4417 W CROMWELL AVE 90027
Certificate Information: 4417 W CROMWELL AVE 90027
- Application / Permit
- 23010-10000-02101
- Plan Check / Job No.
- B23LA09282
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SFD WITH ATTACHED 2-CAR GARAGE PER SB9 TWO-UNIT DEVELOPMENT CA 65852.21 NFPA 13D SOLAR INSTALLATION REQUIRED TO MEET 2.65KW PER TITLE 24 PRIOR TO COFO
- Permit Issued
- Issued on 9/16/2024
- Issuing Office
- Metro
- Current Status
- Issued on 9/16/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/1/2023 | VIVIAN LAO |
| Corrections Issued | 6/6/2023 | VIVIAN LAO |
| Quality Review Completed | 6/9/2023 | KEN GILL |
| Building Plans Picked Up | 6/14/2023 | APPLICANT |
| Applicant returned to address corrections | 7/7/2023 | VIVIAN LAO |
| Applicant returned to address corrections | 8/7/2023 | VIVIAN LAO |
| Applicant returned to address corrections | 8/9/2023 | VIVIAN LAO |
| Applicant returned to address corrections | 10/16/2023 | VIVIAN LAO |
| Plan Check Approved | 11/27/2023 | VIVIAN LAO |
| Issued | 9/16/2024 | APPLICANT |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 6/22/2023 | VIVIAN LAO |
| Grading Pre-Inspection | Cleared | 6/22/2023 | VIVIAN LAO |
| Address approval | Cleared | 7/3/2023 | JEANIE LAM |
| BHO/Hillside ordinance | Cleared | 7/3/2023 | JEANIE LAM |
| BHO/Hillside ordinance | Cleared | 7/3/2023 | JEANIE LAM |
| BHO/Hillside ordinance | Cleared | 7/3/2023 | JEANIE LAM |
| BHO/Hillside ordinance | Cleared | 7/3/2023 | JEANIE LAM |
| BHO/Hillside ordinance | Cleared | 7/3/2023 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 7/6/2023 | JEANIE LAM |
| Sewer availability | Cleared | 7/6/2023 | JEANIE LAM |
| Trees in Parkway | Cleared | 7/6/2023 | ADALBERTO VERA |
| Permit | Cleared | 7/12/2023 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 7/25/2023 | JOHN CONNEALLY |
| Senate Bill 9 | Cleared | 7/26/2023 | ANNA VIDAL |
| Low Impact Development (LID) | Cleared | 11/15/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 11/16/2023 | JUSTIN BICOL |
Contact Information
| Contractor | Adus Master Inc; Lic. No.: 1091203-B | 655 N CENTRAL AVENUE #1756 GLENDALE, CA 91203 |
| Engineer | Kim,, Paul; Lic. No.: GE2066 | 21266 E SUNDANCE ST WALNUT, CA 91789 |
| Engineer | Lee,, Sang Youck; Lic. No.: S3821 | 3531 BROOKHILL ST GLENDALE, CA 91214 |
| Engineer | Pukkanasut,, Jirayus; Lic. No.: C73728 | 1424 ROLLING HILLS DR FULLERTON, CA 92835 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/25/2024 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 10/15/2024 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 10/15/2024 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 11/18/2024 | Partial Approval | BRENDAN MORELLI |
| Excavation/Setback/Form/Re-Bar | 12/10/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 12/19/2024 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 12/27/2024 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 1/30/2025 | Approved | ENRIQUE MIRELES |
| Sewer | 1/30/2025 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 2/24/2025 | Approved | ENRIQUE MIRELES |
| Deputy Steel/Welding | 3/12/2025 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2025 | Approved | ENRIQUE MIRELES |
| Wood Frame | 6/12/2025 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 6/18/2025 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 6/18/2025 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 6/18/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 7/3/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| Green Building Rough | 7/3/2025 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 7/3/2025 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 7/3/2025 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 7/3/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 7/3/2025 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 7/8/2025 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 7/14/2025 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 7/24/2025 | Approved | ENRIQUE MIRELES |
| Insulation | 7/24/2025 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 8/13/2025 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 8/13/2025 | Approved | ENRIQUE MIRELES |
| Shower Pan | 8/13/2025 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 1/27/2026 | Approved | ENRIQUE MIRELES |
| Service/Power Release | 2/19/2026 | Corrections Issued | ENRIQUE MIRELES |