4203-4205 N AGNES AVE 91604
Certificate Information: 4203-4205 N AGNES AVE 91604
- Application / Permit
- 23010-10000-02098
- Plan Check / Job No.
- B23LA09270
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *EPLAN* NEW 2-STORY SFD WITH ATTACHED 2-CAR GARAGE, TRELLIS, AND ADU PER LAMC 12.22A.33(c)-(d). NFPA 13D
- Permit Issued
- Issued on 5/7/2024
- Issuing Office
- Current Status
- CofO Issued on 8/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/25/2023 | VIVIAN LAO |
| Corrections Issued | 5/31/2023 | VIVIAN LAO |
| Quality Review Completed | 5/31/2023 | GARO TELMI |
| Applicant returned to address corrections | 9/13/2023 | VIVIAN LAO |
| Applicant returned to address corrections | 1/25/2024 | VIVIAN LAO |
| Plan Check Approved | 1/26/2024 | VIVIAN LAO |
| Issued | 5/7/2024 | APPLICANT |
| CofO in Progress | 7/7/2025 | JAVIER RAMOS JR |
| Permit Finaled | 8/27/2025 | RUBEN SALAS |
| Permit Finaled | 8/27/2025 | RUBEN SALAS |
| CofO Issued | 8/27/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/17/2023 | CARLOS AGUILERA |
| ZI | Cleared | 6/26/2023 | NELSON RODRIGUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/19/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 7/19/2023 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 7/28/2023 | KURT CORRAL |
| Trees in Parkway | Cleared | 10/23/2023 | ADALBERTO VERA |
| Permit | Cleared | 11/1/2023 | NIKKI ZULUETA |
| Low Impact Development (LID) | Cleared | 12/13/2023 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 12/15/2023 | NIKKI ZULUETA |
Contact Information
| Architect | Biglin,, Brian W; Lic. No.: C29771 | 1152 ADIRONDACK COURT SIMI VALLEY, CA 93065 |
| Contractor | Advanced Construction; Lic. No.: 801955-B | , |
| Contractor | Gemilyan Karen; Lic. No.: 801955-B | , |
| Engineer | Dermendjian,, Raffi Hrag; Lic. No.: C88261 | 9325 SHOSHONE AVENUE NORTHRIDGE, CA 91325 |
| Engineer | Naraghi-Arani,, Kamran; Lic. No.: NA40985 | , |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/21/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Excavation/Setback/Form/Re-Bar | 6/26/2024 | Approved | CHRISTOPHER ROJAS |
| Underground Mechanical | 6/26/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 7/9/2024 | Approved | CHRISTOPHER ROJAS |
| Deputy Reinf. Concrete | 7/10/2024 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 9/5/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Deputy Wood Construction | 9/23/2024 | Conditional Approval | ROBERT GOLD |
| ELECTRICAL-Rough | 11/19/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| HVAC-Rough | 11/19/2024 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 11/20/2024 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 11/20/2024 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 11/20/2024 | Approved | CHRISTOPHER ROJAS |
| Verify Sprinkler Sign Off | 11/20/2024 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 12/4/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Shower Pan | 12/4/2024 | Approved | CHRISTOPHER ROJAS |
| Insulation | 12/11/2024 | Approved | CHRISTOPHER ROJAS |
| Drywall Nailing | 12/17/2024 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 1/22/2025 | Approved | CHRISTOPHER ROJAS |
| Sewer | 3/11/2025 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 6/10/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 6/10/2025 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 6/10/2025 | SGSOV Not Required | JAVIER RAMOS JR |
| Smoke Detectors | 6/10/2025 | Approved | JAVIER RAMOS JR |
| Final | 6/17/2025 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 6/17/2025 | Partial Approval | JAVIER RAMOS JR |
| HVAC-Final | 6/17/2025 | Approved | JAVIER RAMOS JR |
| Service/Power Release | 6/17/2025 | Not Ready for Inspection | JAVIER RAMOS JR |
| Green Building Final | 6/18/2025 | Approved | JAVIER RAMOS JR |
| Final | 7/7/2025 | OK to Issue CofO | JAVIER RAMOS JR |
| Service/Power Release | 7/7/2025 | Approved | JAVIER RAMOS JR |