1515 W 190TH ST 90248

Certificate Information: 1515 W 190TH ST 90248

Application / Permit
23010-10000-01915
Plan Check / Job No.
B23LA08432
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(22) Warehouse
Work Description
ePlan: New 1 story, 45' high, Type IIIB, warehouse / distribution center facility per 507- min 60' open space around the building.
Permit Issued
Issued on 10/9/2025
Issuing Office
Metro
Current Status
Issued on 10/9/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/8/2023 APPLICANT
Assigned to Plan Check Engineer 5/25/2023 KESETE HAREGOT
Corrections Issued 6/20/2023 KESETE HAREGOT
Quality Review Completed 6/23/2023 RODOLFO ARIAS
Applicant returned to address corrections 1/2/2024 KESETE HAREGOT
Applicant returned to address corrections 6/24/2024 KESETE HAREGOT
Applicant returned to address corrections 7/11/2024 KESETE HAREGOT
Applicant returned to address corrections 7/19/2024 KESETE HAREGOT
Plan Check Approved 8/13/2025 KESETE HAREGOT
Plan Check Approved 9/8/2025 KESETE HAREGOT
Plan Check Approved 9/10/2025 KESETE HAREGOT
Issued 10/9/2025 APPLICANT

Permit Application Clearance Information

Construction within easement Cleared 6/14/2023 TINA MIRANDA
Address approval Cleared 10/30/2023 JILVER MAZARIEGOS
Miscellaneous Cleared 11/1/2023 NOAH MCCOY
Prkng lot landscape/Water mgmt Cleared 11/1/2023 NOAH MCCOY
Site Plan review Cleared 11/1/2023 NOAH MCCOY
Encroachment in public way Cleared 12/7/2023 JILVER MAZARIEGOS
Building over 36-ft Cleared 1/11/2024 CALOSHA APPROVED
Sewer availability Cleared 1/11/2024 KHAING AYE
Eng Process Fee Ord 176,300 Cleared 1/22/2024 KHAING AYE
Miscellaneous Cleared 2/7/2024 JILVER MAZARIEGOS
Trees in Parkway Cleared 2/7/2024 ADALBERTO VERA
Highway dedication Cleared 2/20/2024 JILVER MAZARIEGOS
DAS Clearance Cleared 4/9/2024 Ricardo Ramirez Solis
Hydrant and Access approval Cleared 4/15/2024 KURT CORRAL
Low Impact Development (LID) Cleared 4/15/2024 ANDRES COVARRUBIAS
Driveway location Cleared 4/24/2024 MOHAMMAD HASAN
Internal circulation Cleared 4/24/2024 MOHAMMAD HASAN
Roof/Waste drainage to street Cleared 5/1/2024 STEVEN JIN
Permit Cleared 5/6/2024 ERIK BEASLEY
Green Code Cleared 6/2/2024 Ricardo Ramirez Solis

Contact Information

Architect Nouizi,, Ilyes M; Lic. No.: C32135 14252 CULVER DRIVE SUITE A-605      IRVINE, CA 92604
Contractor Norm Wilson & Sons Inc; Lic. No.: 435700-B 3400 EAST SPRING STREET      LONG BEACH, CA 908062430
Engineer Gerges,, Rafik; Lic. No.: S5092 301 N LAKE AVE.   SUITE 500    PASADENA, CA 91101
Geologist Feffer,, Joshua R; Lic. No.: EG2138 12253 GORHAM AVE      LOS ANGELES, CA 90049
Landscape Architect Nolan,, Colleen M; Lic. No.: LA5439 13355 SILVERADO CT      CORONA, CA 92883

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/10/2025 Partial Approval RICARDO ROBLES
Footing/Foundation/Slab 1/15/2026 Partial Approval RICARDO ROBLES
Pre-Inspection 1/15/2026 Partial Approval ROGELIO REYNA
Deputy Reinf. Concrete 1/20/2026 Conditional Approval RICARDO ROBLES
Deputy Reinf. Concrete 1/23/2026 Conditional Approval DAVID TSAU
Footing/Foundation/Slab 1/26/2026 Partial Approval DAVID TSAU
Pre-Inspection 1/27/2026 Partial Approval DAVID TSAU
Pre-Inspection 1/29/2026 Partial Approval DAVID TSAU
Deputy Reinf. Concrete 2/2/2026 Approved DAVID TSAU
Footing/Foundation/Slab 2/2/2026 Partial Approval DAVID TSAU
Pre-Inspection 2/2/2026 Partial Approval MICHAEL PETRUSKO
Deputy Other (see comments) 2/3/2026 Conditional Approval DAVID TSAU
Deputy Reinf. Concrete 2/3/2026 Conditional Approval DAVID TSAU
Footing/Foundation/Slab 2/4/2026 Partial Approval DAVID TSAU
Deputy Reinf. Concrete 2/5/2026 Conditional Approval DAVID TSAU
Footing/Foundation/Slab 2/10/2026 Partial Inspection DAVID TSAU
Excavation/Setback/Form/Re-Bar 2/11/2026 No Access for Inspection DAVID TSAU
Deputy Other (see comments) 2/20/2026 Conditional Approval DAVID TSAU
Footing/Foundation/Slab 2/24/2026 Partial Inspection DAVID TSAU
Deputy Reinf. Concrete 2/25/2026 Conditional Approval DAVID TSAU
Footing/Foundation/Slab 2/26/2026 Partial Approval DAVID TSAU
Deputy Reinf. Concrete 3/2/2026 Approved DAVID TSAU
Footing/Foundation/Slab 3/2/2026 Partial Approval DAVID TSAU
Deputy Reinf. Concrete 3/3/2026 Conditional Approval DAVID TSAU
Deputy Reinf. Concrete 3/4/2026 Conditional Approval MICHAEL PETRUSKO
Deputy Reinf. Concrete 3/6/2026 Conditional Approval MICHAEL PETRUSKO
Deputy Reinf. Concrete 3/9/2026 Conditional Approval MICHAEL PETRUSKO
Footing/Foundation/Slab 3/10/2026 Partial Approval MICHAEL PETRUSKO
Deputy Reinf. Concrete 3/11/2026 Approved DAVID TSAU
Excavation/Setback/Form/Re-Bar 3/11/2026 Partial Approval DAVID TSAU
Deputy Reinf. Concrete 3/16/2026 Approved DAVID TSAU
Green Building Rough 3/17/2026 Conditional Approval DAVID TSAU
Reinforced Concrete Frame 3/17/2026 Partial Inspection DAVID TSAU
Verify Sprinkler Sign Off 3/17/2026 Conditional Approval DAVID TSAU
Deputy Reinf. Concrete 3/19/2026 Conditional Approval DAVID TSAU
Deputy Reinf. Concrete 3/24/2026 Conditional Approval DAVID TSAU
Deputy Reinf. Concrete 3/25/2026 Approved DAVID TSAU
Wood Frame 3/25/2026 Partial Inspection DAVID TSAU
Special/Order Compliance 3/27/2026 Conditional Approval MICHAEL PETRUSKO
Special/Order Compliance 4/1/2026 No Access for Inspection MICHAEL PETRUSKO
Footing/Foundation/Slab 4/2/2026 Partial Approval DAVID TSAU
Wood Frame 4/2/2026 Not Ready for Inspection DAVID TSAU
Deputy Reinf. Concrete 4/3/2026 Conditional Approval DAVID TSAU
Deputy Steel/Welding 4/3/2026 Conditional Approval DAVID TSAU
Footing/Foundation/Slab 4/3/2026 Partial Approval DAVID TSAU
Special/Order Compliance 4/3/2026 Conditional Approval MICHAEL PETRUSKO
Green Building Rough 4/7/2026 Not Ready for Inspection DAVID TSAU
Reinforced Concrete Frame 4/7/2026 Not Ready for Inspection DAVID TSAU
Verify Sprinkler Sign Off 4/7/2026 Not Ready for Inspection DAVID TSAU
Green Building Rough 4/8/2026 Approved MICHAEL PETRUSKO
Reinforced Concrete Frame 4/8/2026 Partial Approval MICHAEL PETRUSKO
Verify Sprinkler Sign Off 4/8/2026 Approved MICHAEL PETRUSKO
Deputy Steel/Welding 4/9/2026 Conditional Approval MICHAEL PETRUSKO
Special/Order Compliance 4/15/2026 Partial Approval MICHAEL PETRUSKO
Deputy Reinf. Concrete 4/17/2026 Approved DAVID TSAU
Footing/Foundation/Slab 4/17/2026 Partial Inspection DAVID TSAU
Special/Order Compliance 4/20/2026 Partial Inspection MICHAEL PETRUSKO
Deputy Reinf. Concrete 4/27/2026 Conditional Approval MICHAEL PETRUSKO
Deputy Steel/Welding 4/27/2026 Conditional Approval MICHAEL PETRUSKO
Footing/Foundation/Slab 4/27/2026 Approved MICHAEL PETRUSKO
Structural Steel Frame 5/8/2026 Partial Inspection DAVID TSAU
Special/Order Compliance 5/11/2026 Not Ready for Inspection MICHAEL PETRUSKO
Special/Order Compliance 5/14/2026 Conditional Approval MICHAEL PETRUSKO
Structural Steel Frame 5/18/2026 Partial Inspection DAVID TSAU
Deputy Reinf. Concrete 5/20/2026 Approved MICHAEL PETRUSKO
Deputy Steel/Welding 5/20/2026 Approved MICHAEL PETRUSKO
Special/Order Compliance 5/26/2026 Partial Inspection MICHAEL PETRUSKO
Deputy Steel/Welding 5/27/2026 Conditional Approval DAVID TSAU
Reinforced Concrete Frame 5/28/2026 Partial Approval DAVID TSAU
Floor/Roof Diaphrgm/Shear Wall 6/1/2026 Partial Approval DAVID TSAU
Special/Order Compliance 6/5/2026 Conditional Approval MICHAEL PETRUSKO