5238-5240 W OLYMPIC BLVD 90036
Certificate Information: 5238-5240 W OLYMPIC BLVD 90036
- Application / Permit
- 23010-10000-02085
- Plan Check / Job No.
- B23LA09200
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ADDITION TO 1ST FLOOR GARAGE. NEW 2ND FLOOR ADDITION FOR TWO DETACHED ACCESSORY DWELLING UNITS PER CA Govt. Code 65852.2(e)(1)(D) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 8/27/2024
- Issuing Office
- Current Status
- CofO Issued on 6/8/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 6/1/2023 | CARLOS MONTES |
| Corrections Issued | 6/8/2023 | CARLOS MONTES |
| Quality Review Completed | 6/8/2023 | GARO TELMI |
| Applicant returned to address corrections | 11/14/2023 | CARLOS MONTES |
| Applicant returned to address corrections | 3/18/2024 | CARLOS MONTES |
| Plan Check Approved | 8/6/2024 | CARLOS MONTES |
| Issued | 8/27/2024 | APPLICANT |
| CofO in Progress | 6/2/2025 | RONNIE MINDANAO |
| Permit Finaled | 6/8/2025 | DEROLD HAUFF |
| CofO Issued | 6/8/2025 | DEROLD HAUFF |
| Permit Finaled | 6/8/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| CPC | Cleared | 7/10/2023 | FIPE LEILUA |
| ZA Case | Cleared | 7/10/2023 | FIPE LEILUA |
| Address approval | Cleared | 7/31/2023 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 7/31/2023 | JEANIE LAM |
| Construction near power lines | Cleared | 8/21/2023 | RIDWAN HARDY |
| Sewer availability | Cleared | 8/23/2023 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 8/24/2023 | TREVOR QUAN |
Contact Information
| Contractor | Neo Builders And Design Inc; Lic. No.: 1114778-B | , |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 10/18/2024 | Approved | RONNIE MINDANAO |
| Underground Mechanical | 10/18/2024 | Approved | RONNIE MINDANAO |
| Footing/Foundation/Slab | 10/24/2024 | Approved | RONNIE MINDANAO |
| METHANE-Barrier | 10/24/2024 | Approved | RONNIE MINDANAO |
| METHANE-Subgrade | 10/24/2024 | Approved | RONNIE MINDANAO |
| Deputy Reinf. Concrete | 11/4/2024 | Conditional Approval | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 11/12/2024 | Partial Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 11/25/2024 | Corrections Issued | RONNIE MINDANAO |
| Pre-Inspection | 12/13/2024 | Not Ready for Inspection | JOSE MACIAS |
| Pre-Inspection | 12/19/2024 | Order to Comply Issued | RONNIE MINDANAO |
| Deputy Steel/Welding | 12/20/2024 | Conditional Approval | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2024 | Conditional Approval | NICHOLAS LOPEZ |
| Special/Order Compliance | 12/23/2024 | Approved | ANDREW NAVE |
| ELECTRICAL-Rough | 1/15/2025 | Corrections Issued | RONNIE MINDANAO |
| HVAC-Rough | 1/15/2025 | Corrections Issued | RONNIE MINDANAO |
| PLUMBING-Rough | 1/15/2025 | Approved | RONNIE MINDANAO |
| ELECTRICAL-Rough | 1/21/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| HVAC-Rough | 1/21/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Shower Pan | 1/23/2025 | Approved | RONNIE MINDANAO |
| Insulation | 1/27/2025 | Corrections Issued | RONNIE MINDANAO |
| Interior/Exterior Lathing | 1/27/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 1/29/2025 | Conditional Approval | RONNIE MINDANAO |
| ELECTRICAL-Rough | 1/29/2025 | Approved | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 1/29/2025 | Partial Approval | RONNIE MINDANAO |
| Green Building Rough | 1/29/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| HVAC-Rough | 1/29/2025 | Approved | RONNIE MINDANAO |
| Insulation | 1/29/2025 | Corrections Issued | RONNIE MINDANAO |
| Interior/Exterior Lathing | 1/29/2025 | Approved | RONNIE MINDANAO |
| METHANE-Rough | 1/29/2025 | Approved | RONNIE MINDANAO |
| Insulation | 2/4/2025 | Corrections Issued | RONNIE MINDANAO |
| Drywall Nailing | 2/10/2025 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 3/27/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| HVAC-Final | 3/27/2025 | Corrections Issued | RONNIE MINDANAO |
| PLUMBING-Final | 3/27/2025 | Corrections Issued | RONNIE MINDANAO |
| ELECTRICAL-Final | 4/4/2025 | Corrections Issued | RONNIE MINDANAO |
| HVAC-Final | 4/4/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| PLUMBING-Final | 4/4/2025 | Approved | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 4/9/2025 | Approved | RONNIE MINDANAO |
| ELECTRICAL-Final | 4/9/2025 | Approved | RONNIE MINDANAO |
| Final | 4/9/2025 | Corrections Issued | RONNIE MINDANAO |
| Green Building Final | 4/9/2025 | Approved | RONNIE MINDANAO |
| Green Building Rough | 4/9/2025 | Approved | RONNIE MINDANAO |
| HVAC-Final | 4/9/2025 | Approved | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 4/9/2025 | SGSOV Approved | RONNIE MINDANAO |
| Smoke Detectors | 4/9/2025 | Approved | RONNIE MINDANAO |
| Final | 4/24/2025 | Corrections Issued | RONNIE MINDANAO |
| Final | 5/6/2025 | Not Ready for Inspection | RONNIE MINDANAO |
| Service/Power Release | 5/6/2025 | Approved | RONNIE MINDANAO |
| Final | 5/28/2025 | No Access for Inspection | JOSE MACIAS |
| Final | 5/30/2025 | OK to Issue CofO | RONNIE MINDANAO |