8016 N FAIR AVE 1-39 91352

Certificate Information: 8016 N FAIR AVE 1-39 91352

Application / Permit
23010-10000-01978
Plan Check / Job No.
B23LA08766
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 4 STORY 39 UNITS, 100% AFFORDABLE HOUSING (1 VERY LOW, 30 LOW, 7 MODERATE INCOME, 1 MANAGER UNITS) APARTMENT TO INCLUDE 3 STORY TYPE VA APARTMENT OVER 1 STORY TYPE IA PARKING/LOBBY PER 12.22.A.25 STATE DENSITY BONUS
Permit Issued
Issued on 3/18/2025
Issuing Office
Metro
Current Status
Issued on 3/18/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/11/2023 APPLICANT
Assigned to Zoning Architect 5/11/2023 NEVRIK NAVASARTIAN
Assigned to Plan Check Engineer 5/18/2023 VU NGUYEN
Corrections Issued 5/26/2023 VU NGUYEN
Quality Review Completed 6/1/2023 EUGENE BARBEAU
Plan Check Approved 3/4/2025 VU NGUYEN
Issued 3/18/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 9/19/2023 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 9/20/2023 CARLOS AGUILERA
Hydrant and Access approval Cleared 12/7/2023 LAVEON RIDER
Trees in Parkway Cleared 7/17/2024 MIGUEL ORNELAS
Bicycle Parking Cleared 7/19/2024 CARLOS AGUILERA
Highway dedication Cleared 7/19/2024 CARLOS AGUILERA
DAS Clearance Cleared 10/30/2024 VU NGUYEN
Fire Marshal Fire Life Safety Cleared 10/30/2024 MENOA AGHAJANI
Low Impact Development (LID) Cleared 11/12/2024 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 11/14/2024 CARLOS AGUILERA
Sewer availability Cleared 12/5/2024 CARLOS AGUILERA
Green Code Cleared 12/23/2024 VU NGUYEN
Density Bonus Cleared 2/6/2025 JASON WELLS
Building over 36-ft Cleared 2/12/2025 CALOSHA APPROVED
Clean Up Green Up Cleared 2/14/2025 NATHAN ROMINE
Miscellaneous Cleared 2/14/2025 NATHAN ROMINE
Miscellaneous Cleared 2/14/2025 NATHAN ROMINE
Miscellaneous Cleared 2/14/2025 NATHAN ROMINE
Miscellaneous Cleared 2/14/2025 NATHAN ROMINE
Miscellaneous Cleared 2/14/2025 NATHAN ROMINE
Miscellaneous Cleared 2/14/2025 NATHAN ROMINE
Miscellaneous Cleared 2/14/2025 NATHAN ROMINE
Opn space landscape/Water mgmt Cleared 2/14/2025 NATHAN ROMINE
Zoning Plan Check Cleared 2/24/2025 NEVRIK NAVASARTIAN
Permit Cleared 2/28/2025 CARLOS AGUILERA

Contact Information

Contractor U L Construction Inc; Lic. No.: 1026462-B       ,
Engineer Gharai,, Armin; Lic. No.: C61464 6701 CORIE LN      WEST HILLS, CA 91307
Engineer Jitechian,, Ara; Lic. No.: C54893 9433 VIA PATRICIA      BURBANK, CA 91504

Inspector Information

GREGORY POMISH, (818) 374-3303 Office Hours: 7:00-8:00 AM MON-FRI
EDWIN GREGORYONA, (818) 374-3303 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/25/2025 Not Ready for Inspection GREGORY POMISH
Pre-Inspection 4/10/2025 Partial Approval DANNY RODRIGUEZ
Pre-Inspection 4/11/2025 Approved DANNY RODRIGUEZ
Deputy Reinf. Concrete 4/28/2025 Approved DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 4/28/2025 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 4/29/2025 Approved DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 4/29/2025 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Reinf. Concrete 5/2/2025 Approved DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 5/6/2025 Corrections Issued JOHN KITCKO
Excavation/Setback/Form/Re-Bar 5/7/2025 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 5/9/2025 Conditional Approval DANNY RODRIGUEZ
Deputy Reinf. Concrete 5/20/2025 Conditional Approval JOHN KITCKO
Deputy Reinf. Concrete 5/21/2025 Approved DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 5/21/2025 Partial Inspection DANNY RODRIGUEZ
Excavation/Setback/Form/Re-Bar 5/23/2025 Partial Approval JOHN KITCKO
Deputy Other (see comments) 5/27/2025 Conditional Approval JOHN KITCKO
Deputy Reinf. Concrete 6/3/2025 Conditional Approval JOHN KITCKO
Excavation/Setback/Form/Re-Bar 6/4/2025 Partial Approval DANIEL VARNUM
Deputy Reinf. Concrete 6/5/2025 Conditional Approval ROBERT DAVIS
Deputy Reinf. Concrete 6/9/2025 Conditional Approval ANDREW DORSO
Excavation/Setback/Form/Re-Bar 6/9/2025 Partial Inspection ANDREW DORSO
Excavation/Setback/Form/Re-Bar 6/12/2025 Partial Inspection ANDREW DORSO
Deputy Reinf. Concrete 6/24/2025 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 6/24/2025 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 6/30/2025 Approved JOHN KITCKO
Excavation/Setback/Form/Re-Bar 6/30/2025 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 7/1/2025 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 7/8/2025 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 7/31/2025 Conditional Approval GREGORY POMISH
Excavation/Setback/Form/Re-Bar 7/31/2025 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 8/1/2025 Conditional Approval GREGORY POMISH
Excavation/Setback/Form/Re-Bar 8/29/2025 Partial Approval ROBERT DAVIS
Footing/Foundation/Slab 8/29/2025 Conditional Approval ROBERT DAVIS
Deputy Reinf. Concrete 9/8/2025 Conditional Approval GREGORY POMISH
Footing/Foundation/Slab 9/8/2025 Partial Approval GREGORY POMISH
Deputy Reinf. Concrete 9/9/2025 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 9/9/2025 Partial Approval GREGORY POMISH
Deputy Wood Construction 9/29/2025 Conditional Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 9/30/2025 Partial Approval GREGORY POMISH
Green Building Rough 9/30/2025 Partial Inspection GREGORY POMISH
Verify Sprinkler Sign Off 9/30/2025 Partial Inspection GREGORY POMISH
Wood Frame 9/30/2025 Partial Approval GREGORY POMISH
Deputy Wood Construction 10/14/2025 Conditional Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 10/14/2025 Not Ready for Inspection GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 10/16/2025 Partial Approval GREGORY POMISH
Deputy Wood Construction 10/24/2025 Conditional Approval ANDREW DORSO
Deputy Steel/Welding 10/27/2025 Approved JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 10/27/2025 Partial Approval JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 10/29/2025 Partial Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 11/3/2025 Partial Inspection GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 11/7/2025 Not Ready for Inspection DEANDRE HOFFMAN
Floor/Roof Diaphrgm/Shear Wall 11/14/2025 Partial Inspection JOHN KITCKO
Floor/Roof Diaphrgm/Shear Wall 12/4/2025 Partial Inspection GREGORY POMISH
Insulation 12/4/2025 Partial Approval GREGORY POMISH
Deputy Wood Construction 12/5/2025 Conditional Approval GREGORY POMISH
Drywall Nailing 12/8/2025 Partial Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 12/8/2025 Partial Approval GREGORY POMISH
Special/Order Compliance 12/8/2025 Partial Approval SCOTT SOBEL
Deputy Wood Construction 12/9/2025 Conditional Approval GREGORY POMISH
Floor/Roof Diaphrgm/Shear Wall 12/10/2025 Partial Inspection GREGORY POMISH
Insulation 12/15/2025 Partial Approval GREGORY POMISH
Deputy Wood Construction 12/18/2025 Conditional Approval GREGORY POMISH
Drywall Nailing 12/19/2025 Partial Approval GREGORY POMISH
Drywall Nailing 1/8/2026 Partial Inspection GREGORY POMISH
Insulation 1/8/2026 Partial Approval GREGORY POMISH
Wood Frame 1/16/2026 Partial Approval ROBERT DAVIS
Insulation 1/21/2026 Partial Approval GREGORY POMISH
Drywall Nailing 1/27/2026 Partial Approval GREGORY POMISH
Insulation 1/27/2026 Partial Approval GREGORY POMISH
Drywall Nailing 2/3/2026 Partial Approval GREGORY POMISH
Insulation 2/4/2026 Partial Approval GREGORY POMISH
Drywall Nailing 2/10/2026 Partial Approval GREGORY POMISH
Interior/Exterior Lathing 2/11/2026 Approved GREGORY POMISH
Drywall Nailing 2/20/2026 Partial Approval GREGORY POMISH
Light Gage Steel Frame 3/3/2026 Partial Inspection GREGORY POMISH
Special/Order Compliance 3/17/2026 Partial Inspection JOHN KITCKO
Drywall Nailing 3/20/2026 Partial Approval GREGORY POMISH
Drywall Nailing 4/8/2026 Partial Inspection GREGORY POMISH
Final 4/28/2026 Partial Inspection GREGORY POMISH
Footing/Foundation/Slab 4/28/2026 Approved GREGORY POMISH
Green Building Final 4/28/2026 Partial Inspection GREGORY POMISH
Green Building Rough 4/28/2026 Approved GREGORY POMISH
Reinforced Concrete Frame 4/28/2026 Partial Inspection GREGORY POMISH
SGSOV-Seismic Gas S/O Valve 4/28/2026 SGSOV Not Ready GREGORY POMISH
Smoke Detectors 4/28/2026 Partial Inspection GREGORY POMISH
Verify Sprinkler Sign Off 4/28/2026 Partial Inspection GREGORY POMISH
Wood Frame 4/28/2026 Partial Inspection GREGORY POMISH
Final 5/18/2026 Not Ready for Inspection EDWIN GREGORYONA
Green Building Final 5/18/2026 Not Ready for Inspection EDWIN GREGORYONA
Reinforced Concrete Frame 5/18/2026 Not Ready for Inspection EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 5/18/2026 SGSOV Not Ready EDWIN GREGORYONA
Smoke Detectors 5/18/2026 Not Ready for Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 5/18/2026 Not Ready for Inspection EDWIN GREGORYONA
Wood Frame 5/18/2026 Not Ready for Inspection EDWIN GREGORYONA
Pre-Inspection 5/19/2026 Approved EDWIN GREGORYONA
Final 6/3/2026 Partial Inspection EDWIN GREGORYONA
Green Building Final 6/3/2026 Partial Inspection EDWIN GREGORYONA
Reinforced Concrete Frame 6/3/2026 Approved EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 6/3/2026 SGSOV Not Ready EDWIN GREGORYONA
Smoke Detectors 6/3/2026 Partial Inspection EDWIN GREGORYONA
Verify Sprinkler Sign Off 6/3/2026 Approved EDWIN GREGORYONA
Wood Frame 6/3/2026 Approved EDWIN GREGORYONA
Final 6/25/2026 Partial Inspection EDWIN GREGORYONA
Green Building Final 6/25/2026 Partial Inspection EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 6/25/2026 SGSOV Not Ready EDWIN GREGORYONA
Smoke Detectors 6/25/2026 Partial Inspection EDWIN GREGORYONA
Final 7/22/2026 Conditional Approval EDWIN GREGORYONA
Green Building Final 7/22/2026 Approved EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 7/22/2026 SGSOV Approved EDWIN GREGORYONA
Smoke Detectors 7/22/2026 Approved EDWIN GREGORYONA