12085 W VALLEYHEART DR 91604
Certificate Information: 12085 W VALLEYHEART DR 91604
- Application / Permit
- 23010-10000-02097
- Plan Check / Job No.
- B23LA09266
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: 1) New 2-Story Single Family Dwelling to be fully sprinklered NFPA 13D
- Permit Issued
- Issued on 4/28/2025
- Issuing Office
- Current Status
- CofO Issued on 5/12/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/25/2023 | MARCELA FRANQUEZ |
| Corrections Issued | 5/27/2023 | MARCELA FRANQUEZ |
| Quality Review Completed | 6/15/2023 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 12/18/2023 | MARCELA FRANQUEZ |
| Applicant returned to address corrections | 12/17/2024 | MARCELA FRANQUEZ |
| Plan Check Approved | 1/31/2025 | MARCELA FRANQUEZ |
| Plan Check Approved | 4/21/2025 | MARCELA FRANQUEZ |
| Issued | 4/28/2025 | APPLICANT |
| CofO in Progress | 3/6/2026 | JAVIER RAMOS JR |
| CofO Issued | 5/12/2026 | RUBEN SALAS |
| Permit Finaled | 5/12/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/19/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 7/19/2023 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 7/31/2023 | KURT CORRAL |
| ZI | Cleared | 12/19/2023 | YINGSHI HUANG |
| Roof/Waste drainage to street | Cleared | 2/1/2024 | CARLOS AGUILERA |
| Low Impact Development (LID) | Cleared | 6/25/2024 | LUIS LUVANO |
Contact Information
| Contractor | Advanced Construction; Lic. No.: 801955-B | , |
| Contractor | Gemilyan Karen; Lic. No.: 801955-B | , |
| Engineer | Naraghi-Arani,, Kamran; Lic. No.: NA40985 | , |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/19/2025 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 5/19/2025 | Partial Approval | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 6/5/2025 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 7/22/2025 | Partial Approval | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 7/22/2025 | Approved | JAVIER RAMOS JR |
| Deputy Steel/Welding | 7/31/2025 | Conditional Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 8/28/2025 | Corrections Issued | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 9/26/2025 | Partial Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 9/26/2025 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 9/26/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Rough | 9/26/2025 | Approved | JAVIER RAMOS JR |
| Sewer | 9/26/2025 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 9/26/2025 | Approved | JAVIER RAMOS JR |
| Verify Sprinkler Sign Off | 9/26/2025 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 9/29/2025 | Partial Approval | JAVIER RAMOS JR |
| Shower Pan | 9/29/2025 | Not Ready for Inspection | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 9/30/2025 | Partial Approval | JAVIER RAMOS JR |
| Deputy Wood Construction | 10/2/2025 | Conditional Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 10/3/2025 | Approved | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/3/2025 | Approved | DAVID MATSON |
| Green Building Rough | 10/3/2025 | Approved | DAVID MATSON |
| Insulation | 10/3/2025 | Approved | DAVID MATSON |
| Interior/Exterior Lathing | 10/14/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Shower Pan | 10/14/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 10/16/2025 | Approved | CHRISTOPHER MORFIN |
| Green Building Final | 2/4/2026 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 2/4/2026 | Partial Approval | JAVIER RAMOS JR |
| Gas Test | 2/19/2026 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 2/19/2026 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 2/19/2026 | SGSOV Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 2/26/2026 | Approved | JAVIER RAMOS JR |
| Final | 2/26/2026 | Corrections Issued | JAVIER RAMOS JR |
| Service/Power Release | 2/26/2026 | Approved | JAVIER RAMOS JR |
| Smoke Detectors | 2/26/2026 | Approved | JAVIER RAMOS JR |
| Structural Steel Frame | 2/26/2026 | Approved | JAVIER RAMOS JR |
| Final | 3/6/2026 | OK to Issue CofO | JAVIER RAMOS JR |
| HVAC-Final | 3/6/2026 | Approved | JAVIER RAMOS JR |