18322 W INGOMAR ST 91335

Certificate Information: 18322 W INGOMAR ST 91335

Application / Permit
23010-10000-02028
Plan Check / Job No.
B23LA08979
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: (N) 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33.(c)-(d)
Permit Issued
Issued on 9/18/2023
Issuing Office
Valley
Current Status
CofO Issued on 8/30/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/16/2023 APPLICANT
Assigned to Plan Check Engineer 6/1/2023 DANIEL YIP
Corrections Issued 6/8/2023 DANIEL YIP
Quality Review Completed 6/8/2023 GARO TELMI
Applicant returned to address corrections 8/14/2023 DANIEL YIP
Applicant returned to address corrections 8/15/2023 DANIEL YIP
Plan Check Approved 8/31/2023 DANIEL YIP
Plan Check Approved 9/13/2023 DANIEL YIP
No Progress 9/13/2023 DANIEL YIP
Plan Check Approved 9/13/2023 DANIEL YIP
Issued 9/18/2023 APPLICANT
CofO in Progress 7/14/2025 JUAN ALVARADO
Permit Finaled 8/30/2025 RUBEN SALAS
CofO Issued 8/30/2025 RUBEN SALAS
Permit Finaled 8/30/2025 RUBEN SALAS

Permit Application Clearance Information

Low Impact Development (LID) Cleared 7/24/2023 MELINEH AGHAKHABIAN
Address approval Cleared 7/27/2023 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 7/27/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 8/1/2023 CARLOS AGUILERA
Sewer availability Cleared 8/1/2023 CARLOS AGUILERA

Contact Information

Contractor Los Angeles Retrofit & Construction Inc; Lic. No.: 1023060-B 18075 VENTURA BLVD STE #101      ENCINO, CA 91316
Engineer Maalouf,, Sami; Lic. No.: C53210 15445 VENTURA BLVD STE 367      SHERMAN OAKS, CA 91403

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/6/2024 Partial Approval MORRIS JACKSON
Sewer 6/6/2024 Approved MORRIS JACKSON
Underground Mechanical 6/6/2024 Not Ready for Inspection MORRIS JACKSON
Footing/Foundation/Slab 6/10/2024 Approved JEFFREY BULL
ELECTRICAL-Rough 6/11/2024 Partial Approval JEFFREY BULL
PLUMBING-Rough 6/11/2024 Partial Approval JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 7/12/2024 Partial Approval JEFFREY BULL
BUILDING-Rough-Frame 10/7/2024 Not Ready for Inspection JEFFREY BULL
ELECTRICAL-Rough 10/7/2024 Approved JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 10/7/2024 Approved JEFFREY BULL
HVAC-Rough 10/7/2024 Approved JEFFREY BULL
PLUMBING-Rough 10/7/2024 Approved JEFFREY BULL
Interior/Exterior Lathing 10/18/2024 Partial Approval DAVID SCANTLIN
Insulation 10/24/2024 Corrections Issued JEFFREY BULL
Drywall Nailing 11/1/2024 Approved JEFFREY BULL
Green Building Rough 11/1/2024 Approved JEFFREY BULL
Interior/Exterior Lathing 11/21/2024 Partial Approval GEVORK IPCHYAN
Shower Pan 11/21/2024 Approved GEVORK IPCHYAN
BUILDING-Rough-Frame 7/8/2025 Approved JUAN ALVARADO
Final 7/8/2025 Corrections Issued JUAN ALVARADO
Green Building Final 7/8/2025 Approved JUAN ALVARADO
SGSOV-Seismic Gas S/O Valve 7/8/2025 SGSOV Not Required JUAN ALVARADO
Service/Power Release 7/8/2025 Not Required JUAN ALVARADO
Smoke Detectors 7/8/2025 Approved JUAN ALVARADO
Verify Sprinkler Sign Off 7/8/2025 Approved JUAN ALVARADO
ELECTRICAL-Final 7/11/2025 Approved JUAN ALVARADO
Final 7/11/2025 OK to Issue CofO JUAN ALVARADO
HVAC-Final 7/11/2025 Approved JUAN ALVARADO
PLUMBING-Final 7/11/2025 Approved JUAN ALVARADO