1485 W 47TH ST 90062

Certificate Information: 1485 W 47TH ST 90062

Application / Permit
23010-10000-01954
Plan Check / Job No.
B23LA08613
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New ADU PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g). Framing to comply with WFPP.
Permit Issued
Issued on 7/11/2023
Issuing Office
South Los Angeles
Current Status
CofO Issued on 1/30/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/9/2023 APPLICANT
Assigned to Plan Check Engineer 5/15/2023 JOSEPH RAFOLS
Corrections Issued 5/16/2023 JOSEPH RAFOLS
Building Plans Picked Up 5/17/2023 APPLICANT
Issued 7/11/2023 APPLICANT
CofO in Progress 1/23/2024 ALIZAH MAYAGOITIA
Permit Finaled 1/30/2024 DEROLD HAUFF
CofO Issued 1/30/2024 DEROLD HAUFF
Permit Finaled 1/30/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/1/2023 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 6/1/2023 ADRIAN SANCHEZ
Roof/Waste drainage to street Cleared 6/1/2023 ADRIAN SANCHEZ
Sewer availability Cleared 6/1/2023 ADRIAN SANCHEZ
Low Impact Development (LID) Cleared 7/5/2023 LUIS LUVANO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 7/17/2023 Partial Approval BRENDAN MORELLI
Footing/Foundation/Slab 7/24/2023 Approved STUART CHAPMAN
ELECTRICAL-Rough 8/24/2023 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 8/24/2023 Approved SABAS ALONSO
Green Building Rough 8/24/2023 Approved SABAS ALONSO
PLUMBING-Rough 8/24/2023 Approved SABAS ALONSO
BUILDING-Rough-Frame 8/30/2023 Approved SABAS ALONSO
HVAC-Rough 8/30/2023 Approved SABAS ALONSO
Verify Sprinkler Sign Off 8/30/2023 Approved SABAS ALONSO
Insulation 9/6/2023 Approved JOSH MEISTER
Interior/Exterior Lathing 9/6/2023 Approved JOSH MEISTER
Drywall Nailing 9/11/2023 Corrections Issued MICHAEL LEWIS
Interior/Exterior Lathing 9/11/2023 Approved MICHAEL LEWIS
Drywall Nailing 9/14/2023 Approved SABAS ALONSO
Interior/Exterior Lathing 9/14/2023 Corrections Issued SABAS ALONSO
Interior/Exterior Lathing 9/18/2023 Approved SABAS ALONSO
ELECTRICAL-Final 12/29/2023 Corrections Issued ALEJANDRO DE ARTOLA
Service/Power Release 12/29/2023 Corrections Issued ALEJANDRO DE ARTOLA
Smoke Detectors 12/29/2023 Approved ALEJANDRO DE ARTOLA
Final 1/16/2024 Partial Approval ALIZAH MAYAGOITIA
Green Building Final 1/16/2024 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 1/16/2024 SGSOV Not Required ALIZAH MAYAGOITIA
Service/Power Release 1/16/2024 Approved ALIZAH MAYAGOITIA
Final 1/23/2024 OK to Issue CofO ALIZAH MAYAGOITIA