4624-4626 S COOLIDGE AVE 90230
Certificate Information: 4624-4626 S COOLIDGE AVE 90230
- Application / Permit
- 23010-10000-01906
- Plan Check / Job No.
- B23LA08387
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Junior Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERT WORKSHOP/STORAGE INTO A (N) IRREGULAR SHAPED 36'-0" x 19'-7" JUNIOR ACCESSORY DWELLING UNIT TO COMPLY WITH 65852.2(e)(1)(A) AND 65852.22. SEE COMMENTS
- Permit Issued
- Issued on 10/13/2023
- Issuing Office
- Current Status
- CofO Issued on 1/30/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/8/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/8/2023 | ALFRED RAMIREZ |
| Corrections Issued | 5/9/2023 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 5/23/2023 | ALFRED RAMIREZ |
| Plan Check Approved | 10/13/2023 | ALFRED RAMIREZ |
| Issued | 10/13/2023 | APPLICANT |
| CofO in Progress | 1/19/2024 | JESUS RODRIGUEZ |
| Permit Finaled | 1/30/2024 | DANIEL ORRANTE |
| CofO Issued | 1/30/2024 | DANIEL ORRANTE |
| Permit Finaled | 1/30/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 5/11/2023 | DARIN LAM |
| Sewer availability | Cleared | 5/11/2023 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 5/12/2023 | DARIN LAM |
| Specific Plan | Cleared | 5/16/2023 | JOSHUA JONES |
Contact Information
| Contractor | H C L Group Inc; Lic. No.: 1052561-B | , |
| Contractor | Hcl Group Inc; Lic. No.: 1052561-B | , |
| Engineer | Askarian,, Soroosh; Lic. No.: C83413 | 22287 MULHOLLAND HWY 163 CALABASAS, CA 91302 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 10/20/2023 | Corrections Issued | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 10/20/2023 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2023 | Approved | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 10/20/2023 | Approved | JESUS RODRIGUEZ |
| MERV13>=Rough | 10/20/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 10/20/2023 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 11/9/2023 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 11/9/2023 | Approved | JESUS RODRIGUEZ |
| Insulation | 11/9/2023 | Approved | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 11/9/2023 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 1/12/2024 | Corrections Issued | HERBERT GIRON |
| Final | 1/12/2024 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 1/12/2024 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 1/12/2024 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 1/12/2024 | SGSOV Approved | HERBERT GIRON |
| Smoke Detectors | 1/12/2024 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 1/18/2024 | Approved | JESUS RODRIGUEZ |
| Final | 1/18/2024 | OK to Issue CofO | JESUS RODRIGUEZ |
| HVAC-Final | 1/18/2024 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 1/18/2024 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 1/18/2024 | SGSOV Approved | JESUS RODRIGUEZ |
| Service/Power Release | 1/18/2024 | Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 1/18/2024 | Approved | JESUS RODRIGUEZ |