1527 W HILL DR 90041
Certificate Information: 1527 W HILL DR 90041
- Application / Permit
- 23010-10000-01967
- Plan Check / Job No.
- B23LA08646
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: (N) DETACHED ADU per CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 11/15/2023
- Issuing Office
- Current Status
- CofO Issued on 11/26/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/15/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/18/2023 | ALFREDO JARA |
| Corrections Issued | 5/22/2023 | ALFREDO JARA |
| Applicant returned to address corrections | 8/26/2023 | ALFREDO JARA |
| Applicant returned to address corrections | 11/7/2023 | AMY GUEVARRA |
| Plan Check Approved | 11/14/2023 | CAROLEAN BASMA |
| Issued | 11/15/2023 | APPLICANT |
| CofO in Progress | 11/19/2024 | ROY SPAULDING |
| Permit Finaled | 11/26/2024 | DEROLD HAUFF |
| CofO Issued | 11/26/2024 | DEROLD HAUFF |
| Permit Finaled | 11/26/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 5/22/2023 | ALFREDO JARA |
| Hydrant and Access approval | Cleared | 7/22/2023 | GILBERT URREA |
| Low Impact Development (LID) | Cleared | 8/7/2023 | VICTOR MENDOZA |
| Roof/Waste drainage to street | Cleared | 8/20/2023 | AHMED AMARRAGY |
| Address approval | Cleared | 9/6/2023 | AHMED AMARRAGY |
| Eng Process Fee Ord 176,300 | Cleared | 9/7/2023 | AHMED AMARRAGY |
| Sewer availability | Cleared | 9/7/2023 | AHMED AMARRAGY |
| Miscellaneous | Cleared | 9/26/2023 | ALBERT TAM |
| Construction near power lines | Cleared | 10/21/2023 | RIDWAN HARDY |
Contact Information
| Contractor | K M Builders; Lic. No.: 1080573-B | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: NA76828 | , |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/15/2023 | Corrections Issued | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 4/5/2024 | Partial Approval | CRAIG VAUGHAN |
| PLUMBING-Rough | 4/5/2024 | Partial Approval | CRAIG VAUGHAN |
| Grounding or Bonding | 4/12/2024 | Approved | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 4/25/2024 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 4/30/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 7/1/2024 | Corrections Issued | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 7/1/2024 | Approved | JOSEPH MCGARRY |
| Wood Frame | 7/1/2024 | Not Ready for Inspection | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 7/11/2024 | Partial Approval | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2024 | No Access for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 7/15/2024 | No Access for Inspection | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/23/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 7/24/2024 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2024 | No Access for Inspection | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 8/7/2024 | Corrections Issued | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 8/7/2024 | Corrections Issued | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2024 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 8/7/2024 | Corrections Issued | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 8/13/2024 | Partial Approval | CRAIG VAUGHAN |
| PLUMBING-Rough | 8/13/2024 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 8/19/2024 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 8/22/2024 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 8/22/2024 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 8/22/2024 | Partial Approval | CRAIG VAUGHAN |
| Drywall Nailing | 8/28/2024 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 8/28/2024 | Not Ready for Inspection | CRAIG VAUGHAN |
| Shower Pan | 9/12/2024 | No Access for Inspection | ROY SPAULDING |
| Shower Pan | 9/18/2024 | Approved | ROY SPAULDING |
| Interior/Exterior Lathing | 9/23/2024 | Approved | ROY SPAULDING |
| Final | 11/4/2024 | Corrections Issued | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 11/4/2024 | SGSOV Approved | ROY SPAULDING |
| Service/Power Release | 11/4/2024 | Not Ready for Inspection | ROY SPAULDING |
| Smoke Detectors | 11/4/2024 | Approved | ROY SPAULDING |
| Final | 11/13/2024 | OK to Issue CofO | ROY SPAULDING |
| Service/Power Release | 11/13/2024 | Approved | ROY SPAULDING |