interior/Exterior Lathing 2/14/2025 Approved MISAEL ESPARZA
Insulation 3/3/2025 Corrections Issued MISAEL ESPARZA
Insulation 3/5/2025 Corrections Issued MISAEL ESPARZA
Pre-Inspection 3/5/2025 Partial Inspection MISAEL ESPARZA
Pre-Inspection 3/10/2025 Partial Inspection JUAN VALENZUELA
Drywall Nailing 3/13/2025 Partial Inspection JUAN VALENZUELA
Green Building Rough 3/13/2025 Partial Inspection JUAN VALENZUELA
ELECTRICAL-Final 8/15/2025 Corrections Issued MISAEL ESPARZA
PLUMBING-Final 8/15/2025 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Final 8/26/2025 Approved MISAEL ESPARZA
HVAC-Final 8/26/2025 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Final 8/26/2025 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 8/29/2025 Approved MISAEL ESPARZA
Drywall Nailing 8/29/2025 Approved MISAEL ESPARZA
Final 8/29/2025 Corrections Issued MISAEL ESPARZA
Green Building Final 8/29/2025 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 8/29/2025 Approved MISAEL ESPARZA
HVAC-Final 8/29/2025 Corrections Issued MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 8/29/2025 SGSOV Not Required MISAEL ESPARZA
Service/Power Release 8/29/2025 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 8/29/2025 Approved MISAEL ESPARZA
Verify Sprinkler Sign Off 8/29/2025 Approved MISAEL ESPARZA
Final 9/10/2025 OK to Issue CofO MISAEL ESPARZA
Green Building Final 9/10/2025 Approved MISAEL ESPARZA
Service/Power Release 9/10/2025 Approved MISAEL ESPARZA