4203-4205 N AGNES AVE 91604

Certificate Information: 4203-4205 N AGNES AVE 91604

Application / Permit
23010-10000-02098
Plan Check / Job No.
B23LA09270
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
*EPLAN* NEW 2-STORY SFD WITH ATTACHED 2-CAR GARAGE, TRELLIS, AND ADU PER LAMC 12.22A.33(c)-(d). NFPA 13D
Permit Issued
Issued on 5/7/2024
Issuing Office
Current Status
CofO Issued on 8/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/18/2023 APPLICANT
Assigned to Plan Check Engineer 5/25/2023 VIVIAN LAO
Corrections Issued 5/31/2023 VIVIAN LAO
Quality Review Completed 5/31/2023 GARO TELMI
Applicant returned to address corrections 9/13/2023 VIVIAN LAO
Applicant returned to address corrections 1/25/2024 VIVIAN LAO
Plan Check Approved 1/26/2024 VIVIAN LAO
Issued 5/7/2024 APPLICANT
CofO in Progress 7/7/2025 JAVIER RAMOS JR
Permit Finaled 8/27/2025 RUBEN SALAS
Permit Finaled 8/27/2025 RUBEN SALAS
CofO Issued 8/27/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/17/2023 CARLOS AGUILERA
ZI Cleared 6/26/2023 NELSON RODRIGUEZ
Eng Process Fee Ord 176,300 Cleared 7/19/2023 CARLOS AGUILERA
Sewer availability Cleared 7/19/2023 CARLOS AGUILERA
Hydrant and Access approval Cleared 7/28/2023 KURT CORRAL
Trees in Parkway Cleared 10/23/2023 ADALBERTO VERA
Permit Cleared 11/1/2023 NIKKI ZULUETA
Low Impact Development (LID) Cleared 12/13/2023 SAMUEL LINN
Roof/Waste drainage to street Cleared 12/15/2023 NIKKI ZULUETA

Contact Information

Architect Biglin,, Brian W; Lic. No.: C29771 1152 ADIRONDACK COURT      SIMI VALLEY, CA 93065
Contractor Advanced Construction; Lic. No.: 801955-B       ,
Contractor Gemilyan Karen; Lic. No.: 801955-B       ,
Engineer Dermendjian,, Raffi Hrag; Lic. No.: C88261 9325 SHOSHONE AVENUE      NORTHRIDGE, CA 91325
Engineer Naraghi-Arani,, Kamran; Lic. No.: NA40985       ,

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 6/21/2024 Corrections Issued CHRISTOPHER ROJAS
Excavation/Setback/Form/Re-Bar 6/26/2024 Approved CHRISTOPHER ROJAS
Underground Mechanical 6/26/2024 Partial Approval CHRISTOPHER ROJAS
Footing/Foundation/Slab 7/9/2024 Approved CHRISTOPHER ROJAS
Deputy Reinf. Concrete 7/10/2024 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 8/7/2024 Partial Approval CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 9/5/2024 Partial Approval CHRISTOPHER ROJAS
Deputy Wood Construction 9/23/2024 Conditional Approval ROBERT GOLD
ELECTRICAL-Rough 11/19/2024 Corrections Issued CHRISTOPHER ROJAS
HVAC-Rough 11/19/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 11/20/2024 Approved CHRISTOPHER ROJAS
Green Building Rough 11/20/2024 Approved CHRISTOPHER ROJAS
PLUMBING-Rough 11/20/2024 Approved CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 11/20/2024 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 12/4/2024 Partial Approval CHRISTOPHER ROJAS
Shower Pan 12/4/2024 Approved CHRISTOPHER ROJAS
Insulation 12/11/2024 Approved CHRISTOPHER ROJAS
Drywall Nailing 12/17/2024 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 1/22/2025 Approved CHRISTOPHER ROJAS
Sewer 3/11/2025 Approved JOSE AVILA
ELECTRICAL-Final 6/10/2025 Approved JAVIER RAMOS JR
PLUMBING-Final 6/10/2025 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 6/10/2025 SGSOV Not Required JAVIER RAMOS JR
Smoke Detectors 6/10/2025 Approved JAVIER RAMOS JR
Final 6/17/2025 Corrections Issued JAVIER RAMOS JR
Green Building Final 6/17/2025 Partial Approval JAVIER RAMOS JR
HVAC-Final 6/17/2025 Approved JAVIER RAMOS JR
Service/Power Release 6/17/2025 Not Ready for Inspection JAVIER RAMOS JR
Green Building Final 6/18/2025 Approved JAVIER RAMOS JR
Final 7/7/2025 OK to Issue CofO JAVIER RAMOS JR
Service/Power Release 7/7/2025 Approved JAVIER RAMOS JR