2709-2709 1/2 S GRIFFITH AVE 90011

Certificate Information: 2709-2709 1/2 S GRIFFITH AVE 90011

Application / Permit
23010-10000-01940
Plan Check / Job No.
B23LA08528
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(2) Accessory Dwelling Unit Building per GCS 65852.2(e)(1)(D) and applicable part of LAMC 12.22 A.33(c)-(d), (g). All work per engineered plans. (NFPA 13D FIRE SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 9/22/2023
Issuing Office
Metro
Current Status
CofO Issued on 7/24/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/8/2023 APPLICANT
Assigned to Plan Check Engineer 5/11/2023 MICHAEL LANZONE
Corrections Issued 5/11/2023 MICHAEL LANZONE
Building Plans Picked Up 5/17/2023 APPLICANT
Plan Check Approved 8/22/2023 GEORGE ALVAREZ
Issued 9/22/2023 APPLICANT
CofO in Progress 7/15/2024 ALEJANDRO DE ARTOLA
CofO Issued 7/24/2024 DEROLD HAUFF
Permit Finaled 7/24/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/31/2023 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 6/2/2023 TREVOR QUAN
Sewer availability Cleared 6/2/2023 TREVOR QUAN
Low Impact Development (LID) Cleared 7/19/2023 LUIS LUVANO
Construction near power lines Cleared 8/14/2023 RIDWAN HARDY
Roof/Waste drainage to street Cleared 8/17/2023 TREVOR QUAN

Contact Information

Contractor Owner-Builder       ,
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/27/2023 Partial Approval ALEJANDRO DE ARTOLA
Underground Mechanical 9/27/2023 Approved ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 10/6/2023 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 10/24/2023 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 10/26/2023 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 11/28/2023 Corrections Issued ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 11/28/2023 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 11/29/2023 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 11/29/2023 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 11/29/2023 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 11/29/2023 Approved ALEJANDRO DE ARTOLA
Green Building Rough 11/30/2023 Approved ALEJANDRO DE ARTOLA
Insulation 11/30/2023 Corrections Issued ALEJANDRO DE ARTOLA
Verify Sprinkler Sign Off 11/30/2023 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 12/5/2023 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 12/5/2023 Approved ALEJANDRO DE ARTOLA
Insulation 12/5/2023 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 12/11/2023 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 12/11/2023 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 4/23/2024 Corrections Issued ALEJANDRO DE ARTOLA
Final 4/23/2024 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 4/23/2024 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 4/23/2024 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 4/23/2024 SGSOV Not Ready ALEJANDRO DE ARTOLA
Smoke Detectors 4/23/2024 Approved ALEJANDRO DE ARTOLA
HVAC-Final 4/25/2024 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 4/25/2024 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 4/26/2024 Corrections Issued ALEJANDRO DE ARTOLA
Final 4/26/2024 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 4/26/2024 Approved ALEJANDRO DE ARTOLA
Green Building Final 4/26/2024 Approved ALEJANDRO DE ARTOLA
HVAC-Final 4/26/2024 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 4/26/2024 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 4/26/2024 SGSOV Not Required ALEJANDRO DE ARTOLA
Service/Power Release 4/26/2024 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 4/30/2024 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 4/30/2024 Approved ALEJANDRO DE ARTOLA
Service/Power Release 4/30/2024 Corrections Issued ALEJANDRO DE ARTOLA
Service/Power Release 7/10/2024 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 7/12/2024 Approved ALEJANDRO DE ARTOLA
Final 7/12/2024 OK to Issue CofO ALEJANDRO DE ARTOLA
Service/Power Release 7/12/2024 Approved ALEJANDRO DE ARTOLA