4211-4213 N AGNES AVE 91604

Certificate Information: 4211-4213 N AGNES AVE 91604

Application / Permit
23010-10000-02099
Plan Check / Job No.
B23LA09273
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
*EPLAN* NEW 2-STORY SFD WITH ATTACHED 2-CAR GARAGE AND ADU PER LAMC 12.22.A.33(c)-(d). NFPA 13D SOLAR INSTALLATION TO MEET 2.97KW PER TITLE 24 REQUIRED PRIOR TO COFO.
Permit Issued
Issued on 5/7/2024
Issuing Office
Current Status
CofO Issued on 6/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/18/2023 APPLICANT
Assigned to Plan Check Engineer 5/25/2023 VIVIAN LAO
Corrections Issued 5/30/2023 VIVIAN LAO
Quality Review Completed 5/30/2023 GARO TELMI
Applicant returned to address corrections 10/18/2023 VIVIAN LAO
Applicant returned to address corrections 10/19/2023 VIVIAN LAO
Applicant returned to address corrections 2/2/2024 VIVIAN LAO
Plan Check Approved 2/7/2024 VIVIAN LAO
Issued 5/7/2024 APPLICANT
CofO in Progress 5/7/2025 JAVIER RAMOS JR
Permit Finaled 6/6/2025 RUBEN SALAS
CofO Issued 6/6/2025 RUBEN SALAS
Permit Finaled 6/6/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/17/2023 CARLOS AGUILERA
ZI Cleared 7/3/2023 DAVID URITA
Eng Process Fee Ord 176,300 Cleared 7/19/2023 CARLOS AGUILERA
Sewer availability Cleared 7/19/2023 CARLOS AGUILERA
Hydrant and Access approval Cleared 7/28/2023 KURT CORRAL
Low Impact Development (LID) Cleared 12/14/2023 SAMUEL LINN
Roof/Waste drainage to street Cleared 12/14/2023 CARLOS AGUILERA
Permit Cleared 12/21/2023 CARLOS AGUILERA
Trees in Parkway Cleared 12/21/2023 ADALBERTO VERA

Contact Information

Contractor Advanced Construction; Lic. No.: 801955-B       ,
Contractor Gemilyan Karen; Lic. No.: 801955-B       ,
Engineer Burgess,, John J; Lic. No.: C21877 27758 SANTA MARGARITA PKWY 284      MISSION VIEJO, CA 92691
Engineer Dermendjian,, Raffi Hrag; Lic. No.: C88261 9325 SHOSHONE AVENUE      NORTHRIDGE, CA 91325
Engineer Naraghi-Arani,, Kamran; Lic. No.: C40985 30423 CANWOOD ST STE 223      AGOURA HILLS, CA 91301

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 6/21/2024 Corrections Issued CHRISTOPHER ROJAS
Excavation/Setback/Form/Re-Bar 6/24/2024 Approved CHRISTOPHER ROJAS
Underground Mechanical 6/24/2024 Approved CHRISTOPHER ROJAS
Footing/Foundation/Slab 6/26/2024 Partial Approval CHRISTOPHER ROJAS
Deputy Reinf. Concrete 6/27/2024 Conditional Approval DAVID MATSON
Deputy Steel/Welding 6/27/2024 Conditional Approval DAVID MATSON
Piling/Pier/Caisson 7/9/2024 Approved CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 8/1/2024 Partial Approval CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 8/29/2024 Partial Approval CHRISTOPHER ROJAS
HVAC-Rough 10/7/2024 Corrections Issued JOSE AVILA
PLUMBING-Rough 10/7/2024 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 10/15/2024 Approved CHRISTOPHER ROJAS
HVAC-Rough 10/15/2024 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 10/15/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 10/22/2024 Approved MISAEL ESPARZA
Green Building Rough 10/22/2024 Not Ready for Inspection MISAEL ESPARZA
Verify Sprinkler Sign Off 10/22/2024 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 11/1/2024 Corrections Issued CHRISTOPHER ROJAS
Interior/Exterior Lathing 11/1/2024 Partial Approval CHRISTOPHER ROJAS
Insulation 11/8/2024 Approved CHRISTOPHER ROJAS
Shower Pan 11/8/2024 Approved CHRISTOPHER ROJAS
Drywall Nailing 11/19/2024 Approved CHRISTOPHER ROJAS
Green Building Rough 11/19/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 11/22/2024 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 12/4/2024 Approved CHRISTOPHER ROJAS
Underground Mechanical 1/22/2025 Partial Approval CHRISTOPHER ROJAS
Sewer 2/24/2025 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 4/15/2025 Approved JAVIER RAMOS JR
HVAC-Final 4/15/2025 Approved JAVIER RAMOS JR
PLUMBING-Final 4/15/2025 Approved JAVIER RAMOS JR
Service/Power Release 4/30/2025 Approved JUAN VALENZUELA
Final 5/5/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 5/5/2025 Approved ROBERTO PALACIOS-LOPEZ
Green Building Final 5/5/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 5/5/2025 SGSOV Not Required ROBERTO PALACIOS-LOPEZ
Smoke Detectors 5/5/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 5/6/2025 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 5/6/2025 Approved JAVIER RAMOS JR