22521 W VICTORY BLVD 91307
Certificate Information: 22521 W VICTORY BLVD 91307
- Application / Permit
- 23010-10000-02026
- Plan Check / Job No.
- B23LA08976
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Patio Cover
- Work Description
- PROPOSED 12' X 52'-6" 1-STORY PATIO COVER WITH STORAGE ROOMS AT REAR OF LOT.
- Permit Issued
- Issued on 5/24/2023
- Issuing Office
- Metro
- Current Status
- CofO in Progress on 10/30/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/15/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/18/2023 | LAWRENCE QUIRANTE |
| Corrections Issued | 5/20/2023 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 5/22/2023 | APPLICANT |
| Applicant returned to address corrections | 5/23/2023 | AUNG SOE |
| Plan Check Approved | 5/24/2023 | JOSEPH RAFOLS |
| Issued | 5/24/2023 | APPLICANT |
| CofO in Progress | 7/5/2023 | TROY SANDERS |
| No Progress | 10/30/2024 | TROY SANDERS |
| CofO in Progress | 10/30/2024 | TROY SANDERS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 5/24/2023 | TORI CHEN |
| Eng Process Fee Ord 176,300 | Cleared | 5/24/2023 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 5/24/2023 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Martirossyan,, Armen; Lic. No.: C64223 | 802 PORTOLA AVE GLENDALE, CA 91206 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/30/2023 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 6/5/2023 | Partial Approval | HORACE FULTZ |
| BUILDING-Rough-Frame | 6/21/2023 | Approved | HORACE FULTZ |
| ELECTRICAL-Rough | 6/21/2023 | Approved | HORACE FULTZ |
| Green Building Rough | 6/21/2023 | Approved | HORACE FULTZ |
| Verify Sprinkler Sign Off | 6/21/2023 | Approved | HORACE FULTZ |
| Drywall Nailing | 6/23/2023 | Approved | TROY SANDERS |
| Final | 6/29/2023 | Corrections Issued | TROY SANDERS |
| Green Building Final | 6/29/2023 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 6/29/2023 | SGSOV Approved | TROY SANDERS |
| Service/Power Release | 6/29/2023 | Approved | TROY SANDERS |
| Smoke Detectors | 6/29/2023 | Approved | TROY SANDERS |
| Final | 7/3/2023 | OK to Issue CofO | TROY SANDERS |
| Special/Order Compliance | 10/29/2024 | Corrections Issued | TROY SANDERS |